NTISthis.com

Evidence Guide: PMASUP246 - Disconnect and reconnect non-flared tube fitting joints

Student: __________________________________________________

Signature: _________________________________________________

Tips for gathering evidence to demonstrate your skills

The important thing to remember when gathering evidence is that the more evidence the better - that is, the more evidence you gather to demonstrate your skills, the more confident an assessor can be that you have learned the skills not just at one point in time, but are continuing to apply and develop those skills (as opposed to just learning for the test!). Furthermore, one piece of evidence that you collect will not usualy demonstrate all the required criteria for a unit of competency, whereas multiple overlapping pieces of evidence will usually do the trick!

From the Wiki University

 

PMASUP246 - Disconnect and reconnect non-flared tube fitting joints

What evidence can you provide to prove your understanding of each of the following citeria?

Plan and prepare for job

  1. Identify work requirements
  2. Inspect job site
  3. Confirm isolations have been completed to standard
  4. Confirm hazard controls
  5. Coordinate with appropriate personnel
  6. Select appropriate tools
  7. Re-check that work requirements fit within skill level
  8. Complete required checklists and records
Identify work requirements

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Inspect job site

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Confirm isolations have been completed to standard

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Confirm hazard controls

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Coordinate with appropriate personnel

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Select appropriate tools

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Re-check that work requirements fit within skill level

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Complete required checklists and records

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Disconnect tube fitting in accordance with procedures

  1. Implement hazard controls
  2. Prepare tools, drip trays, and so on, with appropriate care
  3. Undo support clamps as required
  4. Vent as required
  5. Break joint and drain tube as required
  6. Identify any skills escalation required
  7. Manage open pipe to ensure contents are not contaminated or damaged
  8. Complete checklists and records as required
Implement hazard controls

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Prepare tools, drip trays, and so on, with appropriate care

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Undo support clamps as required

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Vent as required

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Break joint and drain tube as required

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Identify any skills escalation required

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Manage open pipe to ensure contents are not contaminated or damaged

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Complete checklists and records as required

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Inspect tube and components

  1. Inspect fittings and tube
  2. Assess degree of misalignment and refer, as required
  3. Clean fittings as required
  4. Identify any damage or defects
  5. Confirm compliance of components and refer, as required
  6. Identify any problems and take action
Inspect fittings and tube

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Assess degree of misalignment and refer, as required

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Clean fittings as required

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Identify any damage or defects

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Confirm compliance of components and refer, as required

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Identify any problems and take action

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Reconnect tube fitting in accordance with procedures

  1. Check components are to specification
  2. Apply sealants/seals as required
  3. Assemble the joint to procedures
  4. Re-check alignment
  5. Reattach support clamps as required
  6. Complete checklists and records as required
Check components are to specification

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Apply sealants/seals as required

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Assemble the joint to procedures

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Re-check alignment

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Reattach support clamps as required

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Complete checklists and records as required

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Finish the job

  1. Make a final check of joint alignment
  2. Organise required checks
  3. Confirm joint integrity as required
  4. Complete checklists and records as required
Make a final check of joint alignment

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Organise required checks

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Confirm joint integrity as required

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Complete checklists and records as required

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Assessed

Teacher: ___________________________________ Date: _________

Signature: ________________________________________________

Comments:

 

 

 

 

 

 

 

 

Instructions to Assessors

Evidence Guide

Elements describe the essential outcomes.

Performance criteria describe the performance needed to demonstrate achievement of the element.

1

Plan and prepare for job

1.1

Identify work requirements

1.2

Inspect job site

1.3

Confirm isolations have been completed to standard

1.4

Confirm hazard controls

1.5

Coordinate with appropriate personnel

1.6

Select appropriate tools

1.7

Re-check that work requirements fit within skill level

1.8

Complete required checklists and records

2

Disconnect tube fitting in accordance with procedures

2.1

Implement hazard controls

2.2

Prepare tools, drip trays, and so on, with appropriate care

2.3

Undo support clamps as required

2.4

Vent as required

2.5

Break joint and drain tube as required

2.6

Identify any skills escalation required

2.7

Manage open pipe to ensure contents are not contaminated or damaged

2.8

Complete checklists and records as required

3

Inspect tube and components

3.1

Inspect fittings and tube

3.2

Assess degree of misalignment and refer, as required

3.3

Clean fittings as required

3.4

Identify any damage or defects

3.5

Confirm compliance of components and refer, as required

3.6

Identify any problems and take action

4

Reconnect tube fitting in accordance with procedures

4.1

Check components are to specification

4.2

Apply sealants/seals as required

4.3

Assemble the joint to procedures

4.4

Re-check alignment

4.5

Reattach support clamps as required

4.6

Complete checklists and records as required

5

Finish the job

5.1

Make a final check of joint alignment

5.2

Organise required checks

5.3

Confirm joint integrity as required

5.4

Complete checklists and records as required

Required Skills and Knowledge

Elements describe the essential outcomes.

Performance criteria describe the performance needed to demonstrate achievement of the element.

1

Plan and prepare for job

1.1

Identify work requirements

1.2

Inspect job site

1.3

Confirm isolations have been completed to standard

1.4

Confirm hazard controls

1.5

Coordinate with appropriate personnel

1.6

Select appropriate tools

1.7

Re-check that work requirements fit within skill level

1.8

Complete required checklists and records

2

Disconnect tube fitting in accordance with procedures

2.1

Implement hazard controls

2.2

Prepare tools, drip trays, and so on, with appropriate care

2.3

Undo support clamps as required

2.4

Vent as required

2.5

Break joint and drain tube as required

2.6

Identify any skills escalation required

2.7

Manage open pipe to ensure contents are not contaminated or damaged

2.8

Complete checklists and records as required

3

Inspect tube and components

3.1

Inspect fittings and tube

3.2

Assess degree of misalignment and refer, as required

3.3

Clean fittings as required

3.4

Identify any damage or defects

3.5

Confirm compliance of components and refer, as required

3.6

Identify any problems and take action

4

Reconnect tube fitting in accordance with procedures

4.1

Check components are to specification

4.2

Apply sealants/seals as required

4.3

Assemble the joint to procedures

4.4

Re-check alignment

4.5

Reattach support clamps as required

4.6

Complete checklists and records as required

5

Finish the job

5.1

Make a final check of joint alignment

5.2

Organise required checks

5.3

Confirm joint integrity as required

5.4

Complete checklists and records as required

Evidence required to demonstrate competence in this unit must be relevant to and satisfy the requirements of the elements and performance criteria, and include the ability to:

replace existing components with new components

carry out minor maintenance within own skill level

identify and report problems outside own competence

identify and control hazards related to tube fitting joints

inspect job site to confirm:

location

authorisations required

access and egress needs

recent work undertaken on joint

tube fitting type matches specification

inspect non-flared tube fitting components to check for:

contaminants

signs of damage, defects or deterioration in all components

cleanliness and correct surface roughness of mating surfaces

alignment

correct specifications.

Evidence must be provided that demonstrates knowledge of:

tube connection types as applicable

principles of how non-flared tube joints seal

tool types and applications

organisation’s tube fitting procedures

hierarchy of control

communication protocols (e.g. radio, phone, computer, paper and permissions/authorities)

routine problems, faults and their symptoms, and the corrective action to be taken

process materials and conditions at the location of the fitting

relevant environmental requirements.

Range Statement

This field allows for different work environments and conditions that may affect performance. Essential operating conditions that may be present (depending on the work situation, needs of the candidate, accessibility of the item, and local industry and regional contexts) are included.

Regulatory framework

The latest version of all legislation, regulations, industry codes of practice and Australian/international standards, or the version specified by the local regulatory authority, must be used, and include one or more of the following:

legislative requirements, including work health and safety (WHS)

industry codes of practice and guidelines

environmental regulations and guidelines

Australian and other standards

licence and certification requirements

All operations to which this unit applies are subject to stringent health, safety and environment (HSE) requirements, which may be imposed through state/territory or federal legislation, and these must not be compromised at any time. Where there is an apparent conflict between performance criteria and HSE requirements, the HSE requirements take precedence.

Procedures

All operations must be performed in accordance with relevant procedures.

Procedures are written, verbal, visual, computer-based or in some other form, include one or more of the following:

emergency procedures

work instructions

standard operating procedures (SOPs)

safe work method statements (SWMS)

formulas/recipes

batch sheets

temporary instructions

any similar instructions provided for the smooth running of the plant

Hazards

Hazards include one or more of the following:

gases and liquids under pressure

structural hazards

equipment failures

industrial (machinery, equipment and product)

equipment or product mass

plant services (steam, condensate and cooling water)

limited head spaces or overhangs

working at heights, in restricted or confined spaces, or in environments subjected to heat, dusts or vapours

flammability and explosivity

hazardous products and materials

unauthorised personnel

sharp edges, protrusions or obstructions

slippery surfaces, spills or leaks

extreme weather

other hazards that might arise

Work requirements

Work requirements may include one or more of the following:

fitting, tubing and thread specifications

fitting brand

specific sealing method and type

process line and process materials

parts and equipment required

local detectors requiring isolation

required skill level

conflicting work

Work requirements come from briefings, handovers, and work orders and include one or more of the following:

compliance documentation

product specifications

nature and scope of tasks

achievement targets

operational conditions

lighting conditions

plant or equipment defects

hazards and potential hazards

coordination requirements or issues

Job site

Inspecting job site includes identifying one or more of the following:

location

authorisations required

access and egress needs

hazards

recent work undertaken on joint

fitting type (matches specification)

Implementing hazard controls

Implementing hazard controls includes one or more of the following:

selection and use of appropriate personal protective equipment (PPE)

obtaining appropriate authorisations

checking required isolations

controlling other work in area

controlling access to area

using gas tester

verifying and confirming isolation

safe fitting breaking procedure (line of fire)

Inspecting components

Inspecting tube fitting components includes one or more of the following:

full tube insertion

orientation of ferrules

correct tube deburring

for signs of damage, defects or deterioration in all components

confirming compliance of components

Components

Components includes, but are not limited to, one or more of the following:

fitting body

fitting nut

front ferrule

rear ferrule

tube

tube clamps and support saddles

Refer

Refer means to refer the issue to the person with the required skills, knowledge and/or authority to deal with the matter.

Checklists and records

Checklists and records include one or more of the following:

paper or electronic based

verbal/radio reports

reporting items found which require action

Action

Action in response to problems includes the following:

determining problems needing action

accessing and applying relevant technical and plant data

applying appropriate problem solving techniques to determine possible fault causes

rectifying problem using appropriate solution within area of responsibility

following through items initiated until final resolution has occurred

reporting problems outside area of responsibility/ability to resolve to designated person

Action includes one or more of the following:

replacing existing components with new components

carrying out minor maintenance within operator's skill level

identifying and reporting problems outside operator's competence

identifying and controlling hazards related to tube fitting joints

Routine problems

Routine problems must be resolved by applying known solutions.

Routine problems are predictable and include one or more of the following:

fitting leaks

blockages/build-up/fouling

erosion/wear

ancillary equipment problems

support clamps incorrectly attached

worn threads

misalignments

lack of full tube insertion

ferrule missing or reversed

incorrect installation

Known solutions are drawn from one or more of the following:

procedures

training

remembered experience

Non-routine problems must be reported according to according to relevant procedures.