NTISthis.com

Evidence Guide: RIICBS204D - Conduct aggregate spreader box operations

Student: __________________________________________________

Signature: _________________________________________________

Tips for gathering evidence to demonstrate your skills

The important thing to remember when gathering evidence is that the more evidence the better - that is, the more evidence you gather to demonstrate your skills, the more confident an assessor can be that you have learned the skills not just at one point in time, but are continuing to apply and develop those skills (as opposed to just learning for the test!). Furthermore, one piece of evidence that you collect will not usualy demonstrate all the required criteria for a unit of competency, whereas multiple overlapping pieces of evidence will usually do the trick!

From the Wiki University

 

RIICBS204D - Conduct aggregate spreader box operations

What evidence can you provide to prove your understanding of each of the following citeria?

Plan and prepare to conduct aggregate spreader box operations

  1. Access, interpret and apply aggregate spreader box operations documentation and ensure the work activity is compliant
  2. Obtain, read, interpret, clarify and confirm work requirements
  3. Identify and address potential risks, hazards and environmental issues, and implement control measures
  4. Select and wear personal protective equipment appropriate for work activities
  5. Confirm and apply environmental protection and safety requirements
  6. Obtain, interpret and implement traffic management signage requirements
  7. Select and check for faults plant, tools and equipment to carry out tasks
  8. Obtain and interpret emergency procedures, and be prepared for fire/accident/emergency
Access, interpret and apply aggregate spreader box operations documentation and ensure the work activity is compliant

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Obtain, read, interpret, clarify and confirm work requirements

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Identify and address potential risks, hazards and environmental issues, and implement control measures

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Select and wear personal protective equipment appropriate for work activities

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Confirm and apply environmental protection and safety requirements

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Obtain, interpret and implement traffic management signage requirements

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Select and check for faults plant, tools and equipment to carry out tasks

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Obtain and interpret emergency procedures, and be prepared for fire/accident/emergency

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Set up to conduct aggregate spreader box operations

  1. Place cut on/cut off paper in preparation for bitumen spraying and at the end of the spray run
  2. Connect equipment to the truck prior to operation
  3. Set spreader box to required width
  4. Check spreader box to ensure correct operation
  5. Check spreader box calibration
  6. Establish communication with the truck driver
  7. Check and record size of aggregate prior to spreading
Place cut on/cut off paper in preparation for bitumen spraying and at the end of the spray run

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Connect equipment to the truck prior to operation

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Set spreader box to required width

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Check spreader box to ensure correct operation

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Check spreader box calibration

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Establish communication with the truck driver

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Check and record size of aggregate prior to spreading

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Spread aggregate

  1. Remove cut on/cut off paper in preparation for aggregate spreading
  2. Coordinate opening and closing of the spreader box accurately with speed and application of aggregate
  3. Instruct driver to adjust speed, line or angle of body as required
  4. Monitor spread rate and make adjustments
  5. Complete spreading
Remove cut on/cut off paper in preparation for aggregate spreading

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Coordinate opening and closing of the spreader box accurately with speed and application of aggregate

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Instruct driver to adjust speed, line or angle of body as required

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Monitor spread rate and make adjustments

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Complete spreading

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Perform hand spreading and spotting duties

  1. Check and correct uniformity of run as required
  2. Use correct hand spreading method
Check and correct uniformity of run as required

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Use correct hand spreading method

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Disconnect and clean up

  1. Disconnect spreader box after operation
  2. Check to ensure truck is completely free of spreader and the spreader has all connecting parts correctly positioned for transportation or further use
  3. Clear work area and dispose of or recycle materials
  4. Clean, check, maintain and store plant, tools and equipment
  5. Carry out housekeeping requirements
Disconnect spreader box after operation

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Check to ensure truck is completely free of spreader and the spreader has all connecting parts correctly positioned for transportation or further use

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Clear work area and dispose of or recycle materials

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Clean, check, maintain and store plant, tools and equipment

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Carry out housekeeping requirements

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Plan and prepare to conduct aggregate spreader box operations

  1. Access, interpret and apply aggregate spreader box operations documentation and ensure the work activity is compliant
  2. Obtain, read, interpret, clarify and confirm work requirements
  3. Identify and address potential risks, hazards and environmental issues, and implement control measures
  4. Select and wear personal protective equipment appropriate for work activities
  5. Confirm and apply environmental protection and safety requirements
  6. Obtain, interpret and implement traffic management signage requirements
  7. Select and check for faults plant, tools and equipment to carry out tasks
  8. Obtain and interpret emergency procedures, and be prepared for fire/accident/emergency
Access, interpret and apply aggregate spreader box operations documentation and ensure the work activity is compliant

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Obtain, read, interpret, clarify and confirm work requirements

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Identify and address potential risks, hazards and environmental issues, and implement control measures

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Select and wear personal protective equipment appropriate for work activities

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Confirm and apply environmental protection and safety requirements

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Obtain, interpret and implement traffic management signage requirements

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Select and check for faults plant, tools and equipment to carry out tasks

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Obtain and interpret emergency procedures, and be prepared for fire/accident/emergency

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Set up to conduct aggregate spreader box operations

  1. Place cut on/cut off paper in preparation for bitumen spraying and at the end of the spray run
  2. Connect equipment to the truck prior to operation
  3. Set spreader box to required width
  4. Check spreader box to ensure correct operation
  5. Check spreader box calibration
  6. Establish communication with the truck driver
  7. Check and record size of aggregate prior to spreading
Place cut on/cut off paper in preparation for bitumen spraying and at the end of the spray run

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Connect equipment to the truck prior to operation

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Set spreader box to required width

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Check spreader box to ensure correct operation

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Check spreader box calibration

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Establish communication with the truck driver

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Check and record size of aggregate prior to spreading

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Spread aggregate

  1. Remove cut on/cut off paper in preparation for aggregate spreading
  2. Coordinate opening and closing of the spreader box accurately with speed and application of aggregate
  3. Instruct driver to adjust speed, line or angle of body as required
  4. Monitor spread rate and make adjustments
  5. Complete spreading
Remove cut on/cut off paper in preparation for aggregate spreading

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Coordinate opening and closing of the spreader box accurately with speed and application of aggregate

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Instruct driver to adjust speed, line or angle of body as required

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Monitor spread rate and make adjustments

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Complete spreading

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Perform hand spreading and spotting duties

  1. Check and correct uniformity of run as required
  2. Use correct hand spreading method
Check and correct uniformity of run as required

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Use correct hand spreading method

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Disconnect and clean up

  1. Disconnect spreader box after operation
  2. Check to ensure truck is completely free of spreader and the spreader has all connecting parts correctly positioned for transportation or further use
  3. Clear work area and dispose of or recycle materials
  4. Clean, check, maintain and store plant, tools and equipment
  5. Carry out housekeeping requirements
Disconnect spreader box after operation

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Check to ensure truck is completely free of spreader and the spreader has all connecting parts correctly positioned for transportation or further use

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Clear work area and dispose of or recycle materials

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Clean, check, maintain and store plant, tools and equipment

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Carry out housekeeping requirements

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Assessed

Teacher: ___________________________________ Date: _________

Signature: ________________________________________________

Comments:

 

 

 

 

 

 

 

 

Instructions to Assessors

Evidence Guide

1. Plan and prepare to conduct aggregate spreader box operations

1.1 Access, interpret and apply aggregate spreader box operations documentation and ensure the work activity is compliant

1.2 Obtain, read, interpret, clarify and confirm work requirements

1.3 Identify and address potential risks, hazards and environmental issues, and implement control measures

1.4 Select and wear personal protective equipment appropriate for work activities

1.5 Confirm and apply environmental protection and safety requirements

1.6 Obtain, interpret and implement traffic management signage requirements

1.7 Select and check for faults plant, tools and equipment to carry out tasks

1.8 Obtain and interpret emergency procedures, and be prepared for fire/accident/emergency

2. Set up to conduct aggregate spreader box operations

2.1 Place cut on/cut off paper in preparation for bitumen spraying and at the end of the spray run

2.2 Connect equipment to the truck prior to operation

2.3 Set spreader box to required width

2.4 Check spreader box to ensure correct operation

2.5 Check spreader box calibration

2.6 Establish communication with the truck driver

2.7 Check and record size of aggregate prior to spreading

3. Spread aggregate

3.1 Remove cut on/cut off paper in preparation for aggregate spreading

3.2 Coordinate opening and closing of the spreader box accurately with speed and application of aggregate

3.3 Instruct driver to adjust speed, line or angle of body as required

3.4 Monitor spread rate and make adjustments

3.5 Complete spreading

4. Perform hand spreading and spotting duties

4.1 Check and correct uniformity of run as required

4.2 Use correct hand spreading method

5. Disconnect and clean up

5.1 Disconnect spreader box after operation

5.2 Check to ensure truck is completely free of spreader and the spreader has all connecting parts correctly positioned for transportation or further use

5.3 Clear work area and dispose of or recycle materials

5.4 Clean, check, maintain and store plant, tools and equipment

5.5 Carry out housekeeping requirements

Required Skills and Knowledge

1. Plan and prepare to conduct aggregate spreader box operations

1.1 Access, interpret and apply aggregate spreader box operations documentation and ensure the work activity is compliant

1.2 Obtain, read, interpret, clarify and confirm work requirements

1.3 Identify and address potential risks, hazards and environmental issues, and implement control measures

1.4 Select and wear personal protective equipment appropriate for work activities

1.5 Confirm and apply environmental protection and safety requirements

1.6 Obtain, interpret and implement traffic management signage requirements

1.7 Select and check for faults plant, tools and equipment to carry out tasks

1.8 Obtain and interpret emergency procedures, and be prepared for fire/accident/emergency

2. Set up to conduct aggregate spreader box operations

2.1 Place cut on/cut off paper in preparation for bitumen spraying and at the end of the spray run

2.2 Connect equipment to the truck prior to operation

2.3 Set spreader box to required width

2.4 Check spreader box to ensure correct operation

2.5 Check spreader box calibration

2.6 Establish communication with the truck driver

2.7 Check and record size of aggregate prior to spreading

3. Spread aggregate

3.1 Remove cut on/cut off paper in preparation for aggregate spreading

3.2 Coordinate opening and closing of the spreader box accurately with speed and application of aggregate

3.3 Instruct driver to adjust speed, line or angle of body as required

3.4 Monitor spread rate and make adjustments

3.5 Complete spreading

4. Perform hand spreading and spotting duties

4.1 Check and correct uniformity of run as required

4.2 Use correct hand spreading method

5. Disconnect and clean up

5.1 Disconnect spreader box after operation

5.2 Check to ensure truck is completely free of spreader and the spreader has all connecting parts correctly positioned for transportation or further use

5.3 Clear work area and dispose of or recycle materials

5.4 Clean, check, maintain and store plant, tools and equipment

5.5 Carry out housekeeping requirements

Evidence is required to be collected that demonstrates a candidate’s competency in this unit. Evidence must be relevant to the roles within this sector’s work operations and satisfy all of the requirements of the performance criteria of this unit and include evidence that the candidate:

locates and applies applicable legislation, documentation, policies and procedures

implements the requirements, procedures and techniques for the safe, effective and efficient completion of conduct of aggregate spreader box operations, including:

selecting and using required tools and equipment

setting up and disconnecting the spreader box

spreading aggregate including coordination opening and closing of spreader box

hand spreading and spotting

works effectively with others to conduct aggregate spreader box operations that meets all of the required outcomes, including:

organising work activities to meet all task requirements

communicating clearly and concisely with others to receive and clarify work instructions

using a range of communication techniques and systems such as signage to advise others of work activity and exclusion zone

instructing driver to adjust speed, line or angle of body as required

demonstrates completion of conducting aggregate spreader box operations that safely, effectively and efficiently meets all of the required outcomes including:

identifying, reporting and recording hazards and risks

a minimum of four (4) transverse paper joints are placed, picked up and disposed of

a minimum of six (6) truckloads of at least two (2) different aggregate are spread to the design application rate. It must include three (3) runs of wings, tapers and turning lanes on at least three (3) sites varying in complexity

The candidate must demonstrate knowledge of conducting aggregate spreader box operations through:

applying legislative, organisational and site requirements and procedures for:

site and equipment safety requirements

sprayed seal types

aggregate types and sizes

spreader box operations

project quality requirements

housekeeping

equipment types, characteristics, technical capabilities and limitations

applying operational, maintenance and basic diagnostic procedures for the spreader box

applying site isolation and traffic control responsibilities and authorities

applying processes for the calculation of material requirements, application rates and travel speed

safety data sheets and materials handling methods

JSAs/JSEA/safe work method statements