Tips for gathering evidence to demonstrate your skills

The important thing to remember when gathering evidence is that the more evidence the better - that is, the more evidence you gather to demonstrate your skills, the more confident an assessor can be that you have learned the skills not just at one point in time, but are continuing to apply and develop those skills (as opposed to just learning for the test!). Furthermore, one piece of evidence that you collect will not usualy demonstrate all the required criteria for a unit of competency, whereas multiple overlapping pieces of evidence will usually do the trick!

From the Wiki University

 

ICTPMG401 - Support small scale ICT projects

What evidence can you provide to prove your understanding of each of the following citeria?

Support project commencement

  1. Confirm business opportunity to ensure the project objectives are understood
  2. Identify stakeholders and gather requirements
  3. Prepare a project charter or project proposal and obtain agreement from project sponsor
Confirm business opportunity to ensure the project objectives are understood

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Identify stakeholders and gather requirements

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Prepare a project charter or project proposal and obtain agreement from project sponsor

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Support project plan development

  1. Break down the requirements to identify tasks and resources needed to complete the project plan
  2. Compile a schedule of project tasks, including realistic timeframes and costs if required
  3. Allocate task responsibilities to project team members
  4. Agree on a process with the sponsor to manage risks or unexpected events that may arise and affect project objectives
Break down the requirements to identify tasks and resources needed to complete the project plan

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Compile a schedule of project tasks, including realistic timeframes and costs if required

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Allocate task responsibilities to project team members

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Agree on a process with the sponsor to manage risks or unexpected events that may arise and affect project objectives

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Support project completion

  1. Work with project team to ensure project activities meet timeframe, scope, cost and quality expectations
  2. Monitor and control project risks and issues according to the agreed process
  3. Verify that project deliverables meet project expectations and sign off as complete
  4. Train users, if applicable
Work with project team to ensure project activities meet timeframe, scope, cost and quality expectations

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Monitor and control project risks and issues according to the agreed process

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Verify that project deliverables meet project expectations and sign off as complete

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Train users, if applicable

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Support project closure

  1. Prepare ICT support or maintenance documents if applicable
  2. Obtain final project sign-off from sponsor and key stakeholders
  3. Document lessons learned and close the project
Prepare ICT support or maintenance documents if applicable

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Obtain final project sign-off from sponsor and key stakeholders

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Document lessons learned and close the project

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Assessed

Teacher: ___________________________________ Date: _________

Signature: ________________________________________________

Comments:

 

 

 

 

 

 

 

 

Instructions to Assessors

Evidence Guide

ELEMENT

PERFORMANCE CRITERIA

Elements describe the essential outcomes.

Performance criteria describe the performance needed to demonstrate achievement of the element.

1. Support project commencement

1.1 Confirm business opportunity to ensure the project objectives are understood

1.2 Identify stakeholders and gather requirements

1.3 Prepare a project charter or project proposal and obtain agreement from project sponsor

2. Support project plan development

2.1 Break down the requirements to identify tasks and resources needed to complete the project plan

2.2 Compile a schedule of project tasks, including realistic timeframes and costs if required

2.3 Allocate task responsibilities to project team members

2.4 Agree on a process with the sponsor to manage risks or unexpected events that may arise and affect project objectives

3. Support project completion

3.1 Work with project team to ensure project activities meet timeframe, scope, cost and quality expectations

3.2 Monitor and control project risks and issues according to the agreed process

3.3 Verify that project deliverables meet project expectations and sign off as complete

3.4 Train users, if applicable

4. Support project closure

4.1 Prepare ICT support or maintenance documents if applicable

4.2 Obtain final project sign-off from sponsor and key stakeholders

4.3 Document lessons learned and close the project

Required Skills and Knowledge

ELEMENT

PERFORMANCE CRITERIA

Elements describe the essential outcomes.

Performance criteria describe the performance needed to demonstrate achievement of the element.

1. Support project commencement

1.1 Confirm business opportunity to ensure the project objectives are understood

1.2 Identify stakeholders and gather requirements

1.3 Prepare a project charter or project proposal and obtain agreement from project sponsor

2. Support project plan development

2.1 Break down the requirements to identify tasks and resources needed to complete the project plan

2.2 Compile a schedule of project tasks, including realistic timeframes and costs if required

2.3 Allocate task responsibilities to project team members

2.4 Agree on a process with the sponsor to manage risks or unexpected events that may arise and affect project objectives

3. Support project completion

3.1 Work with project team to ensure project activities meet timeframe, scope, cost and quality expectations

3.2 Monitor and control project risks and issues according to the agreed process

3.3 Verify that project deliverables meet project expectations and sign off as complete

3.4 Train users, if applicable

4. Support project closure

4.1 Prepare ICT support or maintenance documents if applicable

4.2 Obtain final project sign-off from sponsor and key stakeholders

4.3 Document lessons learned and close the project

Evidence of the ability to:

develop a project plan appropriate to the project objectives and the project proposal

support the initiation, control and completion of a simple small-scale information and communications technology (ICT) project

identify and apply requirements and expectations of a project according to the project plan.

Note: If a specific volume or frequency is not stated, then evidence must be provided at least once.

To complete the unit requirements safely and effectively, the individual must:

identify the different project-management and planning methods and tools

explain the characteristics of technical teams

describe the different methods of communication and communication styles, including interviewing techniques

explain the organisational values, policies and processes that may be relevant to the project

describe the risks associated with small scale projects including:

cost

scope

timelines.