The important thing to remember when gathering evidence is that the more evidence the better - that is, the more evidence you gather to demonstrate your skills, the more confident an assessor can be that you have learned the skills not just at one point in time, but are continuing to apply and develop those skills (as opposed to just learning for the test!). Furthermore, one piece of evidence that you collect will not usualy demonstrate all the required criteria for a unit of competency, whereas multiple overlapping pieces of evidence will usually do the trick!
From the Wiki University
What evidence can you provide to prove your understanding of each of the following citeria?
Notify client and relevant authorities and agencies of the schedule of works.
|
|
Fees due are paid and site handover date is confirmed with client. Completed |
Evidence:
|
Insurance and security requirements are established and provided. Completed |
Evidence:
|
Parking restrictions are determined and advised to relevant personnel. Completed |
Evidence:
|
Authorities requiring formal notification of the commencement of work are contacted. Completed |
Evidence:
|
Organise the delivery of on-site accommodation and facilities.
|
|
Requirements for on-site accommodation and facilities are identified. Completed |
Evidence:
|
Site office, storage sheds and on-site toilet facilities are arranged, received and positioned. Completed |
Evidence:
|
Site signage is erected to comply with regulations. Completed |
Evidence:
|
Processes are developed and implemented to identify and protect existing services at the site. Completed |
Evidence:
|
Council requirements are identified and met. Completed |
Evidence:
|
Organise the delivery of plant.
|
|
On-site plant delivery dates are confirmed. Completed |
Evidence:
|
Hoardings are erected and rubbish removal facilities are arranged. Completed |
Evidence:
|
Arrange the connection of temporary services.
|
|
Temporary power and water connections are arranged with service providers. Completed |
Evidence:
|
Temporary site access and egress are arranged and authorisations obtained from the local authority. Completed |
Evidence:
|
Organise on-site human resources.
|
|
On-site human resource requirements are identified. Completed |
Evidence:
|
Construction work supervisor is engaged or appointed. Completed |
Evidence:
|
Industrial relations and safety matters occurring on supervised work site that could impact on the resourcing and preparation for building work are addressed where required. Completed |
Evidence:
|
Appropriate personnel is engaged according to project needs. Completed |
Evidence:
|
Order materials.
|
|
Orders for prefabricated materials are placed using approved company documentation and site delivery dates are confirmed. Completed |
Evidence:
|
Construction arrangements required by contract are finalised to satisfy the project schedule. Completed |
Evidence:
|