The important thing to remember when gathering evidence is that the more evidence the better - that is, the more evidence you gather to demonstrate your skills, the more confident an assessor can be that you have learned the skills not just at one point in time, but are continuing to apply and develop those skills (as opposed to just learning for the test!). Furthermore, one piece of evidence that you collect will not usualy demonstrate all the required criteria for a unit of competency, whereas multiple overlapping pieces of evidence will usually do the trick!
From the Wiki University
What evidence can you provide to prove your understanding of each of the following citeria?
Prepare for cutting
|
|
Applicable occupational health and safety (OHS), environmental, legislative and organisational requirements relevant to cutting material using high speed optimiser are identified and followed Completed |
Evidence:
|
Job requirements are obtained from work order or computer download in line with site procedures Completed |
Evidence:
|
Materials suitable for cutting to length and angles are obtained from pre-selected order or identified from available stock Completed |
Evidence:
|
Program requirements are selected and loaded, and machine cycle is checked in line with site procedures Completed |
Evidence:
|
Material cutting patterns and saw setup sequences are identified to enable loading of boards for cutting Completed |
Evidence:
|
Cutting equipment is checked, adjustments made where necessary, and started in line with manufacturer recommendations and site procedures Completed |
Evidence:
|
Communication with others is established and maintained in line with OHS requirements Completed |
Evidence:
|
Operate programmed machinery
|
|
Materials are loaded and machinery is operated in line with planned cutting sequence, specifications and OHS requirements Completed |
Evidence:
|
First board cut after setup is checked for length and angle to site or order tolerances, and setup is adjusted as required Completed |
Evidence:
|
Equipment lock-out procedures are applied in line with OHS requirements and site procedures Completed |
Evidence:
|
Off-cuts and rejected boards are identified, segregated and disposed of in line with site procedures and environmental requirements Completed |
Evidence:
|
Problems are identified, assessed and resolved or promptly reported in line with site procedures Completed |
Evidence:
|
Monitor and adjust processing
|
|
Processing is regularly monitored and minor problems are resolved in line with OHS requirements, site procedures and tolerances Completed |
Evidence:
|
Equipment is maintained in line with OHS requirements, site procedures and manufacturer recommendations Completed |
Evidence:
|
Major problems and equipment faults are promptly reported in line with site procedures Completed |
Evidence:
|
Work area is regularly cleared of off-cuts and sawdust in line with site standards, and environmental and OHS requirements Completed |
Evidence:
|
Production and quality recordsand reports are processed in line with site procedures and organisational requirements Completed |
Evidence:
|