The important thing to remember when gathering evidence is that the more evidence the better - that is, the more evidence you gather to demonstrate your skills, the more confident an assessor can be that you have learned the skills not just at one point in time, but are continuing to apply and develop those skills (as opposed to just learning for the test!). Furthermore, one piece of evidence that you collect will not usualy demonstrate all the required criteria for a unit of competency, whereas multiple overlapping pieces of evidence will usually do the trick!
From the Wiki University
What evidence can you provide to prove your understanding of each of the following citeria?
Prepare for work.
|
|
Irrigation plans and specifications are obtained and site is inspected. Completed |
Evidence:
|
Safety (OHS) requirements associated with installing and commissioning domestic irrigation pumps, and workplace environmental requirements, are adhered to throughout the work. Completed |
Evidence:
|
Quality assurance requirements are identified and adhered to in accordance with workplace requirements. Completed |
Evidence:
|
Tasks are planned and sequenced in conjunction with others involved in or affected by the work and statutory and regulatory authority requirements. Completed |
Evidence:
|
Tools and equipment for installing and commissioning domestic irrigation pumps, including personal protective equipment, are selected and checked for serviceability. Completed |
Evidence:
|
Work area is prepared to support efficient installation and commissioning of domestic irrigation pumps. Completed |
Evidence:
|
Identify installation requirements.
|
|
Irrigation system requirements are identified from plans, specifications and relevant information. Completed |
Evidence:
|
Pump and installation materials are selected according to type, installation, range of flow rates, operating head and delivery distance. Completed |
Evidence:
|
Pump is identified, ordered and collected in accordance with workplace procedures. Completed |
Evidence:
|
Pump is checked for compliance with standards, docket and order form, and for acceptable condition. Completed |
Evidence:
|
Install and commission pump.
|
|
Pump set out position is compliant with irrigation plans and manufacturer recommendations. Completed |
Evidence:
|
Pump base is installed in accordance with plans and specifications. Completed |
Evidence:
|
Pump is fitted onto base, aligned to mark out and fastened and fixed into position. Completed |
Evidence:
|
Suction line is connected to pump in accordance with specifications and manufacturer recommendations. Completed |
Evidence:
|
Discharge line is connected to pump in accordance with specifications and manufacturer recommendations. Completed |
Evidence:
|
Piping and pump is pressure tested in accordance with manufacturer specifications. Completed |
Evidence:
|
Operation of pump is tested and adjusted to achieve effective operation in accordance with manufacturer specifications. Completed |
Evidence:
|
Details of test data are recorded and documented in format required by quality assurance procedures. Completed |
Evidence:
|
Clean up.
|
|
Work area is cleared and materials disposed of or recycled in accordance with state and territory legislation and workplace procedures. Completed |
Evidence:
|
Tools and equipment are cleaned, checked, maintained and stored in accordance with manufacturer recommendations and workplace procedures. Completed |
Evidence:
|
Documentation is completed in accordance with workplace requirements. Completed |
Evidence:
|