The important thing to remember when gathering evidence is that the more evidence the better - that is, the more evidence you gather to demonstrate your skills, the more confident an assessor can be that you have learned the skills not just at one point in time, but are continuing to apply and develop those skills (as opposed to just learning for the test!). Furthermore, one piece of evidence that you collect will not usualy demonstrate all the required criteria for a unit of competency, whereas multiple overlapping pieces of evidence will usually do the trick!
From the Wiki University
What evidence can you provide to prove your understanding of each of the following citeria?
Erect and strip simple formwork.
|
|
Formwork design is identified from drawings. Completed |
Evidence:
|
Formwork is erected safely on commencement. Completed |
Evidence:
|
Form release agent is applied to erected formwork where specified. Completed |
Evidence:
|
Timber components are de-nailed following stripping of formwork. Completed |
Evidence:
|
Components are cleaned, stacked and stored for reuse or bundled for removal. Completed |
Evidence:
|
Formwork components are removed from site. Completed |
Evidence:
|
Place and tie reinforcement.
|
|
Reinforcing components are handled and positioned safely. Completed |
Evidence:
|
Reinforcing bars and mesh are positioned. Completed |
Evidence:
|
Bar chairs and spacers are positioned, with minimum edge cover. Completed |
Evidence:
|
Formwork or excavation is cleaned of excess material and debris prior to concrete placement. Completed |
Evidence:
|
Concrete is safely transported by wheelbarrow. Completed |
Evidence:
|
Pump line/chute is controlled and concrete placed. Completed |
Evidence:
|
Concrete is placed in formwork to specified depth. Completed |
Evidence:
|
Concrete is screeded to the alignment of formwork and project specified datums. Completed |
Evidence:
|
Surface of concrete is finished in accordance with specifications. Completed |
Evidence:
|
Work area is cleared and materials disposed of, reused or recycled in accordance with legislation, regulations and codes of practice and job specification. Completed |
Evidence:
|
Plant, tools and equipment are cleaned, checked, maintained and stored in accordance with manufacturer recommendations and standard work practices. Completed |