The important thing to remember when gathering evidence is that the more evidence the better - that is, the more evidence you gather to demonstrate your skills, the more confident an assessor can be that you have learned the skills not just at one point in time, but are continuing to apply and develop those skills (as opposed to just learning for the test!). Furthermore, one piece of evidence that you collect will not usualy demonstrate all the required criteria for a unit of competency, whereas multiple overlapping pieces of evidence will usually do the trick!
From the Wiki University
What evidence can you provide to prove your understanding of each of the following citeria?
Identify maintenance/ project and plant requirements
|
|
Analyse relevant company records to determine activities which have been scheduled for the shutdown Completed |
Evidence:
|
Obtain information on maintenance activities intended for the shutdown. Completed |
Evidence:
|
Obtain information on production activities intended for the shutdown Completed |
Evidence:
|
Obtain information on projects or construction activities intended for the shutdown Completed |
Evidence:
|
Compile a list of all activities intended for the shutdown, including sufficient detail to allow for shutdown planning Completed |
Evidence:
|
Negotiate conflicts between proposed activities Completed |
Evidence:
|
Identify tasks, timelines and resources
|
|
Break down each agreed shutdown activity into required tasks Completed |
Evidence:
|
Determine time, people, material, other resources required and 'owner' for each task Completed |
Evidence:
|
Determine prerequisite tasks for each task Completed |
Evidence:
|
Identify conflicts between tasks arising from resources or other causes Completed |
Evidence:
|
Negotiate conflicts between tasks Completed |
Evidence:
|
Compile database of all tasks and their requirements Completed |
Evidence:
|
Develop schedule
|
|
Develop draft shutdown schedule, including planning activities Completed |
Evidence:
|
Determine critical path or similar for shutdown tasks Completed |
Evidence:
|
Analyse tasks on critical path to determine methods of reducing critical path Completed |
Evidence:
|
Develop revised schedule Completed |
Evidence:
|
Consult with all relevant stakeholders and analyse revised schedule for conflicts and possible savings Completed |
Evidence:
|
Negotiate conflicts Completed |
Evidence:
|
Develop final schedule and critical path or similar Completed |
Evidence:
|
Communicate with all relevant stakeholders
|
|
Contribute to shutdown planning meetings with stakeholders Completed |
Evidence:
|
Meet with stakeholders individually Completed |
Evidence:
|
Prepare reports and documents as required Completed |
Evidence:
|
Ensure all permissions required for tasks have been obtained Completed |
Evidence:
|
Liaise with suppliers and contractors to obtain parts, materials and services Completed |
Evidence:
|
Monitor shutdown
|
|
Establish systems to allow monitoring of shutdown to schedule Completed |
Evidence:
|
Monitor progress to schedule Completed |
Evidence:
|
Identify causes of not meeting schedule Completed |
Evidence:
|
Negotiate a solution to cause Completed |
Evidence:
|
Adjust schedule to meet changed circumstances but still meet overall timeline (if at all possible) Completed |
Evidence:
|