Install roof coverings to curved roof structures

This unit of competency specifies the outcomes required to set out and install roofing to hyperbolic, paraboloid, barrel vault roof, curved roof and bull nosed roof structures.

Application

Site location for work application may be either domestic or commercial and may be a new work site or an existing structure being renovated, extended, restored or maintained.



Elements and Performance Criteria

ELEMENT

PERFORMANCE CRITERIA

1. Prepare for work.

1.1. Drawings and specifications are obtained and confirmed by site inspection.

1.2. Safety (OHS) requirements associated with installing curved roof structures, and workplace environmental requirements, are adhered to throughout the work.

1.3. Quality assurance requirements are identified and adhered to in accordance with workplace requirements.

1.4. Tasks are planned and sequenced in conjunction with others involved in or affected by the work and statutory and regulatory authority requirements.

1.5. Tools and equipment, including personal protective equipment, are selected and checked for serviceability.

1.6. Work area is prepared to support efficient installation of roof coverings to curved roof structures.

2. Identify installation requirements.

2.1. Quantity and type of manufactured roof covering, and fittings and equipment required, are calculated from design drawings and specifications in compliance with relevant Australian standards, local authorities' requirements and relevant information.

2.2. Proposed sealant, fixing materials, roofing and flashing materials are selected and checked for compatibility.

2.3. Materials and equipment are identified, ordered and collected in accordance with workplace procedures.

2.4. Materials and equipment are checked for compliance with docket and order form and for acceptable condition, and faults are reported.

2.5. Sustainability principles and concepts are applied to work preparation and application.

3. Install roof coverings.

3.1. Safety mesh and thermal insulation are fixed in accordance with relevant Australian standards, job specification and manufacturer requirements.

3.2. Sheets are marked and trimmed prior to fixing and cut edges are treated according to manufacturer specifications.

3.3. Roof covering is installed in accordance with manufacturer specifications.

3.4. Roof covering is performance tested and remedied.

4. Clean up.

4.1. Work area is cleared and materials disposed of, reused or recycled according to legislation, regulations, codes of practice and job specification.

4.2. Tools and equipment are cleaned, checked, maintained and stored in accordance with manufacturer recommendations and workplace procedures.

4.3. Documentation is completed in accordance with workplace requirements.

Required Skills

Required skills

Required skills for this unit are:

communication skills to:

access information

complete workplace documentation

determine requirements

enable clear and direct communication, using questioning to identify and confirm requirements, share information, listen and understand

follow instructions

plan and sequence tasks with others

read and interpret:

documentation from a variety of sources

drawings and specifications

report faults

use language and concepts appropriate to cultural differences

use and interpret non-verbal communication, such as hand signals

identifying and accurately reporting to appropriate personnel any faults in tools, equipment or materials

numeracy skills to apply measurements and calculations

organisational skills, including the ability to plan and set out work

teamwork skills to work with others to action tasks and relate to people from a range of cultural and ethnic backgrounds and with varying physical and mental abilities

technological skills to:

access and understand site-specific instructions in a variety of media

use mobile communication technology.

Required knowledge

Required knowledge for this unit is:

capillary action, thermal expansion and fabrication techniques to prevent leaking installations

corrosion prevention treatment requirements of cut sheets

electrolysis and problems associated with the use of dissimilar metals

job safety analysis (JSA) and safe work method statements (SWMS)

processes of fixing covering to curved roof structures

relevant OHS regulations and fall protection codes and requirements

relevant statutory and authority requirements related to installing roof coverings to curved roof structures

SI system of measurement

types of fasteners, fixings and sealants and their application to the installation of roof coverings.

Evidence Required

The evidence guide provides advice on assessment and must be read in conjunction with the performance criteria, required skills and knowledge, range statement and the Assessment Guidelines for the Training Package.

Overview of assessment

This unit of competency could be assessed in the workplace or a close simulation of the workplace environment providing that simulated or project-based assessment techniques fully replicate plumbing and services workplace conditions, materials, activities, responsibilities and procedures.

Critical aspects for assessment and evidence required to demonstrate competency in this unit

A person who demonstrates competency in this unit must be able to provide evidence of:

locating, interpreting and applying relevant information, relevant Australian standards and specifications to determine requirements, and plan the layout and installation of roof coverings to curved roof structures

applying safety requirements throughout the work sequence, including electrical requirements and the use of personal protective clothing and equipment

as a minimum the ability to, given the plans and specifications, calculate the requirements and install the roof covering to a bull nose or curved roof structure, incorporating one internal and one external corner, ensuring:

application of sustainability principles and concepts

correct identification of requirements and details of proposed installation

covering fits the structure

correct selection and use of appropriate processes, tools and equipment

completing all work to specification

compliance with regulations, standards and organisational quality procedures and processes

communicating and working effectively and safely with others.

Context of and specific resources for assessment

This competency is to be assessed using standard and authorised work practices, safety requirements and environmental constraints.

Assessment of essential underpinning knowledge will usually be conducted in an off-site context.

Assessment is to comply with relevant regulatory or Australian standards' requirements.

Resource implications for assessment include:

an induction procedure and requirement

realistic tasks or simulated tasks covering the minimum task requirements

relevant specifications and work instructions

tools and equipment appropriate to applying safe work practices

support materials appropriate to activity

workplace instructions relating to safe working practices and addressing hazards and emergencies

material safety data sheets

research resources, including industry related systems information.

Reasonable adjustments for people with disabilities must be made to assessment processes where required. This could include access to modified equipment and other physical resources, and the provision of appropriate assessment support.

Method of assessment

Assessment methods must:

satisfy the endorsed Assessment Guidelines of the Construction, Plumbing and Services Training Package

include direct observation of tasks in real or simulated work conditions, with questioning to confirm the ability to consistently identify and correctly interpret the essential underpinning knowledge required for practical application

reinforce the integration of employability skills with workplace tasks and job roles

confirm that competency is verified and able to be transferred to other circumstances and environments.

Validity and sufficiency of evidence requires that:

competency will need to be demonstrated over a period of time reflecting the scope of the role and the practical requirements of the workplace

where the assessment is part of a structured learning experience the evidence collected must relate to a number of performances assessed at different points in time and separated by further learning and practice, with a decision on competency only taken at the point when the assessor has complete confidence in the person's demonstrated ability and applied knowledge

all assessment that is part of a structured learning experience must include a combination of direct, indirect and supplementary evidence.

Assessment processes and techniques should as far as is practical take into account the language, literacy and numeracy capacity of the candidate in relation to the competency being assessed.

Supplementary evidence of competency may be obtained from relevant authenticated documentation from third parties, such as existing supervisors, team leaders or specialist training staff.


Range Statement

The range statement relates to the unit of competency as a whole. It allows for different work environments and situations that may affect performance. Bold italicised wording, if used in the performance criteria, is detailed below. Essential operating conditions that may be present with training and assessment (depending on the work situation, needs of the candidate, accessibility of the item, and local industry and regional contexts) may also be included.

Safety (OHS) is to be in accordance with commonwealth, state and territory legislation and regulations and may include:

handling of materials

hazard control

personal protective clothing and equipment prescribed under legislation, regulations and workplace policies and practices

safe operating procedures, including recognising and preventing hazards associated with:

electricity

hazardous materials and substances

service lines

surrounding structures and facilities

trip hazards

use of tools and equipment

work site visitors and the public

working at heights

working in proximity to others

use of firefighting equipment

use of first aid equipment

workplace environment and safety.

Environmental requirements cover water quality management and may include:

clean-up protection

stormwater protection

waste management.

Quality assurance requirements may include:

Environment Protection Authority (EPA)

environment policy

internal company quality assurance policy and risk management strategy

International Standards Organisation

site safety plan

workplace operations and procedures.

Statutory and regulatory authorities include:

commonwealth, state and local authorities administering applicable Acts, regulations and codes of practice..

Tools and equipment may include:

cranes

fall protection equipment

hand and power tools

ladders

levelling equipment

lifting and load shifting equipment, including:

chain blocks

elevated work platforms

forklifts

hand trolleys

hoists

restricted height scaffolds

rollers

measuring equipment.

Curved roof structure may be:

barrel shaped

concave

convex

hyperbolic

paraboloid.

Information may include:

charts and hand drawings

diagrams or sketches

instructions issued by authorised organisational or external personnel

manufacturer specifications and instructions

material safety data sheets (MSDS)

memos

organisation work specifications and requirements

regulatory and legislative requirements, particularly those pertaining to:

building codes

OHS and environmental requirements

plumbing regulations

relevant Australian standards

safe work procedures relating to installing roof coverings to curved roof structures

signage

verbal, written and graphical instructions

work bulletins

work schedules, plans and specifications.

Materials for installing roof coverings to curved roofs may include:

blanket and batt types

curved metal roof covers of concealed or pierce fixed types

metal rain water goods

metal self drilling and tapping screws

plastic building sheets for walls and roofs

rivets and sealants

thermal insulation of reflective foil laminate

other approved materials.

Fault reporting:

may be written or verbal

is to be in accordance with company's workplace procedures.

Sustainability principles and concepts:

cover the current and future social, economic and environmental use of resources

may include:

appropriate component selection that has minimal environmental impact

efficient energy use

efficient use and recycling of material

correct handling of hazardous materials

thermal heat reflection and retention

disposal of waste material to ensure minimal environmental impact.


Sectors

Unit sector

Plumbing and services


Co-Requisites

Nil


Employability Skills

This unit contains employability skills.


Licensing Information