NTISthis.com

Evidence Guide: CPCCLBM3001A - Licence to operate a concrete placing boom

Student: __________________________________________________

Signature: _________________________________________________

Tips for gathering evidence to demonstrate your skills

The important thing to remember when gathering evidence is that the more evidence the better - that is, the more evidence you gather to demonstrate your skills, the more confident an assessor can be that you have learned the skills not just at one point in time, but are continuing to apply and develop those skills (as opposed to just learning for the test!). Furthermore, one piece of evidence that you collect will not usualy demonstrate all the required criteria for a unit of competency, whereas multiple overlapping pieces of evidence will usually do the trick!

From the Wiki University

 

CPCCLBM3001A - Licence to operate a concrete placing boom

What evidence can you provide to prove your understanding of each of the following citeria?

Set up and prepare for operation.

  1. Ground suitability is inspected and checked.
  2. Concrete placing boom is driven to or located at work area according to procedures.
  3. Concrete placing boom is positioned for work application and stability according to procedures.
  4. Concrete placing boom is started according to procedures and checked for any abnormal noise.
  5. All safety devices are tested according to procedures.
  6. Post start operational checks are carried out according to procedures.
  7. Delivery system components, including booms, lines and adaptors, are positioned securely and safely according to procedures.
  8. Appropriate hazard prevention/control measures are applied to the work area according to procedures.
  9. Pumping systems are tested and prepared for use according to procedures.
Ground suitability is inspected and checked.

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Concrete placing boom is driven to or located at work area according to procedures.

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Concrete placing boom is positioned for work application and stability according to procedures.

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Concrete placing boom is started according to procedures and checked for any abnormal noise.

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

All safety devices are tested according to procedures.

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Post start operational checks are carried out according to procedures.

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Delivery system components, including booms, lines and adaptors, are positioned securely and safely according to procedures.

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Appropriate hazard prevention/control measures are applied to the work area according to procedures.

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Pumping systems are tested and prepared for use according to procedures.

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Deliver concrete.

  1. Supply of bulk concrete to the hopper is coordinated safely with the supply vehicle operator/s.
  2. Concrete placing boom is operated safely using relevant boom movements to deliver the concrete as required.
  3. Safe operating techniques are applied for all operations.
  4. Communication signals are correctly interpreted according to the appropriate standard.
  5. Monitor boom movement constantly ensuring safety of personnel, delivery hose and stability.
  6. Unplanned and/or unsafe situations are responded to in line with procedures.
  7. Concrete placing boom is safely withdrawn from the work area at the completion of the delivery task.
Supply of bulk concrete to the hopper is coordinated safely with the supply vehicle operator/s.

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Concrete placing boom is operated safely using relevant boom movements to deliver the concrete as required.

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Safe operating techniques are applied for all operations.

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Communication signals are correctly interpreted according to the appropriate standard.

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Monitor boom movement constantly ensuring safety of personnel, delivery hose and stability.

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Unplanned and/or unsafe situations are responded to in line with procedures.

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Concrete placing boom is safely withdrawn from the work area at the completion of the delivery task.

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Shut down and secure concrete placing boom.

  1. Delivery lines and hopper are cleaned out according to procedures.
  2. Boom is correctly stowed and secured for travel according to procedures.
  3. Outriggers/stabilisers are stowed and secured according to procedures.
  4. Plates or packing are stowed and secured for travel.
  5. Concrete placing boom is shut down according to procedures.
  6. Routine post-operational equipment checks are carried out according to procedures.
  7. All defects and damage are reported and recorded according to procedures and appropriate action is taken.
Delivery lines and hopper are cleaned out according to procedures.

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Boom is correctly stowed and secured for travel according to procedures.

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Outriggers/stabilisers are stowed and secured according to procedures.

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Plates or packing are stowed and secured for travel.

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Concrete placing boom is shut down according to procedures.

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Routine post-operational equipment checks are carried out according to procedures.

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

All defects and damage are reported and recorded according to procedures and appropriate action is taken.

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Assessed

Teacher: ___________________________________ Date: _________

Signature: ________________________________________________

Comments:

 

 

 

 

 

 

 

 

Instructions to Assessors

Evidence Guide

The evidence guide provides advice on assessment and must be read in conjunction with the performance criteria, required skills and knowledge, range statement and the Assessment Guidelines for the Training Package.

Overview of assessment

Successful assessment of this unit meets the competency requirement of the National Standard for licensing Persons Performing High Risk Work.

State/Territory OHS regulators have mandated the use of Assessment Instruments and Instructions for Assessment for this unit which have been endorsed by the national body responsible for OHS matters.

Critical aspects for assessment and evidence required to demonstrate competency in this unit

A person who demonstrates competency in this unit must be able to provide evidence of the ability to:

comply with OHS licensing legislation

assess ground conditions to confirm that the site is suitable (e.g. firm, level and safe) to erect the concrete placing boom.

assess risk and hazard control strategies, including hierarchy of control as applied to the positioning and safe operation of the concrete placing boom (particular awareness of the risks associated with overhead powerlines/electrical cables, ground conditions, wind, pedestrians and tipping)

complete the pre operational check, positioning, stabilising, set up, operation, post operational checks of a concrete placing boom including all functions to their maximum extension in the moving of the boom and placement of concrete to the safe working rated capacity of the concrete placing boom

operate the concrete placing boom in conjunction with other appropriate personnel (where applicable).

Context of and specific resources for assessment

Assessment of the safe and effective application of knowledge and skill to workplace tasks (performance) must be undertaken using the endorsed Assessment Instrument

Assessment of performance must be undertaken either in the workplace or in a realistically simulated workplace setting

Assessors must ensure that the assessment in the workplace is organised to ensure that all the required equipment and materials and a suitable working area is made available to suit the assessment and the workplace

Assessment must occur under standard and authorised work practices, safety requirements and environmental constraints

Assessment is to comply with relevant appropriate standard requirements

Applicants must have access to:

personal protective equipment (PPE) for the purpose of the Performance Assessment

appropriate concrete placing boom and associated equipment in safe condition

communication equipment (e.g. two way radios, etc) where appropriate

other appropriate personnel to direct the placement of concrete (where applicable).

Method of assessment

Assessment must be conducted using the endorsed Assessment Instruments. These Instruments provide advice on their application.

The use of 'simulators' in the assessment of this unit of competency is not acceptable.

Assessment may be in conjunction with the assessment of other units of competency.

Assessment methods must confirm consistency and accuracy of performance together with application of underpinning knowledge.

Assessment must confirm a reasonable inference that competency is not only able to be satisfied under the particular circumstance, but is able to be transferred to other circumstances.

Guidance information for assessment

Further information about endorsed Assessment Instruments may be obtained from state/territory OHS regulators.

Required Skills and Knowledge

Required skills

Required skills for this unit are:

accurately record and maintain information relating to concrete placing boom operations

communication techniques in the workplace including hand signals and use of fixed channel two-way radios

complete the positioning, stabilising, set up and pack up of concrete placing booms, including the use of outriggers/stabilisers and packing

communication skills at a level sufficient to communicate with other site personnel

operation and control of a concrete placing boom including all functions to within their maximum capability

risk assessment and hazard prevention strategies, including hierarchy of control as applied to the positioning and safe operation of the concrete placing boom (particular awareness of the risks associated with overhead powerlines/electrical cables, ground conditions, wind, pedestrians and tipping)

verify problems and equipment faults and demonstrate appropriate response procedures.

Required knowledge

Required knowledge for this unit is:

assessment of ground conditions to confirm that the site is suitable (eg. firm, level and safe) to set up the concrete placing boom

Commonwealth, state or territory OHS legislation, standards and codes of practice relevant to the full range of processes for conducting concrete placing boom operations

level of literacy to be able to read and comprehend manufacturer's instructions, procedures and safety signs

concrete placing boom delivery operations and operating techniques

organisational and site standards, requirements, policies and procedures for conducting concrete placing boom operations

procedures for the recording, reporting and maintenance of workplace records and information, including the use of the service logbook.

understanding of the hierarchy of hazard identification and control

read and interpret the data plate for the concrete placing boom.

typical routine problems encountered in the process and with equipment and adjustments required for correction.

Range Statement

The range statement relates to the unit of competency as a whole. It allows for different work environments and situations that may affect performance. Bold italicised wording, if used in the performance criteria, is detailed below. Essential operating conditions that may be present with training and assessment (depending on the work situation, needs of the candidate, accessibility of the item, and local industry and regional contexts) may also be included.

Hazards may include but not limited to:

ground stability (eg. ground condition, recently filled trenches, slopes)

overhead hazards (eg. power lines, service pipes)

insufficient lighting

traffic (eg. pedestrians, vehicles, other plant)

environmental conditions (eg. wind, lightning, storms)

other specific hazards (eg. dangerous materials).

Hazard control measures:

Refers to the systematic process of eliminating or reducing the risk to personnel and property through the application of controls.

It includes the application of the hierarchy of control, the six-step preference of control measures to manage and control risk:

elimination

substitution

isolation

engineering control measures

using safe work practices

personal protective equipment.

Appropriate standards may include:

codes of practice

legislation

Australian Standards,

manufacturer's specifications

industry standards (where applicable).

Concrete placing boom may include:

a mobile truck mounted plant incorporating a knuckle boom, capable of power operated slewing and luffing to place concrete by way of pumping through a pipeline attached to, or forming part of, the boom of the plant.

Communication methods may include but not limited to:

verbal and non-verbal language

written instructions

signage

hand signals

listening

questioning to confirm understanding

appropriate worksite protocol.

Appropriate personnel may include but are not limited to:

those associated with the operations of the concrete placing boom

supervisors

suppliers

clients

colleagues

managers.

Procedures may include but are not limited to:

manufacturer's guidelines (range chart, instructions, specifications or checklists)

industry operating procedures

workplace procedures (work instructions, operating procedures, checklists).

Service logbook may include but is not limited to:

any logbook

service book

history record system where the service and maintenance history is kept.

Hoppers may include but not limited to:

large receptacles mounted on the concrete placing boom which receive the concrete from supply vehicles and dispense the concrete to the pumping system.

Communication equipment may include but not limited to:

fixed channel two way radios

mobile phones.

NB: where radio communication equipment is used the transmitting frequencies of the equipment must be selected to prevent interference to or from other radio equipment being used in the vicinity of the crane.

Ground suitability may include but not limited to:

rough uneven ground

backfilled ground

soft soils

hard compacted soil

rock

bitumen

concrete.

Stability may include but not limited to:

deploying outriggers

establish correct size plates or packing

correctly position plates or packing.

Safety devices may include but not limited to:

horns/sirens

audible and visual reversing devices

operator restraint devices (where applicable)

lights

safety interlocks.

Hazard prevention/control measures may include but not limited to:

safety tags on electrical switches/isolators

powerlines are insulated

safety observer used inside exclusion zone

power disconnected

traffic barricades and control

pedestrian barricades

trench covers

movement of obstructions

personal protective equipment

adequate lighting

earth chain.

Supply vehicle may include but not limited to:

cement mixer trucks

agitator trucks

other concrete transport vehicles.

Relevant boom movements may include but not limited to:

raising boom

lowering boom

slewing

knuckling.

Safe operating techniques may include but not limited to:

achieving a safe optimum output from the concrete delivery system within the manufacturers design specifications

ensuring hopper levels are maintained at safe and recommended levels

safe operation of the boom to ensure safety of operator and other personnel

managing engine power to ensure efficiency of concrete pump truck platform movements and to minimise damage to the engine and gears

coordinating engine power with gear selection ensuring smooth transition and operation within torque range.

Communication signals may include but not limited to:

boom up - hand

boom down - hand

boom left - hand

boom right - hand

open or extend boom -hand

close or retract boom - hand

stop boom - hand

start pump speed up - hand

slow pump down - hand

little bit - hand

add water - hand

all done clean-up - hand.

Unplanned and/or unsafe situations may include but not limited to:

failure/lose of control e.g. blown hose or concrete line

failure of equipment e.g. hydraulic system

environmental conditions (e.g. wind, lightning, storms, etc).

Shut down may include but is not limited to:

retracting boom

positioning/securing boom

retracting outriggers/stabilisers

idle engine to stabilise temperature

disengage PTO (where applicable)

turning off engine (where applicable)

remove key from ignition (where applicable)

lock and secure cabin (where applicable).