The important thing to remember when gathering evidence is that the more evidence the better - that is, the more evidence you gather to demonstrate your skills, the more confident an assessor can be that you have learned the skills not just at one point in time, but are continuing to apply and develop those skills (as opposed to just learning for the test!). Furthermore, one piece of evidence that you collect will not usualy demonstrate all the required criteria for a unit of competency, whereas multiple overlapping pieces of evidence will usually do the trick!

From the Wiki University

 

DEFMIL094 - Assist in the preparation, construction and maintenance of roads and tracks

What evidence can you provide to prove your understanding of each of the following citeria?

Plan and prepare for construction

  1. Select and wear appropriate personal protective equipment.
  2. Select and check for serviceability tools and equipment required for the job and report any faults to the supervisor.
  3. Lay out road/track line and clear it of vegetation and obstructions.
Select and wear appropriate personal protective equipment.

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Select and check for serviceability tools and equipment required for the job and report any faults to the supervisor.

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Lay out road/track line and clear it of vegetation and obstructions.

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Construct road/track sub base

  1. Remove soil manually or with the assistance of plant support to establish a base of suitable width, slope and stability.
  2. Coordinate soil and waste removal with plant operators and dump or store.
  3. Compact or stabilise soil (chemically or mechanically) with the assistance of plant support.
  4. Make provision for drainage and crossing points progressively.
Remove soil manually or with the assistance of plant support to establish a base of suitable width, slope and stability.

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Coordinate soil and waste removal with plant operators and dump or store.

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Compact or stabilise soil (chemically or mechanically) with the assistance of plant support.

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Make provision for drainage and crossing points progressively.

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Construct road/track surface and drainage

  1. Transfer, spread, compact and lay/fix road/track base and other surface materials to meet the planned road/track design.
  2. Provide drains and establish water runoff.
Transfer, spread, compact and lay/fix road/track base and other surface materials to meet the planned road/track design.

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Provide drains and establish water runoff.

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Construct crossings

  1. Cut and prepare road/track surface at crossing point using appropriate compaction.
  2. Install culverts in accordance with the predicted volume of water.
  3. Place, backfill and compact pipes or cords.
Cut and prepare road/track surface at crossing point using appropriate compaction.

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Install culverts in accordance with the predicted volume of water.

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Place, backfill and compact pipes or cords.

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Maintain road/track and refurbish work site

  1. Monitor condition of road/track in relation to volume of traffic, loads and expected future requirements.
  2. Identify and repair or report damage likely to lead to safety or environmental issues.
  3. Plan and carry out normal wear and tear damage repair with minimal disruption to other activities.
  4. Identify and modify ineffective drainage.
Monitor condition of road/track in relation to volume of traffic, loads and expected future requirements.

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Identify and repair or report damage likely to lead to safety or environmental issues.

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Plan and carry out normal wear and tear damage repair with minimal disruption to other activities.

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Identify and modify ineffective drainage.

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Plan and prepare for construction

  1. Select and wear appropriate personal protective equipment.
  2. Select and check for serviceability tools and equipment required for the job and report any faults to the supervisor.
  3. Lay out road/track line and clear it of vegetation and obstructions.
Select and wear appropriate personal protective equipment.

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Select and check for serviceability tools and equipment required for the job and report any faults to the supervisor.

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Lay out road/track line and clear it of vegetation and obstructions.

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Construct road/track sub base

  1. Remove soil manually or with the assistance of plant support to establish a base of suitable width, slope and stability.
  2. Coordinate soil and waste removal with plant operators and dump or store.
  3. Compact or stabilise soil (chemically or mechanically) with the assistance of plant support.
  4. Make provision for drainage and crossing points progressively.
Remove soil manually or with the assistance of plant support to establish a base of suitable width, slope and stability.

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Coordinate soil and waste removal with plant operators and dump or store.

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Compact or stabilise soil (chemically or mechanically) with the assistance of plant support.

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Make provision for drainage and crossing points progressively.

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Construct road/track surface and drainage

  1. Transfer, spread, compact and lay/fix road/track base and other surface materials to meet the planned road/track design.
  2. Provide drains and establish water runoff.
Transfer, spread, compact and lay/fix road/track base and other surface materials to meet the planned road/track design.

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Provide drains and establish water runoff.

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Construct crossings

  1. Cut and prepare road/track surface at crossing point using appropriate compaction.
  2. Install culverts in accordance with the predicted volume of water.
  3. Place, backfill and compact pipes or cords.
Cut and prepare road/track surface at crossing point using appropriate compaction.

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Install culverts in accordance with the predicted volume of water.

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Place, backfill and compact pipes or cords.

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Maintain road/track and refurbish work site

  1. Monitor condition of road/track in relation to volume of traffic, loads and expected future requirements.
  2. Identify and repair or report damage likely to lead to safety or environmental issues.
  3. Plan and carry out normal wear and tear damage repair with minimal disruption to other activities.
  4. Identify and modify ineffective drainage.
Monitor condition of road/track in relation to volume of traffic, loads and expected future requirements.

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Identify and repair or report damage likely to lead to safety or environmental issues.

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Plan and carry out normal wear and tear damage repair with minimal disruption to other activities.

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Identify and modify ineffective drainage.

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Assessed

Teacher: ___________________________________ Date: _________

Signature: ________________________________________________

Comments:

 

 

 

 

 

 

 

 

Instructions to Assessors

Evidence Guide

ELEMENTS

PERFORMANCE CRITERIA

Elements describe the essential outcomes

Performance criteria describe the performance needed to demonstrate achievement of the element. Where bold italicised text is used, further information is detailed in the range of conditions section.

1. Plan and prepare for construction

1.1 Select and wear appropriate personal protective equipment.

1.2 Select and check for serviceability tools and equipment required for the job and report any faults to the supervisor.

1.3 Lay out road/track line and clear it of vegetation and obstructions.

2. Construct road/track sub base

2.1 Remove soil manually or with the assistance of plant support to establish a base of suitable width, slope and stability.

2.2 Coordinate soil and waste removal with plant operators and dump or store.

2.3 Compact or stabilise soil (chemically or mechanically) with the assistance of plant support.

2.4 Make provision for drainage and crossing points progressively.

3. Construct road/track surface and drainage

3.1 Transfer, spread, compact and lay/fix road/track base and other surface materials to meet the planned road/track design.

3.2 Provide drains and establish water runoff.

4. Construct crossings

4.1 Cut and prepare road/track surface at crossing point using appropriate compaction.

4.2 Install culverts in accordance with the predicted volume of water.

4.3 Place, backfill and compact pipes or cords.

5. Maintain road/track and refurbish work site

5.1 Monitor condition of road/track in relation to volume of traffic, loads and expected future requirements.

5.2 Identify and repair or report damage likely to lead to safety or environmental issues.

5.3 Plan and carry out normal wear and tear damage repair with minimal disruption to other activities.

5.4 Identify and modify ineffective drainage.

Required Skills and Knowledge

ELEMENTS

PERFORMANCE CRITERIA

Elements describe the essential outcomes

Performance criteria describe the performance needed to demonstrate achievement of the element. Where bold italicised text is used, further information is detailed in the range of conditions section.

1. Plan and prepare for construction

1.1 Select and wear appropriate personal protective equipment.

1.2 Select and check for serviceability tools and equipment required for the job and report any faults to the supervisor.

1.3 Lay out road/track line and clear it of vegetation and obstructions.

2. Construct road/track sub base

2.1 Remove soil manually or with the assistance of plant support to establish a base of suitable width, slope and stability.

2.2 Coordinate soil and waste removal with plant operators and dump or store.

2.3 Compact or stabilise soil (chemically or mechanically) with the assistance of plant support.

2.4 Make provision for drainage and crossing points progressively.

3. Construct road/track surface and drainage

3.1 Transfer, spread, compact and lay/fix road/track base and other surface materials to meet the planned road/track design.

3.2 Provide drains and establish water runoff.

4. Construct crossings

4.1 Cut and prepare road/track surface at crossing point using appropriate compaction.

4.2 Install culverts in accordance with the predicted volume of water.

4.3 Place, backfill and compact pipes or cords.

5. Maintain road/track and refurbish work site

5.1 Monitor condition of road/track in relation to volume of traffic, loads and expected future requirements.

5.2 Identify and repair or report damage likely to lead to safety or environmental issues.

5.3 Plan and carry out normal wear and tear damage repair with minimal disruption to other activities.

5.4 Identify and modify ineffective drainage.

Evidence required to demonstrate competence must satisfy all of the requirements of the elements and performance criteria. If not otherwise specified the candidate must demonstrate evidence of performance of the following on at least one occasion.

using power tools, hand tools, small plant and other engineering equipment

measuring relative to the construction process

using expedient and improvised construction methods and materials

following instructions/directives and reporting information

reading and interpreting job instructions, procedures manuals, job guides, field engineering pamphlets, technical specifications, manufacturer’s specifications, plans, maps and overlays

Evidence required to demonstrate competence must satisfy all of the requirements of the elements and performance criteria. If not otherwise specified the depth of knowledge demonstrated must be appropriate to the job context of the candidate.

workplace and equipment safety requirements

capabilities of small plant and equipment

materials handling and storage

expedient and improvised construction methods

composition of teams and roles and responsibilities of team members

basic numeracy required to determine linear measurement, and number and placement of pegs