The important thing to remember when gathering evidence is that the more evidence the better - that is, the more evidence you gather to demonstrate your skills, the more confident an assessor can be that you have learned the skills not just at one point in time, but are continuing to apply and develop those skills (as opposed to just learning for the test!). Furthermore, one piece of evidence that you collect will not usualy demonstrate all the required criteria for a unit of competency, whereas multiple overlapping pieces of evidence will usually do the trick!
From the Wiki University
What evidence can you provide to prove your understanding of each of the following citeria?
Confirm operational status
|
|
Operational status is confirmed within Occupational Health and Safety (OHS) regulations, environmental and safe working requirements/practices, Standard Operating Procedures (SOP), and housekeeping requirements Completed |
Evidence:
|
Production requirements are checked at start of shift to plan the daily activities as required Completed |
Evidence:
|
Continuing process supplies are maintained Completed |
Evidence:
|
Combustion processes are confirmed to be within operational specifications Completed |
Evidence:
|
Boiler performance is recorded in the operational log Completed |
Evidence:
|
Operational status is communicated to relevant personnel Completed |
Evidence:
|
Monitor and control boiler and ancillary plant operation
|
|
Boiler and ancillary plant operation is monitored and controlled within OHS regulations, environmental and safe working requirements/practices, SOP, and housekeeping requirements Completed |
Evidence:
|
Operational status is confirmed by inspection, observations and other information Completed |
Evidence:
|
Water quality tests are conducted and chemical addition adjusted as required Completed |
Evidence:
|
Steam pressures are monitored and maintained as required Completed |
Evidence:
|
Fuel efficiency calculations and recordings are made Completed |
Evidence:
|
Boiler control adjustments are made to maintain operation within specification Completed |
Evidence:
|
Pre-treatment systems for water to be monitored, tested and maintained are made up Completed |
Evidence:
|
Steam distribution systems are monitored and maintained to client requirements Completed |
Evidence:
|
Operator level maintenance is carried out as required Completed |
Evidence:
|
Handover boiler operations
|
|
Handover of boiler operations is completed within OHS regulations, environmental and safe working requirements/practices, SOP, and housekeeping requirements Completed |
Evidence:
|
Workplace records are maintained in accordance with statutory requirements and workplace procedures Completed |
Evidence:
|
Handover is carried out according to workplace procedure Completed |
Evidence:
|
Boiler operators are aware of boiler status and related equipment at completion of handover Completed |
Evidence:
|
Record and document boiler and plant performance
|
|
Boiler and plant performance is recorded and documented within OHS regulations, environmental and safe working requirements/practices, SOP, and housekeeping requirements Completed |
Evidence:
|
Operating log is maintained Completed |
Evidence:
|
Maintenance requirements are identified and documented as required Completed |
Evidence:
|