The important thing to remember when gathering evidence is that the more evidence the better - that is, the more evidence you gather to demonstrate your skills, the more confident an assessor can be that you have learned the skills not just at one point in time, but are continuing to apply and develop those skills (as opposed to just learning for the test!). Furthermore, one piece of evidence that you collect will not usualy demonstrate all the required criteria for a unit of competency, whereas multiple overlapping pieces of evidence will usually do the trick!
From the Wiki University
What evidence can you provide to prove your understanding of each of the following citeria?
Set up and prepare for working with live fibre
|
|
Obtain relevant legislation, codes, regulations and standards for compliance when conducting work Completed |
Evidence:
|
Scope work by obtaining project plan from appropriate personnel and arrange for site access to comply with security arrangements Completed |
Evidence:
|
Notify appropriate personnel of identified safety hazards at worksite Completed |
Evidence:
|
Determine type of FTTx equipment, components of optical distribution network (ODN) and WDM components from project plan for testing and commissioning Completed |
Evidence:
|
Obtain tools and safety equipment and materials to perform tasks safely and efficiently Completed |
Evidence:
|
Select and use required protective equipment and make site safe and secure for commissioning work Completed |
Evidence:
|
Create safe working environment by following safe work practices and identifying optical fibre hazards that could cause injuries when handling optical fibres and laser based equipment Completed |
Evidence:
|
Connect splitter input fibre to feeder cable
|
|
Follow workplace health and safety (WHS) and environmental requirements for given work, and identify and avoid other services Completed |
Evidence:
|
Locate feeder fibre port to be connected Completed |
Evidence:
|
Determine state (live or not) of fibre port to be connected and notify transmitter to ensure that power is turned off at source if fibre port is live Completed |
Evidence:
|
Connect up connectorised splitter input fibres as instructed by manufacturer Completed |
Evidence:
|
Arrange for power to be turned back on to newly connected feeder port Completed |
Evidence:
|
Perform live WDM commission testing of ODN installation used in FTTx network
|
|
Locate appropriate test points in ODN from manufacturer’s instructions for WDM testing Completed |
Evidence:
|
Test live wavelengths for WDM tests following safety precautions Completed |
Evidence:
|
Test optical signal strengths for operating wavelengths incoming into optical network termination (ONT) and determine if signal strengths are within range of acceptable power levels Completed |
Evidence:
|
Test losses between WDM outputs and individual line multiplexers (LM) for each wavelength, and determine if within maximum and minimum power losses Completed |
Evidence:
|
Conduct all acceptance tests as specified by manufacturer Completed |
Evidence:
|
Record and tabulate all test results for commissioning requirements Completed |
Evidence:
|
Clean up worksite
|
|
Seal and secure any enclosures and cabinets Completed |
Evidence:
|
Remove waste and debris from worksite and dispose of according to environmental requirements Completed |
Evidence:
|
Notify appropriate personnel of job completion and obtain sign off Completed |
Evidence:
|