• CPCCLRG3002A - Licence to perform rigging intermediate level

CPCCLRG3002A
Licence to perform rigging intermediate level

This unit specifies the outcomes required to perform rigging work at the intermediate level, which includes all the outcomes for rigging work at the basic level, and also includes rigging of cranes, rigging of conveyors, rigging of dredges and excavators, rigging associated with tilt slabs, rigging associated with demolition work, and dual lifts for licensing purposes.

Application

This unit requires the applicant to be able plan the work, select and inspect equipment, set up task, erect structures and plant and dismantle structures and plant.

This unit is based upon the National Standard for Licensing Persons Performing High Risk Work.

This unit in its current form meets state and territory licensing requirements. Any alteration will result in a unit which is not acceptable to regulators for the purpose of licensing.

This unit has a pre-requisite requirement. This requirement may be met by either the successful completion of the unit CPCCLRG3001A Licence to perform rigging basic level or holding a valid licence for basic rigging.


Prerequisites

CPCCLRG3001A

Licence to perform rigging basic level


Elements and Performance Criteria

ELEMENT

PERFORMANCE CRITERIA

1. Plan job.

1.1. Task to be undertaken is assessed

1.2. Potential workplace hazards are identified

1.3. Hazard control measures are identified consistent with appropriate standards to ensure the safety of personnel and equipment

1.4. Site information is obtained

1.5. All forces and loads associated with erecting and dismantling structures and associated plant are considered in consultation with appropriate personnel.

1.6. Rigging equipment and associated equipment are identified in consultation with appropriate personnel according to procedures and site information.

1.7. Safety equipment is identified.

1.8. Appropriate communication methods are identified with appropriate personnel.

2. Select and inspect equipment.

2.1. Rigging equipment and associated equipment are selected and inspected according to procedures and the appropriate standard.

2.2. Safety equipment is selected and inspected according to procedures.

2.3. All defective rigging equipment, associated equipment and safety equipment is isolated, reported and recorded according to procedures.

2.4. Communication equipment is selected and inspected for serviceability (where applicable)

3. Set up tasks.

3.1. Appropriate hazard prevention/control measures are applied to the work area according to procedures.

3.2. Ground suitability is inspected and checked (where appropriate).

3.3. Site information is reviewed, interpreted and communicated to appropriate personnel and appropriate personnel.

3.4. All forces and loads associated with erecting and dismantling structures and associated plant are determined in consultation with appropriate personnel.

3.5. Safety equipment is fitted and worn correctly (where appropriate).

3.6. Rigging equipment and associated plant are positioned for work application and stability according to procedures.

4. Erect structures and plant.

4.1. Structures and associated plant is erected according to procedures and site information.

4.2. Stability of structures and associated plant is maintained during erection according to procedures.

4.3. Work is conducted safely at heights including safe and effective use of safety equipment.

4.4. Appropriate communication methods and communication equipment, are used to co-ordinate the tasks.

4.5. Temporary guys, ties, propping and shoring, including flexible steel wire rope, and tubing, are connected where required.

4.6. Associated plant and rigging equipment is used according to procedures and the appropriate standard.

4.7. Associated equipment is used in a safe and appropriate manner.

4.8. The completed task is inspected according to the appropriate standard.

4.9. Excess materials are removed from the work area (where applicable)

5. Dismantle structures and plant.

5.1. Structures and associated plant are dismantled according to procedures and the appropriate standard.

5.2. Work is conducted safely at heights including safe and effective use of safety equipment.

5.3. Stability of structures and associated plant is maintained during dismantling according to procedures.

5.4. Rigging equipment, associated equipment, safety equipment and associated plant are inspected for damage and defects

5.5. All defective rigging equipment, associated equipment, associated plant and safety equipment are isolated reported and recorded according to procedures.

5.6. Rigging equipment and associated equipment are stored according to procedures and the appropriate standard.

5.7. Hazard prevention/control measures are removed (where appropriate)

Required Skills

Required skills

Required skills for this unit are:

ability to calculate Safe Working Load (SWL) and Working Load Limit (WLL)

ability to erect and dismantle, level, plumb and stabilise associated plant and structures

ability to work safely at heights including the correct application of safety equipment.

accurate interpretation of structural charts and structural plans (site information)

correct application and use of all rigging and associated equipment

risk assessment and hazard control strategies

interpersonal and communication skills at a level sufficient to site/workplace requirements. This includes the relevant communication methods and equipment.

verify problems and equipment faults and demonstrate appropriate response.

Required knowledge

Required knowledge for this unit is:

appropriate mathematical procedures for estimation and measurement of loads

ability to interpret manufacturer's specifications for all plant and equipment use in rigging operations

knowledge of principles relating to all plant, equipment and structural stability

knowledge of the types and functions of rigging, safety and associated equipment including an understanding of their limitations

organisational and workplace standards, requirements, policies and procedures for rigging

understanding of the hierarchy of hazard identification and control

relevant Commonwealth, state or territory and local government OHS legislation, standards and codes of practice for undertaking rigging activities

understanding of inspection and maintenance requirements of a wide range of appropriate plant and equipment in line with Australian Standards or manufacturer's specifications

estimation of ground bearing pressures of the full range of soil types and associated ground conditions for setting up plant and equipment.

Evidence Required

The evidence guide provides advice on assessment and must be read in conjunction with the performance criteria, required skills and knowledge, range statement and the Assessment Guidelines for the Training Package.

Overview of assessment

Successful assessment of this unit meets the competency requirement of the National Standard for licensing Persons Performing High Risk Work.

State/Territory OHS regulators have mandated the use of Assessment Instruments and Instructions for Assessment for this unit which have been endorsed by the national body responsible for OHS matters.

Critical aspects for assessment and evidence required to demonstrate competency in this unit

A person who demonstrates competency in this unit must be able to provide evidence of the ability to:

comply with OHS licensing legislation.

effectively communicate and work safely with others in the work area.

effectively conduct risk assessment and management procedures.

effectively complete the following tasks:

adding and removing a tower crane section, or

adding and removing a crane lattice boom section, or

erecting a non guyed tower (e.g. light tower, and

perform a multiple crane lift, or

a multiple winch lift, or

a combination of a crane and winch lift, and

lifting and installing a series of tilt-up panels, or

lifting and installing a series of scenery panels (i.e. entertainment industry), and

demolish/remove a series of tilt-up panel structures, or

demolish/remove a series of scenery panel structures, and

demolishing a concrete encased structural steel column and beam.

NB: All specifications for these performance tasks are detailed in the endorsed assessment instrument.

effectively conduct pre and post operational checks of intermediate rigging equipment.

Context of and specific resources for assessment

Assessment of the safe and effective application of knowledge and skill to workplace tasks (performance) must be undertaken using the endorsed Assessment Instrument.

Assessment of performance must be undertaken either in the workplace or in a realistically simulated workplace setting.

Assessors must ensure that the assessment in the workplace is organised to ensure that all the required equipment and materials and a suitable working area is made available to suit the assessment and the workplace.

Assessment must occur under standard and authorised work practices, safety requirements and environmental constraints.

Assessment is to comply with relevant appropriate standard requirements.

Applicants must have access to:

personal protective equipment (PPE) for the purpose of the Performance Assessment

appropriate safety equipment is safe condition

appropriate rigging equipment, associated equipment associated plant in safe condition as described in the endorsed assessment instrument

communication equipment (e.g. radios) where applicable

appropriate materials as required for safe erection of structures.

Method of assessment

Assessment must be conducted using the endorsed Assessment Instruments. These Instruments provide advice on their application.

The use of 'simulators' in the assessment of this unit of competency is not acceptable.

Assessment may be in conjunction with the assessment of other units of competency.

Assessment methods must confirm consistency and accuracy of performance together with application of underpinning knowledge.

Assessment must confirm a reasonable inference that competency is not only able to be satisfied under the particular circumstance, but is able to be transferred to other circumstances.

Guidance information for assessment

Further information about endorsed Assessment Instruments may be obtained from state/territory OHS regulators.


Range Statement

The range statement relates to the unit of competency as a whole. It allows for different work environments and situations that may affect performance. Bold italicised wording, if used in the performance criteria, is detailed below. Essential operating conditions that may be present with training and assessment (depending on the work situation, needs of the candidate, accessibility of the item, and local industry and regional contexts) may also be included.

Hazards may include but not limited to:

ground stability (e.g. ground condition, recently filled trenches, slopes)

overhead hazards (e.g. power lines, service pipes) (NB: Minimum clearance distance from powerlines or electrical equipment as determined by relevant state authority or electrical supply authority)

traffic (e.g. pedestrians, vehicles, other plant)

insufficient lighting

environmental conditions (e.g. wind, lightning, storms)

other specific hazards (e.g. dangerous materials).

Hazard control measures:

Refers to the systematic process of eliminating or reducing the risk to personnel and property through the application of controls.

It includes the application of the hierarchy of control, the six-step preference of control measures to manage and control risk:

elimination

substitution

isolation

engineering control measures

using safe work practices

personal protective equipment.

Appropriate standards may include but are not limited to:

codes of practice

legislation

Australian Standards

manufacturer's specifications

industry standards (where applicable).

Site Information may include but is not limited to:

local conditions such as access and egress

work method statements

site-specific job safety analyses and other site specific documentation as required

task plans /schedules and structural plans.

Forces and Loads may include but are not limited to:

dead loads

live loads

static load

dynamic loads

wind loads.

Structures may include but not limited to:

concrete tilt-up panels

scenery panels (used in entertainment)

non guyed light towers.

Associated plant may include but is not limited to:

all types of cranes

conveyors

dredges

excavators.

Appropriate personnel may include but not limited to:

supervisors

engineers

colleagues

managers who are authorised to take responsibility for the workplace or operations.

Rigging Equipment may include but is not limited to:

scaffolds

elevated work platforms

stages

personnel box

cantilevered crane loading platforms,

mast climbers

safety screens and shutters

cranes including but not limited to:

non-slewing cranes

mobile slewing cranes

vehicle loading cranes

tower cranes

self-erecting tower cranes

portal boom cranes

derrick cranes

bridge and gantry cranes.

Associated equipment may include but is not limited to:

all associated equipment at the basic rigging level, and

lifting clutches (swift lifts)

chain motors.

Procedures may include but are not limited to:

manufacturer's guidelines (instructions, specifications or checklists)

industry operating procedures, relevant codes of practice

workplace procedures (work instructions, operating procedures, checklists).

Safety Equipment may include but not limited to:

safety harness

energy absorber

lanyard

inertia reel

safety nets

static lines.

Communication Methods may include but not limited to:

verbal and non-verbal language

written instructions

signage

hand signals

listening,

questioning to confirm understanding, and appropriate worksite protocol.

NB: Mobile phones are not to be used for signalling purposes during the rigging process.

Communication equipment may include but is not limited to:

fixed channel two-way radios

Hazard prevention/control measures may include but is not limited to:

safety tags on electrical switches/isolators

powerlines are insulated

safety observer used inside exclusion zone

power disconnected

traffic barricades and control

pedestrian barricades

trench covers

movement of obstructions

personal protective equipment

adequate illumination.

Ground suitability may include but is not limited to:

rough uneven ground

backfilled ground

soft soils

hard compacted soil

rock

bitumen

concrete

suspended concrete floors

building roofs

landings

ground bearing pressure.

Appropriate personnel may include but not limited to:

other riggers

doggers

crane operators.

Flexible Steel Wire Rope (FSWR) includes:

identification, uses and connections.

May include termination for:

static lines

guys

purchase systems

lashing

cranes

hoist and winch ropes.


Sectors

Unit sector

Construction


Co-Requisites

Nil


Employability Skills

This unit contains employability skills.


Licensing Information

Refer to Unit Descriptor