NTISthis.com

Evidence Guide: RIICBS308D - Load aggregate using a purpose built loader

Student: __________________________________________________

Signature: _________________________________________________

Tips for gathering evidence to demonstrate your skills

The important thing to remember when gathering evidence is that the more evidence the better - that is, the more evidence you gather to demonstrate your skills, the more confident an assessor can be that you have learned the skills not just at one point in time, but are continuing to apply and develop those skills (as opposed to just learning for the test!). Furthermore, one piece of evidence that you collect will not usualy demonstrate all the required criteria for a unit of competency, whereas multiple overlapping pieces of evidence will usually do the trick!

From the Wiki University

 

RIICBS308D - Load aggregate using a purpose built loader

What evidence can you provide to prove your understanding of each of the following citeria?

Plan and prepare to load aggregate using a purpose built loader

  1. Access, interpret and apply aggregate loading documentation and ensure the work activity is compliant
  2. Obtain, read, interpret, clarify and confirm work requirements
  3. Identify and address potential risks, hazards and environmental issues, and implement control measures
  4. Select and wear personal protective equipment appropriate for work activities
  5. Identify, Obtain, interpret and implement traffic management signage requirements
  6. Select and check for faults plant, tools and equipment to carry out tasks
  7. Confirm and apply environmental protection and safety requirements
  8. Obtain and interpret emergency procedures, and be prepared for fire/accident/emergency
Access, interpret and apply aggregate loading documentation and ensure the work activity is compliant

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Obtain, read, interpret, clarify and confirm work requirements

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Identify and address potential risks, hazards and environmental issues, and implement control measures

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Select and wear personal protective equipment appropriate for work activities

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Identify, Obtain, interpret and implement traffic management signage requirements

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Select and check for faults plant, tools and equipment to carry out tasks

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Confirm and apply environmental protection and safety requirements

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Obtain and interpret emergency procedures, and be prepared for fire/accident/emergency

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Prepare loader for operation

  1. Conduct pre-operational checks
  2. Check type and quantity of pre-coat in tank and adjust to required level
  3. Check pre-coating requirements and select correct loader size
  4. Record material quantities and screen sizes
  5. Select screens appropriate to the aggregate size
Conduct pre-operational checks

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Check type and quantity of pre-coat in tank and adjust to required level

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Check pre-coating requirements and select correct loader size

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Record material quantities and screen sizes

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Select screens appropriate to the aggregate size

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Manage stack site

  1. Identify and record aggregate sizes
  2. Check ground conditions at stack site to minimise contamination
  3. Estimate and record quantities in aggregate stockpiles
  4. Identify suitable parking availability and reserve for trucks while waiting and loading
  5. Keep stack site free from contamination by pre-coat material
Identify and record aggregate sizes

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Check ground conditions at stack site to minimise contamination

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Estimate and record quantities in aggregate stockpiles

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Identify suitable parking availability and reserve for trucks while waiting and loading

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Keep stack site free from contamination by pre-coat material

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Load/screen/pre-coat aggregate

  1. Direct trucks into position to minimise dust to workers and contamination of aggregates in windy conditions
  2. Drive and operate equipment
  3. Load appropriate aggregate quantities into trucks without contamination
  4. Apply pre-coating uniformly to aggregate at specified rate
  5. Load aggregate quantities accurately and complete records
Direct trucks into position to minimise dust to workers and contamination of aggregates in windy conditions

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Drive and operate equipment

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Load appropriate aggregate quantities into trucks without contamination

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Apply pre-coating uniformly to aggregate at specified rate

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Load aggregate quantities accurately and complete records

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Clean up

  1. Clear work area and dispose of or recycle materials
  2. Clean, check, maintain and store plant, tools and equipment
  3. Carry out housekeeping requirements
Clear work area and dispose of or recycle materials

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Clean, check, maintain and store plant, tools and equipment

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Carry out housekeeping requirements

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Plan and prepare to load aggregate using a purpose built loader

  1. Access, interpret and apply aggregate loading documentation and ensure the work activity is compliant
  2. Obtain, read, interpret, clarify and confirm work requirements
  3. Identify and address potential risks, hazards and environmental issues, and implement control measures
  4. Select and wear personal protective equipment appropriate for work activities
  5. Identify, Obtain, interpret and implement traffic management signage requirements
  6. Select and check for faults plant, tools and equipment to carry out tasks
  7. Confirm and apply environmental protection and safety requirements
  8. Obtain and interpret emergency procedures, and be prepared for fire/accident/emergency
Access, interpret and apply aggregate loading documentation and ensure the work activity is compliant

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Obtain, read, interpret, clarify and confirm work requirements

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Identify and address potential risks, hazards and environmental issues, and implement control measures

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Select and wear personal protective equipment appropriate for work activities

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Identify, Obtain, interpret and implement traffic management signage requirements

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Select and check for faults plant, tools and equipment to carry out tasks

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Confirm and apply environmental protection and safety requirements

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Obtain and interpret emergency procedures, and be prepared for fire/accident/emergency

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Prepare loader for operation

  1. Conduct pre-operational checks
  2. Check type and quantity of pre-coat in tank and adjust to required level
  3. Check pre-coating requirements and select correct loader size
  4. Record material quantities and screen sizes
  5. Select screens appropriate to the aggregate size
Conduct pre-operational checks

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Check type and quantity of pre-coat in tank and adjust to required level

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Check pre-coating requirements and select correct loader size

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Record material quantities and screen sizes

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Select screens appropriate to the aggregate size

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Manage stack site

  1. Identify and record aggregate sizes
  2. Check ground conditions at stack site to minimise contamination
  3. Estimate and record quantities in aggregate stockpiles
  4. Identify suitable parking availability and reserve for trucks while waiting and loading
  5. Keep stack site free from contamination by pre-coat material
Identify and record aggregate sizes

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Check ground conditions at stack site to minimise contamination

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Estimate and record quantities in aggregate stockpiles

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Identify suitable parking availability and reserve for trucks while waiting and loading

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Keep stack site free from contamination by pre-coat material

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Load/screen/pre-coat aggregate

  1. Direct trucks into position to minimise dust to workers and contamination of aggregates in windy conditions
  2. Drive and operate equipment
  3. Load appropriate aggregate quantities into trucks without contamination
  4. Apply pre-coating uniformly to aggregate at specified rate
  5. Load aggregate quantities accurately and complete records
  6. Clear work area and dispose of or recycle materials
  7. Clean, check, maintain and store plant, tools and equipment
  8. Carry out housekeeping requirements
Direct trucks into position to minimise dust to workers and contamination of aggregates in windy conditions

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Drive and operate equipment

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Load appropriate aggregate quantities into trucks without contamination

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Apply pre-coating uniformly to aggregate at specified rate

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Load aggregate quantities accurately and complete records

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Clear work area and dispose of or recycle materials

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Clean, check, maintain and store plant, tools and equipment

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Carry out housekeeping requirements

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Assessed

Teacher: ___________________________________ Date: _________

Signature: ________________________________________________

Comments:

 

 

 

 

 

 

 

 

Instructions to Assessors

Evidence Guide

1. Plan and prepare to load aggregate using a purpose built loader

1.1 Access, interpret and apply aggregate loading documentation and ensure the work activity is compliant

1.2 Obtain, read, interpret, clarify and confirm work requirements

1.3 Identify and address potential risks, hazards and environmental issues, and implement control measures

1.4 Select and wear personal protective equipment appropriate for work activities

1.5 Identify, Obtain, interpret and implement traffic management signage requirements

1.6 Select and check for faults plant, tools and equipment to carry out tasks

1.7 Confirm and apply environmental protection and safety requirements

1.8 Obtain and interpret emergency procedures, and be prepared for fire/accident/emergency

2. Prepare loader for operation

2.1 Conduct pre-operational checks

2.2 Check type and quantity of pre-coat in tank and adjust to required level

2.3 Check pre-coating requirements and select correct loader size

2.4 Record material quantities and screen sizes

2.5 Select screens appropriate to the aggregate size

3. Manage stack site

3.1 Identify and record aggregate sizes

3.2 Check ground conditions at stack site to minimise contamination

3.3 Estimate and record quantities in aggregate stockpiles

3.4 Identify suitable parking availability and reserve for trucks while waiting and loading

3.5 Keep stack site free from contamination by pre-coat material

4. Load/screen/pre-coat aggregate

4.1 Direct trucks into position to minimise dust to workers and contamination of aggregates in windy conditions

4.2 Drive and operate equipment

4.3 Load appropriate aggregate quantities into trucks without contamination

4.4 Apply pre-coating uniformly to aggregate at specified rate

4.5 Load aggregate quantities accurately and complete records

5. Clean up

5.1 Clear work area and dispose of or recycle materials

5.2 Clean, check, maintain and store plant, tools and equipment

5.3 Carry out housekeeping requirements

Required Skills and Knowledge

1. Plan and prepare to load aggregate using a purpose built loader

1.1 Access, interpret and apply aggregate loading documentation and ensure the work activity is compliant

1.2 Obtain, read, interpret, clarify and confirm work requirements

1.3 Identify and address potential risks, hazards and environmental issues, and implement control measures

1.4 Select and wear personal protective equipment appropriate for work activities

1.5 Identify, Obtain, interpret and implement traffic management signage requirements

1.6 Select and check for faults plant, tools and equipment to carry out tasks

1.7 Confirm and apply environmental protection and safety requirements

1.8 Obtain and interpret emergency procedures, and be prepared for fire/accident/emergency

2. Prepare loader for operation

2.1 Conduct pre-operational checks

2.2 Check type and quantity of pre-coat in tank and adjust to required level

2.3 Check pre-coating requirements and select correct loader size

2.4 Record material quantities and screen sizes

2.5 Select screens appropriate to the aggregate size

3. Manage stack site

3.1 Identify and record aggregate sizes

3.2 Check ground conditions at stack site to minimise contamination

3.3 Estimate and record quantities in aggregate stockpiles

3.4 Identify suitable parking availability and reserve for trucks while waiting and loading

3.5 Keep stack site free from contamination by pre-coat material

4. Load/screen/pre-coat aggregate

4.1 Direct trucks into position to minimise dust to workers and contamination of aggregates in windy conditions

4.2 Drive and operate equipment

4.3 Load appropriate aggregate quantities into trucks without contamination

4.4 Apply pre-coating uniformly to aggregate at specified rate

4.5 Load aggregate quantities accurately and complete records

5. Clean up

5.1 Clear work area and dispose of or recycle materials

5.2 Clean, check, maintain and store plant, tools and equipment

5.3 Carry out housekeeping requirements

Evidence is required to be collected that demonstrates a candidate’s competency in this unit. Evidence must be relevant to the roles within this sector’s work operations and satisfy all of the requirements of the performance criteria of this unit and include evidence that the candidate:

locates and applies applicable legislation, documentation, policies and procedures

implements the requirements, procedures and techniques for the safe, effective and efficient loading of aggregate using a purpose built loader including:

organise work activities

select and use relevant tools and equipment safely

identify and report on hazards related to the worksite and work activity

works effectively with others to undertake and complete the loading of aggregate using a purpose built loader that meets all of the required outcomes including:

complying with written and verbal reporting requirements and procedures

communicating clearly and concisely with others to receive and clarify work instructions

communicating clearly and concisely with others to resolve coordination requirements prior to commencing and during work activities

demonstrates completion of loading aggregate using a purpose built loader that safely, effectively and efficiently meets all of the required outcomes on more than one (1) occasion including:

a minimum of four (4) truckloads of aggregate from two (2) separate stock piles loaded, screened and pre-coated to job specifications

a minimum of four (4) truckloads of aggregate from two separate stock piles loaded and screened to job specifications

cleaning up of site in accordance with operational requirements

The candidate must demonstrate knowledge in loading aggregate using a purpose built loader through:

applying legislative, organisational and site requirements and procedures for:

site and equipment safety requirements

aggregate loading

dust control

housekeeping

equipment types, characteristics, technical capabilities and limitations

understanding aggregate types, characteristics and uses

understanding aggregate screening and pre-coating procedures

understanding silica, its properties and dangers

understanding the operational, maintenance and basic diagnostic procedures

complying with the site isolation and traffic control responsibilities and authorities

understanding the processes for the calculation of material quantities

safety data sheets