The important thing to remember when gathering evidence is that the more evidence the better - that is, the more evidence you gather to demonstrate your skills, the more confident an assessor can be that you have learned the skills not just at one point in time, but are continuing to apply and develop those skills (as opposed to just learning for the test!). Furthermore, one piece of evidence that you collect will not usualy demonstrate all the required criteria for a unit of competency, whereas multiple overlapping pieces of evidence will usually do the trick!
From the Wiki University
What evidence can you provide to prove your understanding of each of the following citeria?
Prepare for installation of underground enclosure and conduit
|
|
Obtain construction design plan from appropriate personnel and determine and obtain type of underground enclosure specified Completed |
Evidence:
|
Arrange access to site according to required enterprise procedure Completed |
Evidence:
|
Inform appropriate personnel of existing and potential worksite hazards Completed |
Evidence:
|
Verify location of proposed installation according to appropriate plans obtained from authorised personnel Completed |
Evidence:
|
Obtain information about location of other services from relevant authorities Completed |
Evidence:
|
Organise plant, tools and equipment for given work and safe work practice Completed |
Evidence:
|
Place recognised barriers during construction according to safety and enterprise requirements Completed |
Evidence:
|
Install enclosure and conduit
|
|
Excavate site, maintaining stability and allowing ease of access Completed |
Evidence:
|
Install enclosure or pit according to design specifications, and work health and safety (WHS) and environmental requirements Completed |
Evidence:
|
Install conduit according to specifications and manufacturer requirements, ensuring internal surfaces are free from impediments and sharp edges for cable hauling Completed |
Evidence:
|
Seal conduit entry into enclosure against foreign matter Completed |
Evidence:
|
Install cable support structure and access facilities in pits according to specifications Completed |
Evidence:
|
Restore site and complete documentation
|
|
Complete backfill safely using suitable soil and materials that ensure conduit protection Completed |
Evidence:
|
Recover obsolete materials and equipment and return to appropriate point for disposal Completed |
Evidence:
|
Restore site according to requirements of enterprise or approving authority and customer satisfaction Completed |
Evidence:
|
Complete reports on installation and design amendments accurately and file promptly according to enterprise requirements Completed |
Evidence:
|
Notify appropriate personnel of job completion and obtain sign-off Completed |
Evidence:
|