The important thing to remember when gathering evidence is that the more evidence the better - that is, the more evidence you gather to demonstrate your skills, the more confident an assessor can be that you have learned the skills not just at one point in time, but are continuing to apply and develop those skills (as opposed to just learning for the test!). Furthermore, one piece of evidence that you collect will not usualy demonstrate all the required criteria for a unit of competency, whereas multiple overlapping pieces of evidence will usually do the trick!
From the Wiki University
What evidence can you provide to prove your understanding of each of the following citeria?
Evaluate design parameters.
|
|
Scope of work is established for vacuum sewerage systems for wide span and high-rise building projects. Completed |
Evidence:
|
Design requirements are determined from plans, specifications and client briefs. Completed |
Evidence:
|
Vacuum sewerage system attributes are evaluated and a cost-benefit analysis is conducted, comparing a range of pipe materials and system designs. Completed |
Evidence:
|
Statutory and regulatory requirements and Australian and New Zealand standards for the design of vacuum sewerage systems are analysed and applied. Completed |
Evidence:
|
Manufacturer requirements and trade and technical manuals are interpreted. Completed |
Evidence:
|
Additional research, including a desktop study, is conducted to outline design parameters. Completed |
Evidence:
|
Performance requirements are established. Completed |
Evidence:
|
Plan and detail system components.
|
|
Layout of pipework systems and type and location of fittings and valves are planned. Completed |
Evidence:
|
Sewerage loading is calculated using a range of approved methods. Completed |
Evidence:
|
Pipe size calculations are performed for a range of applications in accordance with regulations and manufacturer requirements. Completed |
Evidence:
|
Pipe fixings are designed for a range of applications. Completed |
Evidence:
|
Pumpwell, pump and pump control requirements are sized and detailed. Completed |
Evidence:
|
Approved materials, jointing methods and installation requirements for vacuum sewerage systems are specified. Completed |
Evidence:
|
Design and size systems.
|
|
Vacuum sewerage systems are designed for a range of applications. Completed |
Evidence:
|
Vacuum sewerage systems are designed and sized using computer software packages. Completed |
Evidence:
|
Prepare documentation.
|
|
Plans are prepared for a range of vacuum sewerage systems. Completed |
Evidence:
|
Specification for a vacuum sewerage system is prepared. Completed |
Evidence:
|
Testing and commissioning schedule is prepared. Completed |
Evidence:
|
Operation and maintenance manual is produced. Completed |
Evidence:
|