The important thing to remember when gathering evidence is that the more evidence the better - that is, the more evidence you gather to demonstrate your skills, the more confident an assessor can be that you have learned the skills not just at one point in time, but are continuing to apply and develop those skills (as opposed to just learning for the test!). Furthermore, one piece of evidence that you collect will not usualy demonstrate all the required criteria for a unit of competency, whereas multiple overlapping pieces of evidence will usually do the trick!
From the Wiki University
What evidence can you provide to prove your understanding of each of the following citeria?
Prepare for work.
|
|
Plans and specifications are obtained. Completed |
Evidence:
|
Safety (OHS) requirements associated with draining a work site, and workplace environmental requirements, are adhered to throughout the work. Completed |
Evidence:
|
Quality assurance requirements are identified and adhered to in accordance with workplace requirements. Completed |
Evidence:
|
Tasks are planned and sequenced in conjunction with others involved in or affected by the work. Completed |
Evidence:
|
Tools and equipment, including personal protective equipment, are selected and checked for serviceability. Completed |
Evidence:
|
Work area is prepared to support efficient draining of the work site. Completed |
Evidence:
|
Identify installation requirements.
|
|
Proposed location of stormwater connection points, sumps, wells and pumps are determined from drawings and specifications. Completed |
Evidence:
|
Quantity and type of materials and equipment required are calculated from design drawings and specifications and comply with standards and local authorities' requirements. Completed |
Evidence:
|
Materials and equipment are identified, ordered and collected in accordance with workplace procedures. Completed |
Evidence:
|
Materials and equipment are checked for compliance with docket and order form, and for acceptable condition. Completed |
Evidence:
|
Prepare and excavate site.
|
|
Excavation site is set out to comply with drawings and specifications, installation and consideration for the location of existing services. Completed |
Evidence:
|
Site is excavated in accordance with drawings and specifications, site requirements and standards, ensuring minimum damage to surrounding structures and environment. Completed |
Evidence:
|
Sedimentation controls are constructed and positioned in accordance with specifications. Completed |
Evidence:
|
Install permanent drainage.
|
|
Sumps and wells are constructed at specified levels and locations. Completed |
Evidence:
|
Suction inlet point is prepared in accordance with drawings, specifications and manufacturers' requirements. Completed |
Evidence:
|
Appropriate pumps are installed, in specified locations. Completed |
Evidence:
|
Pipework and hoses are connected and fitted to pumps in accordance with drawings and specifications, manufacturers' requirements and site drainage specifications. Completed |
Evidence:
|
Operate drainage system.
|
|
Pumps are activated to lower water level by specifications. Completed |
Evidence:
|
Pump control system is adjusted to meet specification requirements. Completed |
Evidence:
|
Pumps are maintained in accordance with manufacturer specifications and workplace requirements. Completed |
Evidence:
|
Clean up.
|
|
Ground area is restored and work area is cleared, with materials disposed of or recycled in accordance with state or territory statutory and regulatory authority legislation. Completed |
Evidence:
|
Tools and equipment are cleaned, checked, maintained and stored in accordance with manufacturer recommendations and workplace procedures. Completed |
Evidence:
|
Information is accessed and documentation completed in accordance with workplace requirements. Completed |
Evidence:
|