The important thing to remember when gathering evidence is that the more evidence the better - that is, the more evidence you gather to demonstrate your skills, the more confident an assessor can be that you have learned the skills not just at one point in time, but are continuing to apply and develop those skills (as opposed to just learning for the test!). Furthermore, one piece of evidence that you collect will not usualy demonstrate all the required criteria for a unit of competency, whereas multiple overlapping pieces of evidence will usually do the trick!
From the Wiki University
What evidence can you provide to prove your understanding of each of the following citeria?
Set up and prepare to work with live fibre
|
|
Scope work by obtaining project plan from appropriate personnel, and arrange for site access to comply with security arrangements Completed |
Evidence:
|
Identify hazards, assess work health and safety (WHS) risks, and implement control measures according to workplace procedures Completed |
Evidence:
|
Notify appropriate personnel of identified worksite safety hazards Completed |
Evidence:
|
Determine FTTx equipment, components of optical distribution network (ODN) and WDM components, from project plan, for testing and commissioning Completed |
Evidence:
|
Obtain required tools, safety equipment and materials to perform tasks safely and efficiently Completed |
Evidence:
|
Select and use required personal protective equipment, and make site safe and secure for commissioning work Completed |
Evidence:
|
Connect splitter input fibre to feeder cable
|
|
Identify and avoid disconnection of other services Completed |
Evidence:
|
Monitor implementation of control measures and revise as necessary Completed |
Evidence:
|
Locate feeder fibre port to be connected Completed |
Evidence:
|
Ensure power is turned off at source Completed |
Evidence:
|
Connect connectorised splitter input fibres according to manufacturer specifications Completed |
Evidence:
|
Arrange for power to be turned back on to newly connected feeder port Completed |
Evidence:
|
Perform live WDM commission testing of ODN installation used in FTTx network
|
|
Locate appropriate test points in ODN from manufacturer instructions for WDM testing Completed |
Evidence:
|
Test live wavelengths for WDM tests according to safety precautions Completed |
Evidence:
|
Test optical signal strengths for operating wavelengths incoming into optical network termination (ONT) and determine if signal strengths are within range of acceptable power levels Completed |
Evidence:
|
Test losses between WDM outputs and individual line multiplexers (LM) for each wavelength, and determine if within maximum and minimum power losses Completed |
Evidence:
|
Conduct all manufacturer specified acceptance tests Completed |
Evidence:
|
Record and tabulate all test results for commissioning requirements Completed |
Evidence:
|
Complete installation process
|
|
Seal and secure any enclosures and cabinets Completed |
Evidence:
|
Remove waste and debris from worksite and dispose of according to environmental requirements Completed |
Evidence:
|
Notify appropriate personnel of job completion and obtain sign-off Completed |
Evidence:
|