CPCCCO3036A
Plan concrete work and brief team

This unit of competency specifies the outcomes required to assess the size and scope of a concreting job, identify the resources required to complete the project on time and within budget, and communicate requirements to team members in preparation for concreting work to commence.

Application

This unit of competency supports those who plan and prepare for concreting tasks. The person may be a nominated member of a team, or the team supervisor of concreters working on residential, commercial or civil construction sites.


Prerequisites

CPCCOHS2001A

Apply OHS requirements, policies and procedures in the construction industry


Elements and Performance Criteria

1

Assess concreting site and scope of work.

1.1

Site plans are reviewed and size and complexity of concreting tasks are evaluated.

1.2

Site access and egress information and traffic management plan are assessed and additional provisions or changes negotiated as required.

1.3

Provisions for site storage and amenities are assessed and additional provisions or changes are negotiated as required.

1.4

Concurrent work of other construction teams is assessed and communication channels established or confirmed.

1.5

Work specifications are assessed and project stages identified and sequenced to meet project timelines for completion.

1.6

Work health and safety (WHS) and environmental requirements are confirmed and applied to planning.

2

Determine and source team.

2.1

Dimensions of each pour are confirmed, predicted weather conditions assessed, and basic person-hour requirements for concreting work are then calculated.

2.2

Specialised skill requirements for different project stages are determined and skills of available team members assessed to identify skill shortages.

2.3

Additional team members with required skills are recruited within required timeframe to ensure prompt start to work.

2.4

Team members are allocated to tasks and human resource requirements for all project stages are checked and confirmed as complete.

3

Plan concrete pour.

3.1

Material requirements are calculated, documented and sourced in preparation for work to commence on time and on budget.

3.2

Type of concrete and curing time in predicted weather conditions are assessed for each pour and tasks are scheduled to meet project requirements.

3.3

Plant, tools and equipment required for each project stage are identified, documented and sourced in line with task schedule to ensure availability on site.

3.4

Safe work method statements (SWMS) are developed or adapted for individual tasks according to workplace procedures and safety requirements.

3.5

Potential risks, hazards and contingencies are assessed and management strategies developed.

4

Brief team members.

4.1

Site tour and induction for site safety and environmental requirements are arranged or conducted according to project and workplace requirements.

4.2

Details of task allocations and scheduling are explained and discussed and team understanding of work requirements is confirmed.

4.3

Concurrent work of other construction teams and communication channels are explained to team members and their understanding is confirmed.

4.4

Provisions for dealing with risks, hazards and contingencies are explained and understanding of team members is confirmed.

4.5

Team members are encouraged to clarify work requirements and suggest process improvements at all stages.

Required Skills

Required skills

learning skills to develop and build understanding of:

types of concrete materials

properties and behaviour of concrete in different environmental conditions

numeracy skills to calculate dimensions of pour and resource requirements

oral communication skills to:

brief team members on work specifications and requirements

liaise with site personnel

reading skills to interpret site plans and work specifications

writing skills to develop or adapt SWMS

Required knowledge

project management principles and strategies relevant to concrete work

regulations and standards relevant to concrete work:

AS 3600 Concrete structures

environmental

WHS

risks, hazards and contingencies relevant to concrete work and effective management strategies

role and responsibilities of construction site personnel

skills, plant, tools, equipment and materials required for concrete work

terminology used on construction sites in relation to concreting and other trades

Evidence Required

The evidence guide provides advice on assessment and must be read in conjunction with the performance criteria, required skills and knowledge, range statement and the Assessment Guidelines for the Training Package.

Overview of assessment

This unit of competency could be assessed by performing the mandated tasks in the workplace or a close simulation of the workplace environment, provided that simulated or project-based assessment techniques fully replicate construction workplace conditions, materials, activities, responsibilities and procedures.

Critical aspects for assessment and evidence required to demonstrate competency in this unit

A person should demonstrate the ability to:

predict the number of resources and time required to complete three separate concrete projects, each measuring a minimum of 100 square metres, and identify skill requirements for each project

identify and source appropriately skilled workers to complete the concreting work

brief the concreting team on the work to be completed and quality requirements of the finished work.

Context of and specific resources for assessment

Assessment of this unit:

must be in the context of the work environment

may be conducted in an off-site context, provided it is realistic and sufficiently rigorous to cover all aspects of workplace performance, including task skills, task management skills, contingency management skills and job role environment skills

must meet relevant compliance requirements.

Resource implications for assessment include:

an induction procedure

realistic tasks or simulated tasks covering the mandatory task requirements

relevant specifications and work instructions

support materials appropriate to activity.

Method of assessment

Assessment for this unit must verify the practical application of the required skills and knowledge, using a combination of the following methods:

direct observation of tasks in real or simulated work conditions

questioning to confirm the ability to consistently identify and correctly interpret the essential underpinning knowledge required for practical application

review of relevant authenticated documentation from third parties, such as existing supervisors, team leaders or specialist training staff.

Guidance information for assessment

This unit could be assessed on its own or in combination with other units relevant to the job function.

Reasonable adjustments for people with disabilities must be made to assessment processes where required. This could include access to modified equipment and other physical resources, and the provision of appropriate assessment support.

Assessment processes and techniques should, as far as is practical, take into account the language, literacy and numeracy capacity of the candidate in relation to the competency being assessed.


Range Statement

The range statement relates to the unit of competency as a whole. It allows for different work environments and situations that may affect performance. Bold italicised wording, if used in the performance criteria, is detailed below. Essential operating conditions that may be present with training and assessment (depending on the work situation, needs of the candidate, accessibility of the item, and local industry and regional contexts) may also be included.

Work specifications may include:

instructions issued by authorised organisational and external personnel

regulatory and legislative requirements relating to concrete work, including Australian standards

safety data sheets (SDS) for substances to be used

verbal, written and diagrammatic instructions, including manufacturer specifications and instructions where specified

work schedules, plans and specifications.

Project stages must include:

work preparation:

fitting personal protective equipment (PPE)

selecting and checking tools and equipment

site preparation:

excavation

formwork

subgrade

delivery

pouring

compaction

levelling

finishing

curing

site clean-up.

Work health and safety requirements must include:

assistance of others or the use of manual or mechanical lifting devices with handling activities where size, weight or other issues, such as disability, are a factor

emergency procedures, including extinguishing fires, organisational first aid requirements, and evacuation procedures

hazard control

hazardous materials and substances

PPE prescribed under legislation, regulations and workplace policies and practices relevant to concrete work

safe operating procedures, including the conduct of operational risk assessment and treatments associated with:

earth leakage boxes

lighting

power cables, including overhead service trays, cables and conduits

signage and restricted access barriers

surrounding structures

traffic control

trip hazards

work site visitors and the public

working at heights

working in confined spaces

working in proximity to others

working outdoors in warm climates

use of plant, tools and equipment.

Environmental requirements must include:

clean-up management

dust and noise control

stormwater management

vibration management

waste management.

Specialised skill requirements must include:

decorative concreting

cutting and coring

concrete repairs.

Material requirements must include:

concrete additives

reinforcements.

Plant, tools and equipment must include combinations of the following relevant to the tasks:

hand tools, including:

bolt cutters

crow bars

cutting knives

edging tools

floats

grinders

hammers

jointers

kneel boards

levelling equipment

long handled shovels

marking tools

measuring tapes

nail bags

picks

pinch bars

pliers

rakes

sledge hammers

steel fixing reels

string lines

wire brushes

trowels:

frezno

magnesium trowels

ride-on trowelling machine with pans or blades

stick trowels

walk behind trowels

power tools

plant and equipment:

compressors

material shifting equipment

vibrators.


Sectors

Concreting


Employability Skills

This unit contains employability skills.


Licensing Information

Licensing, legislative, regulatory or certification requirements apply to concreting work in different states and territories. Candidates are advised to consult with the relevant regulatory authorities.