Application
As agreed in the creation of this Training Package, applications for units transferred from the PUA00 Public Safety Training Package will be developed as part of continuous improvement plans, and taking into account the change in Unit of Competency format as detailed in templates for Streamlined Training Packages
Prerequisites
DEFDV001B Dive using self contained underwater breathing apparatus in open water to 30 metres.
Elements and Performance Criteria
ELEMENT | PERFORMANCE CRITERIA |
1. Prepare for underwater concreting | 1.1 Work task and worksite data are determined and analysed to determine the specific requirements for the concrete. 1.2 Work plan is developed consistent with the dive plan. 1.3 Concretingequipment is selected, inspected and prepared including protective equipment. 1.4 Concreting equipment is secured safely to/from the dive site. 1.5 Access obstructions and other hazards are assessed and action is taken to remove/reduce the risk. |
2. Concrete underwater site | 2.1 Work-safe area is established at the worksite. 2.2 Site is cleared and levelled in preparation for the pour. 2.3 Formwork is assembled including stripping agents. 2.4 Reinforcing bars, rods, stirrups and mesh, bar chairs and spacers are positioned. 2.5 Cement is mixed in accordance with the setting and strength specifications. 2.6 Location and safety of divers is confirmed prior to commencing the pour. 2.7 Cement is delivered to the site with a consistent flow. 2.8 Concrete is spread to the required levels incorporating expansion joints. 2.9 Concrete is screeded to a level and the surface is finished using floats or brooms. 2.10 Concrete is protected during curing. |
3. Conclude underwater concreting | 3.1 Environmental impact arising from the concreting is minimised and waste products and formwork are recovered. 3.2 Concreting and protective equipment are de-serviced and stored after use. |
Required Skills
This describes the essential skills and knowledge and their level, required for this unit. |
Required Skills |
establish formwork mix and pour cement operate cement tools and equipment screed concrete |
Required Knowledge |
concreting on land dive equipment dive physics general occupational/diving safety awareness oceanography relevant references and Australian Standards work hazards |
Evidence Required
Critical aspects for assessment and evidence required to demonstrate competency in this unit | Assessment must confirm the ability to attend to personal and collective safety; and to consider the environmental impact as part of the dive plan. Consistency in performance Competency should be demonstrated during a work task where the diver conducts an underwater concreting task such as the reinforcement of pier legs, the placement of footings or laying of a slab or ramp. |
Context of and specific resources for assessment | Context of assessment Competency should be assessed in the ocean. When practicable, assessment should relate to the diver’s vocational focus. Specific resources for assessment Access to a dive location, a complete range of concrete ingredients and concreting equipment. |
Range Statement
The Range Statement relates to the Unit of Competency as a whole. It allows for different work environments and situations that may affect performance. Bold italicised wording in the Performance Criteria is detailed below. | |
Work task may include: | pad foundation post holes slabs trench foundations |
Worksite data may include: | current depth gradient hazards obstacles temperature |
Concrete may vary by: | composition/strength setting time |
Concreting equipment may include: | manual, fuel and electrically operated mixers shovel vibrator |
Selecting, inspecting and preparing concreting equipment may include: | pre-construction of formwork pre-mixing |
Protective equipment may include: | boots gloves |
Action to remove/reduce the risk may include: | erecting signage using patrol/sentry craft |
Formwork may include: | bracing edge boards pegs struts |
Delivery of cement may be via: | manual pump-line shute |
Protection of concrete may include: | use of plastic sheeting |
Environmental impact may include: | contamination of surrounding water (e.g. leaking oil) physical damage to reef and associated floor eco-systems (e.g. coral) visual pollution of waste material (e.g. concrete and metal parts) |
Sectors
Not applicable.
Employability Skills
This unit contains employability skills.
Licensing Information
Not applicable.