RIICCM210A
Install trench support

This unit covers the installation of trench support in the civil construction industry. It includes planning and preparing, installing trench shoring, removing trench shoring, and cleaning up. Licensing, legislative, regulatory and certification requirements that apply to this unit can vary between states, territories, and industry sectors. Relevant information must be sourced prior to application of the unit.

Application

This unit is appropriate for those working in an operational role at worksites within:

Civil construction


Prerequisites

Not applicable.


Elements and Performance Criteria

ELEMENT

PERFORMANCE CRITERIA

1 Plan and prepare

1.1. Access, interpret and apply compliance documentation relevant to the work activity

1.2. Obtain and confirm safety requirements from the site safety plan and organisational policies and procedures, and apply to the allotted task

1.3. Identify, obtain and implement traffic control signage requirements from the project traffic management plan

1.4. Select plant, tools and equipment to carry out tasks consistent with the requirements of the job, check for serviceability and rectify or report any faults

1.5. Identify environmental protection requirements from the project environmental management plan, and confirm and apply to the allotted task

2. Install trench shoring

2.1. Communicate with plant operator to ensure the excavation of trenches complies with site plan, line and depth

2.2. Determine and prepare shoring method

2.3. Set out positioning of shoring

2.4. Position or erect shoring within the trench

2.5. Secure shoring in position and check to ensure structural conformity with regulations

2.6. Clean out excavation out by hand to job requirements

2.7. Provide ladders for access and egress to site safety plan requirements

3. Remove trench shoring

3.1. Release jacking mechanisms and remove ladders

3.2. Check shoring and prepare it for lifting from the trench

3.3. Remove shoring from trench and store it on site

4. Clean up

4.1. Clear work area and dispose of or recycle materials in accordance with project environmental management plan

4.2. Clean, check, maintain and store tools and equipment

Required Skills

Required skills

Specific skills are required to achieve the Performance Criteria of this unit, particularly for its application in the various circumstances in which this unit may be used. This includes the ability to carry out the following, as required to install trench shoring:

apply legislative, organisation and site requirements and procedures for installing trench shoring

organise work activities

select and use relevant tools and equipment safely

identify and report on hazards related to the worksite and work activity

communicate effectively to receive and clarify work instructions

Required knowledge

Specific knowledge is required to achieve the Performance Criteria of this unit, particularly for its application in the various circumstances in which this unit may be used. This includes knowledge of the following, as required to install trench support:

site and equipment safety requirements

excavation techniques

shoring methods and systems

working in confined spaces

construction techniques

equipment types, characteristics, technical capabilities and limitations

operational, maintenance and basic diagnostic procedures

site isolation and traffic control responsibilities and authorities

materials safety data sheets and materials handling methods

project quality requirements

civil construction terminology

JSAs/safe work method statement

Evidence Required

The evidence guide provides advice on assessment and must be read in conjunction with the performance criteria, required skills and knowledge, range statement and the Assessment Guidelines for the Training Package.

Overview of assessment

Critical aspects for assessment and evidence required to demonstrate competency in this unit

The evidence required to demonstrate competency in this unit must be relevant to worksite operations and satisfy all of the requirements of the performance criteria, required skills and knowledge and the range statement of this unit and include evidence of the following:

knowledge of the requirements, procedures and instructions for installing trench support

implementation of requirements, procedures and techniques for the safe, effective and efficient completion of trench support installation

working with others to undertake and complete the installation of trench support in a way that meets all of the required outcomes

consistent timely completion of trench support installation that safely, effectively and efficiently meets the required outcomes

installation of trench support on two projects in trenches deeper than 1.5 metres requiring the trench support to be installed, moved along or within the trench and removed from the trench

Context of and specific resources for assessment

This unit must be assessed in the context of the work environment. Where personal safety or environmental damage are limiting factors, assessment may occur in a simulated environment provided it is realistic and sufficiently rigorous to cover all aspects of workplace performance, including task skills, task management skills, contingency management skills and job role environment skills.

Assessment of this competency requires typical resources normally used in a resources and infrastructure sector environment. Selection and use of resources for particular worksites may differ due to the site circumstances.

The assessment environment should not disadvantage the participant. For example, language, literacy and numeracy demands of assessment should not be greater than those required on the job.

Customisation of assessment and delivery environment to sensitively accommodate cultural diversity.

Aboriginal people and other people from a non English speaking background may have second language issues.

Where applicable, physical resources should include equipment modified for people with disabilities. Access must be provided to appropriate learning and/or assessment support when required.

Method of assessment

This unit may be assessed in a holistic way with other units of competency. The assessment strategy for this unit must verify required knowledge and skill and practical application using more than one of the following assessment methods:

written and/or oral assessment of the candidate's required knowledge

observed, documented and/or first hand testimonial evidence of the candidate's:

implementation of appropriate requirement, procedures and techniques for the safe, effective and efficient achievement of required outcomes

consistent achievement of required outcomes

first hand testimonial evidence of the candidate's:

working with others to undertake and complete the trench support installation

Guidance information for assessment

Consult the SkillsDMC User Guide for further information on assessment including access and equity issues.


Range Statement

The range statement relates to the unit of competency as a whole. It allows for different work environments and situations that may affect performance. Bold italicised wording, if used in the performance criteria, is detailed below. Essential operating conditions that may be present with training and assessment (depending on the work situation, needs of the candidate, accessibility of the item, and local industry and regional contexts) may also be included.

Relevant compliance documentation may include:

legislative, organisational and site requirements and procedures

manufacturer's guidelines and specifications

Australian standards

Employment and workplace relations legislation

Equal Employment Opportunity and Disability Discrimination legislation

Safety requirements may include:

OHS requirements in accordance with state or territory legislation and regulations, organisational safety policies and procedures, and project safety plan including: protective clothing and equipment, use of tools and equipment, workplace environment and safety, handling of materials, use of fire fighting equipment, use of First Aid equipment, hazard control and hazardous materials and substances

safe operating procedures including recognising and preventing hazards associated with high voltage power lines, uneven/unstable terrain, trees, overhead service lines, bridges, surrounding buildings, obstructions, structures, facilities, dangerous materials, recently filled trenches, other machines, personnel, traffic control, working at heights, working in proximity to others, worksite visitors and the public

safe parking practices including ensuring access ways are clear, equipment/machinery is away from overhangs and refuelling sites, safe distance from excavations, and secured from unauthorised access or movement

recognising hazards and risks including uneven/unstable terrain, trees, fires, overhead and underground services, bridges, buildings, excavations, traffic, embankments, cuttings, structures and hazardous materials

emergency procedures related to equipment operation including emergency shutdown and stopping, extinguishing equipment fires, organisational First Aid requirements and evacuation

Traffic control signage may include:

site safety signage

temporary signage for the benefit of motorists and pedestrians

barricades

traffic conditions signage

Tools and equipment may include:

shoring systems

levelling equipment

hand and power tools

measuring equipment

shovels

picks

scaffolding

elevated work platforms

slings

chains

Environmental protection requirements may include:

organisational/project environmental management plan

waste management

water quality protection

noise

vibration

dust

clean-up management

Excavations may include:

trenches

wells

pits

Trench may include:

trenches of at least 1.5 metres in depth

trenches less than 1.5 metres deep

Shoring method may include:

fixed and/or adjustable trench boxes

drag boxes

hydraulic vertical shoring

close timber shoring

aluminium shoring shields

powerbrace

lite box aluminium panels

slide rails

Erect shoring may include:

using trench shoring mechanisms including:

closed timber sheeting

soldier sets

segmental sections

trench shields

using shoring securing mechanisms including:

footings

needles

anchors

sole plates

struts

brackets


Sectors

Civil Works (Common Units)


Competency Field

Refer to Unit Sector(s).


Co-Requisites

Not applicable.


Employability Skills

This unit contains employability skills.


Licensing Information

Refer to Unit Descriptor.