Install mobile generation set for synchronised HV Genset

Version 1.0
Issue Date: April 2024


Qualification -
Unit of Competency UETTDRIS64A - Install mobile generation set for synchronised HV Genset
Description 1)Scope:1.1) DescriptorThis Competency Standard Unit covers installation of temporary portable generation sets to HV distribution assets thereby maintaining supply in accordance with industry regulations and established procedures. It encompasses the operation, connection and disconnection of a temporary portable generator and includes the estimation of HV load and assessing the appropriateness of the generator for the required outcome and networking of generators.
Employability Skills 5) The required outcomes described in this unit of competency contain applicable facets of Employability Skills. The Employability Skills Summary of the qualification in which this unit of competency is packaged will assist in identifying Employability Skill requirements.
Learning Outcomes and Application 2)This Competency Standard Unit is intended to augment formally acquired competencies. It is suitable for employment-based programs under an approved contract of training.
Duration and Setting X weeks, nominally xx hours, delivered in a classroom/online/blended learning setting.
Prerequisites/co-requisites Prerequisite Unit(s)4) Competencies4.1)Granting of competency in this unit shall be made only after competency in the following unit(s) has/have been confirmed.Where pre-requisite pathways have been identified. All competencies in the Common Unit Group must be have been completed plus all the competencies in one (1) of the identified Pathway Unit Group(s):Transmission OverheadDistribution OverheadRail TractionDistribution Cable JointingElectricalCommon Unit GroupUnit CodeUnit TitleUEENEEE101A Apply Occupational Health and Safety regulations, codes and practices in the workplaceUEENEEE102A Fabricate, assemble and dismantle utilities industry componentsUEENEEE104A Solve problems in d.c. CircuitsUEENEEE105A Fix and secure electrotechnology equipmentUEENEEE107A Use drawings, diagrams, schedules, standards, codes and specificationsUEENEEG101A Solve problems in electromagnetic devices and related circuitsUEENEEG102A Solve problems in low voltage a.c. CircuitsUETTDREL16A Working safely near live electrical apparatus Transmission Overhead Pathway Group Unit CodeUnit TitleUETTDREL11A Apply sustainable energy and environmental procedures UETTDREL12A Operate plant and equipment near live electrical conductors and apparatus UETTDRIS44A Perform HV field switching operation to a given scheduleUETTDRIS54A Install and maintain poles, structures, overhead conductors and cables UETTDRTP26A Install transmission structures and associated hardware UETTDRTP27A Maintain transmission structures and associated hardware UETTDRTP29A Install and maintain transmission overhead conductors and cables Distribution Overhead Pathway GroupUnit CodeUnit TitleUETTDREL11A Apply sustainable energy and environmental procedures UETTDRDP12A Maintain overhead energised low voltage conductors and cables UETTDREL12A Operate plant and equipment near live electrical conductors and apparatus UETTDRIS41A Install network infrastructure electrical equipment UETTDRIS42A Maintain network infrastructure electrical equipment UETTDRIS43A Perform low voltage field switching operation to a given schedule.UETTDRIS52A Install and maintain poles, structures and associated hardwareUETTDRIS54A Install and maintain poles, structures, overhead conductors and cables UETTDRIS56A Install and maintain low voltage overhead services Rail Traction Pathway GroupUnit CodeUnit TitleUETTDREL11A Apply sustainable energy and environmental procedures UETTDREL12A Operate plant and equipment near live electrical conductors and apparatus UETTDRIS52A Install and maintain poles, structures and associated hardwareUETTDRIS54A Install and maintain poles, structures, overhead conductors and cables UETTDRRT21A Install traction overhead wiring systems UETTDRRT22A Maintain traction overhead wiring systems UETTDRRT23A Install rail traction bonds UETTDRRT27A Install overhead traction components and equipment UETTDRRT28A Maintain overhead traction components and equipment UETTDRRT30A Perform to a given schedule rail traction switching operationsDistribution Cable Jointing Pathway GroupUnit CodeUnit TitleUETTDRCJ21A Lay ESI electrical cables UETTDRCJ26A Install and maintain de-energised low voltage underground polymeric cables. UETTDRCJ27A Install and maintain de-energised high voltage underground polymeric cables. UETTDREL11A Apply sustainable energy and environmental procedures UETTDREL12A Operate plant and equipment near live electrical conductors and apparatus UETTDRIS41A Install network infrastructure electrical equipment UETTDRIS42A Maintain network infrastructure electrical equipment UETTDRIS43A Perform low voltage field switching operation to a given schedule.UETTDRIS55A Install and maintain low voltage underground services Electrical Pathway GroupUnit CodeUnit TitleUEENEEE137A Document and apply measures to control OHS risks associated with electrotechnology workUEENEEG006A Solve problems in single and three phase low voltage machinesUEENEEG033A Solve problems in single and three phase electrical apparatus and circuitsUEENEEG063A Arrange circuits, control and protection for general electrical installationsUEENEEG106A Terminate cables, cords and accessories for low voltage circuitsUEENEEG108A Trouble-shoot and repair faults in low voltage electrical apparatus and circuitsUEENEEG109A Develop and connect electrical control circuitsUEENEEK142A Apply environmentally and sustainable energy procedures in the energy sectorUETTDRIS67A Solve problems in energy supply network equipmentUETTDRSB39A Perform power system substation switching operation to a given scheduleLiteracy and numeracy skills4.2) Participants are best equipped to achieve this unit if they have reading, writing and numeracy skills indicated by the following scales. Description of each scale is given in Volume 2, Part 3 “Literacy and Numeracy”Reading4Writing4Numeracy4
Competency Field
Development and validation strategy and guide for assessors and learners Student Learning Resources Handouts
Activities
Slides
PPT
Assessment 1 Assessment 2 Assessment 3 Assessment 4
Elements of Competency Performance Criteria              
Element: Prepare/plan to install mobile generation set for synchronised genset HV
  • Works schedule(s), including drawings, plans, requirements, established procedures, and material lists, are obtained, analysed, if necessary, by site inspection and the extent of the preparation of the work determined for planning and coordination.
  • Work is prioritised and sequenced for the most efficient and effective outcome following consultation with others for completion within acceptable timeframes, to a quality standard and in accordance with established procedures.
  • Hazards are identified, OHS risks assessed and control measures are prioritised, implemented and monitored including emergency exits kept clear according to established procedures.
  • Relevant requirements and established procedures for the work are to all personnel and identified for all work sites.
  • OHS policies and procedures related to the work are identified to ensure safe systems of work are followed.
  • Relevant work permits are secured to coordinate the performance of work according to requirements and/or established procedures.
  • Resources including personnel, equipment, tools and personal protective equipment required for the job are identified, scheduled and coordinated and confirmed in a safe and technical working order.
  • Clients/customers are provided with possible solutions and/or options within the scope, acceptable cost and requirements.
  • Liaison and communication issues with other/authorised personnel, authorities, clients and land owners are resolved and activities coordinated to carry out work.
  • Personnel participating in the work, including plant operators and contractors, are fully briefed and respective responsibilities coordinated and authorised where applicable in accordance with established procedures.
  • Site is prepared according to the work schedule and to minimise risk and damage to property, commerce, and individuals in accordance with established procedures.
  • Positioning of road signs, barriers and warning devices is planned and coordinated in accordance with requirements.
       
Element: Carry out the installation of mobile generation set for synchronised genset HV
  • OHS and sustainable energy principles and practices to reduce the incidents of accidents and minimise waste are monitored and actioned in accordance with requirements and/or established procedures.
  • First Aid and other related work procedures are performed according to requirements and/or established procedures.
  • Lifting, climbing, working in confined spaces and aloft, and use of power tools/equipment, techniques and practices are safely exercised according to requirements.
  • Hazard warnings and safety signs are recognised and hazards and assessed OHS risks are reported to the immediate authorised persons for directions according to established procedures.
  • Remedial actions are taken to overcome any shortfalls encountered in the work schedule according to requirements and/or established procedures.
  • Installation of mobile generation set for synchronised genset HV is carried out, in accordance with the work schedule and requirements and/or established procedures.
  • Essential knowledge and associated skills are applied in the safe installation of mobile generation set for synchronised genset HV to ensure completion in an agreed timeframe and, to quality standards with a minimum of waste according to requirements.
  • Solutions to non-routine problems are identified and actioned using acquired essential knowledge and associated skills according to requirements.
  • Ongoing checks of quality of the work are undertaken in accordance with requirements and established procedures to ensure a quality like outcome is achieved for the client/customer and to a community/industry standard.
       
Element: Complete the installation of mobile generation set for synchronised genset HV
  • Work undertaken is checked against works schedule for conformance with requirements, anomalies reported and solutions identified in accordance with established procedures.
  • Accidents and/or injuries are reported and followed up in accordance with requirements/established procedures.
  • Work site is rehabilitated, cleaned up and confirmed safe in accordance with established procedures.
  • Tools, equipment and any surplus resources and materials are, where appropriate, cleaned, checked and returned to storage in accordance with established procedures.
  • Relevant work permit(s) are signed off and, synchronised genset HV apparatus is returned to service and advised to client/customer in accordance with requirements.
  • Works completion records, reports, as installed /modified drawing(s) and/or documentation and information are confirmed, processed and appropriate personnel notified.
       


Evidence Required

List the assessment methods to be used and the context and resources required for assessment. Copy and paste the relevant sections from the evidence guide below and then re-write these in plain English.

9) This provides essential advice for assessment of the unit of competency and must be read in conjunction with the Performance Criteria and the range statement of the unit of competency and the Training Package Assessment Guidelines.

The Evidence Guide forms an integral part of this Competency Standard Unit and shall be used in conjunction with all component parts of this unit and, performed in accordance with the Assessment Guidelines of this Training Package.

Overview of Assessment

9.1)

Longitudinal competency development approaches to assessment, such as Profiling, require data to be reliably gathered in a form that can be consistently interpreted over time. This approach is best utilised in Apprenticeship programs and reduces assessment intervention. It is the Industry’s preferred model for apprenticeships. However, where summative (or final) assessment is used it is to include the application of the competency in the normal work environment or, at a minimum, the application of the competency in a realistically simulated work environment. It is recognised that, in some circumstances, assessment in part or full can occur outside the workplace. However, it must be in accord with Industry and, Regulatory policy in this regard.

Methods chosen for a particular assessment will be influenced by various factors. These include the extent of the assessment, the most effective locations for the assessment activities to take place, access to physical resources, additional safety measures that may be required and the critical nature of the competencies being assessed.

The critical safety nature of working with electricity, electrical equipment, gas or any other hazardous substance/material carries risk in deeming a person competent. Hence, sources of evidence need to be ‘rich’ in nature so as to minimise error in judgment.

Activities associated with normal every day work have a bearing on the decision as to how much and how detailed the data gathered will contribute to its ‘richness’. Some skills are more critical to safety and operational requirements while the same skills may be more or less frequently practiced. These points are raised for the assessors to consider when choosing an assessment method and developing assessment instruments. Sample assessment instruments are included for Assessors in the Assessment Guidelines of this Training Package.

Critical aspects of evidence required to demonstrate competency in this unit

9.2)

Before the critical aspects of evidence are considered all prerequisites shall be met.

Evidence for competence in this unit shall be considered holistically. Each element and associated Performance Criteria shall be demonstrated on at least two occasions in accordance with the “Assessment Guidelines – UET12”. Evidence shall also comprise:

A representative body of Performance Criteria demonstrated within the timeframes typically expected of the discipline, work function and industrial environment. In particular this shall incorporate evidence that shows a candidate is able to:

Implement Occupational Health and Safety workplace procedures and practices including the use of risk control measures as specified in the Performance Criteria and range; and

Apply sustainable energy principles and practices as specified in the Performance Criteria and range; and

Demonstrate an understanding of the essential knowledge and associated skills as described in this unit to such an extent that the learner’s performance outcome is reported in accordance with the preferred approach; namely a percentile graded result, where required by the regulated environment; and

Demonstrate an appropriate level of employability skills; and

Conduct work observing the relevant Anti Discrimination legislation, regulations, policies and workplace procedures; and

Demonstrated performance across a representative range of contexts from the prescribed items below:

Range of tools/equipment/materials/procedures/workplaces/other variables

Group No

The minimum number of items on which skill is to be demonstrated

Item List

A

All of the following:

Autonomous installation of a mobile generator set for synchronised genset HV incorporating operation, connection and disconnection of the generator

Evaluating load characteristics associated with networking of generators.

Synchronisation of the generator control systems onto and off the network without interruption to supply.

Estimation of HV load and assessing the appropriateness of the generator

Operating a generator in parallel to a single HV job

B

At least one occasion

Dealing with an unplanned event by drawing on essential knowledge and associated skills to provide appropriate solutions incorporated in the holistic assessment with the above listed items.

Context of and specific resources for assessment

9.3)

This unit should be assessed as it relates to normal work practice using procedures, information and resources typical of a workplace. This should include:

OHS policy and work procedures and instructions.

Suitable work environment, facilities, equipment and materials to undertake actual installation of mobile generation set for synchronised genset HV

In addition to the resources listed above, in Context of and specific resources for assessment, evidence should show demonstrated competency working at realistic heights above ground i.e. above 3 metres, in limited spaces, with different structural/construction types and method and in a variety of environments.

Method of assessment

9.4)

This Competency Standard Unit shall be assessed by methods given in Volume 1, Part 3 “Assessment Guidelines”.

Note:

Competent performance with inherent safe working practices is expected in the Industry to which this Competency Standard Unit applies. This requires that the specified essential knowledge and associated skills are assessed in a structured environment which is primarily intended for learning/assessment and incorporates all necessary equipment and facilities for learners to develop and demonstrate the essential knowledge and associated skills described in this unit.

Concurrent assessment and relationship with other units

9.5)

There are no concurrent assessment recommendations for this unit.


Submission Requirements

List each assessment task's title, type (eg project, observation/demonstration, essay, assignment, checklist) and due date here

Assessment task 1: [title]      Due date:

(add new lines for each of the assessment tasks)


Assessment Tasks

Copy and paste from the following data to produce each assessment task. Write these in plain English and spell out how, when and where the task is to be carried out, under what conditions, and what resources are needed. Include guidelines about how well the candidate has to perform a task for it to be judged satisfactory.

8) Essential Knowledge and Associated Skills (EKAS): This describes the essential skills and knowledge and their level, required for this unit.

Evidence shall show that knowledge has been acquired of installing mobile generation set for synchronised genset HV.

All knowledge and skills detailed in this unit should be contextualised to current industry practices and technologies.

KS01-TIS64A HV mobile generation set installation

Evidence shall show an understanding of the installation of mobile generation set for synchronised with HV supplies to an extent indicated by the following aspects:

T1 Installation of a HV mobile generation encompassing:

Safety precautions specific to installing mobile generators - safe working policies, practices and procedures, techniques in connecting, operating and disconnecting generators, types of tools and equipment, safe use of tools and equipment.

Techniques in the installation of generator sets - the connection of generator onto and off the network without interruption to supply, estimation of HV load.

Assessing the appropriateness of the generator

T2 HV generator control systems encompassing:

Legislation, Standards, codes, legislation, supply authority regulations and or enterprise requirements pertaining to the operation of a portable generator.

Safety precautions specific to the synchronisation of generator sets - safe working policies, practices and procedures, synchronising procedures.

Techniques in the installation of generator sets control systems - the synchronising of generator control systems onto and off the network without interruption to supply, estimation of HV load, assessing the appropriateness of the generator.

Operating a generator in parallel to a single HV job - overhead systems, indoor systems, customer installations, kiosk substations.

HV generator set and control system to HV distribution assets

T3 Powerline safety practices encompassing:

Protective apparatus and apparel for linework - responsibilities for the selection, use, maintenance and storage of protective apparatus and apparel and the types of protective apparatus and apparel used for the line worker

Requirements for the use of ladders - carrying, erecting, collapsing and lowering different types of extension ladder against a standing pole, maintenance checks on different types of ladders, renewal of extension ropes and the safety issues relating to clearances from overhead conductors

Requirements for climbing and working aloft - methods used to identify a pole is safe to climb, methods used to inspect a line worker’s body belt, application of knots and hitches appropriate to the requirements of a line worker, height safety principles including personal fall protection, prevention and related requirements, and the practical procedure of climbing an overhead structure and fitting a pole chair

Traffic management - purpose of traffic management and a line worker’s responsibilities in accordance with relevant statutory requirements and electricity supply industry requirements, demonstration of the procedure used to provide an effective traffic management scheme and the use of a two-way radio

Control of small fires - identification, selection and operation of the appropriate extinguishing mediums for various types of fires, general fire prevention methods and the precautions for personal protection when fighting small fires

Rescue victims from heights and confined spaces - planning, identifying, the procedures, and establishing responses, developing techniques, involvement of external emergency services and practical demonstration/rehearsals of rescuing a person from heights and from confined spaces and emergency procedures for the rescue of an electric shock victim including CPR

Requirements for aerial linework - planning, establishing and implementing relevant aviation authority clearances, determining system requirements, aircrew familiarisation with network operations and equipment, requirements for effective communications operations for aerial work.

10) This relates to the unit of competency as a whole providing the range of contexts and conditions to which the Performance Criteria apply. It allows for different work environments and situations that will affect performance.

This Competency Standard Unit shall be demonstrated in relation to the installation of mobile generation set for synchronised genset HV and may include overhead systems, indoor systems, customer installations, Kiosk Substations, HV genset and control system associated with loads for networking generator sets.

The following constants and variables included in the element/Performance Criteria in this unit are fully described in the Definitions Section 1 of this volume and form an integral part of the Range Statement of this unit:

Appropriate and relevant persons (see Personnel)

Appropriate authorities

Appropriate work platform

Assessing risk

Assessment

Authorisation

Confined space

Diagnostic, testing and restoration

Documenting detail work events, record keeping and or storage of information

Drawings and specifications

Emergency

Environmental and sustainable energy procedures

Environmental legislation

Environmental management documentation

Established procedures

Fall prevention

Hazards

Identifying hazards

Inspect

Legislation

MSDS

Notification

OHS practices

OHS issues

Permits and/or permits to work

Personnel

Quality assurance systems

Requirements

Testing procedures

Work clearance systems

Copy and paste from the following performance criteria to create an observation checklist for each task. When you have finished writing your assessment tool every one of these must have been addressed, preferably several times in a variety of contexts. To ensure this occurs download the assessment matrix for the unit; enter each assessment task as a column header and place check marks against each performance criteria that task addresses.

Observation Checklist

Tasks to be observed according to workplace/college/TAFE policy and procedures, relevant legislation and Codes of Practice Yes No Comments/feedback
Works schedule(s), including drawings, plans, requirements, established procedures, and material lists, are obtained, analysed, if necessary, by site inspection and the extent of the preparation of the work determined for planning and coordination. 
Work is prioritised and sequenced for the most efficient and effective outcome following consultation with others for completion within acceptable timeframes, to a quality standard and in accordance with established procedures. 
Hazards are identified, OHS risks assessed and control measures are prioritised, implemented and monitored including emergency exits kept clear according to established procedures. 
Relevant requirements and established procedures for the work are to all personnel and identified for all work sites. 
OHS policies and procedures related to the work are identified to ensure safe systems of work are followed. 
Relevant work permits are secured to coordinate the performance of work according to requirements and/or established procedures. 
Resources including personnel, equipment, tools and personal protective equipment required for the job are identified, scheduled and coordinated and confirmed in a safe and technical working order. 
Clients/customers are provided with possible solutions and/or options within the scope, acceptable cost and requirements. 
Liaison and communication issues with other/authorised personnel, authorities, clients and land owners are resolved and activities coordinated to carry out work. 
Personnel participating in the work, including plant operators and contractors, are fully briefed and respective responsibilities coordinated and authorised where applicable in accordance with established procedures. 
Site is prepared according to the work schedule and to minimise risk and damage to property, commerce, and individuals in accordance with established procedures. 
Positioning of road signs, barriers and warning devices is planned and coordinated in accordance with requirements. 
OHS and sustainable energy principles and practices to reduce the incidents of accidents and minimise waste are monitored and actioned in accordance with requirements and/or established procedures. 
First Aid and other related work procedures are performed according to requirements and/or established procedures. 
Lifting, climbing, working in confined spaces and aloft, and use of power tools/equipment, techniques and practices are safely exercised according to requirements. 
Hazard warnings and safety signs are recognised and hazards and assessed OHS risks are reported to the immediate authorised persons for directions according to established procedures. 
Remedial actions are taken to overcome any shortfalls encountered in the work schedule according to requirements and/or established procedures. 
Installation of mobile generation set for synchronised genset HV is carried out, in accordance with the work schedule and requirements and/or established procedures. 
Essential knowledge and associated skills are applied in the safe installation of mobile generation set for synchronised genset HV to ensure completion in an agreed timeframe and, to quality standards with a minimum of waste according to requirements. 
Solutions to non-routine problems are identified and actioned using acquired essential knowledge and associated skills according to requirements. 
Ongoing checks of quality of the work are undertaken in accordance with requirements and established procedures to ensure a quality like outcome is achieved for the client/customer and to a community/industry standard. 
Work undertaken is checked against works schedule for conformance with requirements, anomalies reported and solutions identified in accordance with established procedures. 
Accidents and/or injuries are reported and followed up in accordance with requirements/established procedures. 
Work site is rehabilitated, cleaned up and confirmed safe in accordance with established procedures. 
Tools, equipment and any surplus resources and materials are, where appropriate, cleaned, checked and returned to storage in accordance with established procedures. 
Relevant work permit(s) are signed off and, synchronised genset HV apparatus is returned to service and advised to client/customer in accordance with requirements. 
Works completion records, reports, as installed /modified drawing(s) and/or documentation and information are confirmed, processed and appropriate personnel notified. 

Forms

Assessment Cover Sheet

UETTDRIS64A - Install mobile generation set for synchronised HV Genset
Assessment task 1: [title]

Student name:

Student ID:

I declare that the assessment tasks submitted for this unit are my own work.

Student signature:

Result: Competent Not yet competent

Feedback to student

 

 

 

 

 

 

 

 

Assessor name:

Signature:

Date:


Assessment Record Sheet

UETTDRIS64A - Install mobile generation set for synchronised HV Genset

Student name:

Student ID:

Assessment task 1: [title] Result: Competent Not yet competent

(add lines for each task)

Feedback to student:

 

 

 

 

 

 

 

 

Overall assessment result: Competent Not yet competent

Assessor name:

Signature:

Date:

Student signature:

Date: