The important thing to remember when gathering evidence is that the more evidence the better - that is, the more evidence you gather to demonstrate your skills, the more confident an assessor can be that you have learned the skills not just at one point in time, but are continuing to apply and develop those skills (as opposed to just learning for the test!). Furthermore, one piece of evidence that you collect will not usualy demonstrate all the required criteria for a unit of competency, whereas multiple overlapping pieces of evidence will usually do the trick!
From the Wiki University
What evidence can you provide to prove your understanding of each of the following citeria?
Prepare for work.
|
|
Plans and specifications are obtained. Completed |
Evidence:
|
Safety (OHS) requirements associated with connection of static storage tanks and workplace environmental requirements are adhered to throughout the work. Completed |
Evidence:
|
Quality assurance requirements are identified and adhered to in accordance with workplace requirements. Completed |
Evidence:
|
Tasks are planned and sequenced in conjunction with others involved in or affected by the work. Completed |
Evidence:
|
Tools and equipment for connecting static storage tanks, including personal protective equipment, are selected and checked for serviceability. Completed |
Evidence:
|
Work area is prepared to support efficient connection of static storage tanks. Completed |
Evidence:
|
Identify installation requirements.
|
|
Materials required for the installation are determined from plans and specification. Completed |
Evidence:
|
Materials are selected that comply with standards and job specifications. Completed |
Evidence:
|
Quantities of materials required are calculated from plans. Completed |
Evidence:
|
Materials and equipment are identified, ordered and collected in accordance with workplace procedures. Completed |
Evidence:
|
Materials and equipment are checked for compliance with standards, docket and order form, and for acceptable condition. Completed |
Evidence:
|
Install and test storage tank.
|
|
Storage tank and associated pipework are set out in accordance with drawings, specifications and job instructions. Completed |
Evidence:
|
Pipe supports and fixings, compliant with standards, are installed to plans and manufacturer specifications. Completed |
Evidence:
|
Tank, piping and materials are installed in accordance with plans, specifications and standards. Completed |
Evidence:
|
Jointing systems are compliant with standards. Completed |
Evidence:
|
Installed system is subjected to pressure testing in accordance with standards or job specification. Completed |
Evidence:
|
Test data is recorded in format required by job specifications and quality assurance procedures. Completed |
Evidence:
|
Installation is backfilled in accordance with specifications. Completed |
Evidence:
|
Clean up.
|
|
Work area is cleared, with materials disposed of or recycled in accordance with state or territory statutory and regulatory authority legislation. Completed |
Evidence:
|
Tools and equipment are cleaned, checked, maintained and stored in accordance with manufacturer recommendations and workplace procedures. Completed |
Evidence:
|
Information is accessed and documentation completed in accordance with regulatory authorities and workplace requirements. Completed |
Evidence:
|