NTISthis.com

Evidence Guide: RIICPL302D - Install stormwater systems

Student: __________________________________________________

Signature: _________________________________________________

Tips for gathering evidence to demonstrate your skills

The important thing to remember when gathering evidence is that the more evidence the better - that is, the more evidence you gather to demonstrate your skills, the more confident an assessor can be that you have learned the skills not just at one point in time, but are continuing to apply and develop those skills (as opposed to just learning for the test!). Furthermore, one piece of evidence that you collect will not usualy demonstrate all the required criteria for a unit of competency, whereas multiple overlapping pieces of evidence will usually do the trick!

From the Wiki University

 

RIICPL302D - Install stormwater systems

What evidence can you provide to prove your understanding of each of the following citeria?

Plan and prepare for installing stormwater systems

  1. Access, interpret and apply stormwater systems documentation and ensure the work activity is compliant
  2. Obtain, interpret, clarify and confirm work/plans/specifications requirements
  3. Identify, obtain and implement traffic signage requirements
  4. Select, and check for faults, equipment/tools for work activities
  5. Identify, confirm and apply environmental protection requirements
  6. Select and wear personal protective equipment appropriate for work activities
  7. Identify, address and report potential hazards and risks
  8. Obtain and interpret emergency procedures, and be prepared for fire/accident/emergency
Access, interpret and apply stormwater systems documentation and ensure the work activity is compliant

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Obtain, interpret, clarify and confirm work/plans/specifications requirements

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Identify, obtain and implement traffic signage requirements

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Select, and check for faults, equipment/tools for work activities

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Identify, confirm and apply environmental protection requirements

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Select and wear personal protective equipment appropriate for work activities

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Identify, address and report potential hazards and risks

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Obtain and interpret emergency procedures, and be prepared for fire/accident/emergency

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Set out and excavate

  1. Prepare work area and materials
  2. Determine and apply dewatering requirements
  3. Determine location, alignment direction, level and grade of stormwater system
  4. Set out works to specification
  5. Advise plant operator of excavation requirements and monitor levels
  6. Install stormwater system bedding
Prepare work area and materials

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Determine and apply dewatering requirements

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Determine location, alignment direction, level and grade of stormwater system

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Set out works to specification

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Advise plant operator of excavation requirements and monitor levels

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Install stormwater system bedding

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Install stormwater system

  1. Lower pipes and place in position
  2. Join pipes correctly
  3. Continuously check alignment level and grade continuously for conformance
  4. Position side support and/or overlay beside the pipes
  5. Fit inspection openings
  6. Monitor backfill procedure and ensure work is completed to requirements
Lower pipes and place in position

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Join pipes correctly

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Continuously check alignment level and grade continuously for conformance

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Position side support and/or overlay beside the pipes

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Fit inspection openings

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Monitor backfill procedure and ensure work is completed to requirements

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Test stormwater system

  1. Perform stormwater system test procedures establishing functionality and serviceability
  2. Record and report test results
Perform stormwater system test procedures establishing functionality and serviceability

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Record and report test results

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Clean up

  1. Clear work area and dispose of or recycle materials
  2. Clean, check, maintain and store plant, tools and equipment
Clear work area and dispose of or recycle materials

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Clean, check, maintain and store plant, tools and equipment

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Plan and prepare for installing stormwater systems

  1. Access, interpret and apply stormwater systems documentation and ensure the work activity is compliant
  2. Obtain, interpret, clarify and confirm work/plans/specifications requirements
  3. Identify, obtain and implement traffic signage requirements
  4. Select, and check for faults, equipment/tools for work activities
  5. Identify, confirm and apply environmental protection requirements
  6. Select and wear personal protective equipment appropriate for work activities
  7. Identify, address and report potential hazards and risks
  8. Obtain and interpret emergency procedures, and be prepared for fire/accident/emergency
Access, interpret and apply stormwater systems documentation and ensure the work activity is compliant

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Obtain, interpret, clarify and confirm work/plans/specifications requirements

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Identify, obtain and implement traffic signage requirements

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Select, and check for faults, equipment/tools for work activities

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Identify, confirm and apply environmental protection requirements

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Select and wear personal protective equipment appropriate for work activities

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Identify, address and report potential hazards and risks

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Obtain and interpret emergency procedures, and be prepared for fire/accident/emergency

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Set out and excavate

  1. Prepare work area and materials
  2. Determine and apply dewatering requirements
  3. Determine location, alignment direction, level and grade of stormwater system
  4. Set out works to specification
  5. Advise plant operator of excavation requirements and monitor levels
  6. Install stormwater system bedding
Prepare work area and materials

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Determine and apply dewatering requirements

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Determine location, alignment direction, level and grade of stormwater system

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Set out works to specification

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Advise plant operator of excavation requirements and monitor levels

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Install stormwater system bedding

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Install stormwater system

  1. Lower pipes and place in position
  2. Join pipes correctly
  3. Continuously check alignment level and grade continuously for conformance
  4. Position side support and/or overlay beside the pipes
  5. Fit inspection openings
  6. Monitor backfill procedure and ensure work is completed to requirements
Lower pipes and place in position

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Join pipes correctly

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Continuously check alignment level and grade continuously for conformance

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Position side support and/or overlay beside the pipes

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Fit inspection openings

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Monitor backfill procedure and ensure work is completed to requirements

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Test stormwater system

  1. Perform stormwater system test procedures establishing functionality and serviceability
  2. Record and report test results
  3. Clear work area and dispose of or recycle materials
  4. Clean, check, maintain and store plant, tools and equipment
Perform stormwater system test procedures establishing functionality and serviceability

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Record and report test results

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Clear work area and dispose of or recycle materials

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Clean, check, maintain and store plant, tools and equipment

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Assessed

Teacher: ___________________________________ Date: _________

Signature: ________________________________________________

Comments:

 

 

 

 

 

 

 

 

Instructions to Assessors

Evidence Guide

1. Plan and prepare for installing stormwater systems

1.1 Access, interpret and apply stormwater systems documentation and ensure the work activity is compliant

1.2 Obtain, interpret, clarify and confirm work/plans/specifications requirements

1.3 Identify, obtain and implement traffic signage requirements

1.4 Select, and check for faults, equipment/tools for work activities

1.5 Identify, confirm and apply environmental protection requirements

1.6 Select and wear personal protective equipment appropriate for work activities

1.7 Identify, address and report potential hazards and risks

1.8 Obtain and interpret emergency procedures, and be prepared for fire/accident/emergency

2. Set out and excavate

2.1 Prepare work area and materials

2.2 Determine and apply dewatering requirements

2.3 Determine location, alignment direction, level and grade of stormwater system

2.4 Set out works to specification

2.5 Advise plant operator of excavation requirements and monitor levels

2.6 Install stormwater system bedding

3. Install stormwater system

3.1 Lower pipes and place in position

3.2 Join pipes correctly

3.3 Continuously check alignment level and grade continuously for conformance

3.4 Position side support and/or overlay beside the pipes

3.5 Fit inspection openings

3.6 Monitor backfill procedure and ensure work is completed to requirements

4. Test stormwater system

4.1 Perform stormwater system test procedures establishing functionality and serviceability

4.2 Record and report test results

5. Clean up

5.1 Clear work area and dispose of or recycle materials

5.2 Clean, check, maintain and store plant, tools and equipment

Required Skills and Knowledge

1. Plan and prepare for installing stormwater systems

1.1 Access, interpret and apply stormwater systems documentation and ensure the work activity is compliant

1.2 Obtain, interpret, clarify and confirm work/plans/specifications requirements

1.3 Identify, obtain and implement traffic signage requirements

1.4 Select, and check for faults, equipment/tools for work activities

1.5 Identify, confirm and apply environmental protection requirements

1.6 Select and wear personal protective equipment appropriate for work activities

1.7 Identify, address and report potential hazards and risks

1.8 Obtain and interpret emergency procedures, and be prepared for fire/accident/emergency

2. Set out and excavate

2.1 Prepare work area and materials

2.2 Determine and apply dewatering requirements

2.3 Determine location, alignment direction, level and grade of stormwater system

2.4 Set out works to specification

2.5 Advise plant operator of excavation requirements and monitor levels

2.6 Install stormwater system bedding

3. Install stormwater system

3.1 Lower pipes and place in position

3.2 Join pipes correctly

3.3 Continuously check alignment level and grade continuously for conformance

3.4 Position side support and/or overlay beside the pipes

3.5 Fit inspection openings

3.6 Monitor backfill procedure and ensure work is completed to requirements

4. Test stormwater system

4.1 Perform stormwater system test procedures establishing functionality and serviceability

4.2 Record and report test results

5. Clean up

5.1 Clear work area and dispose of or recycle materials

5.2 Clean, check, maintain and store plant, tools and equipment

Evidence is required to be collected that demonstrates a candidate’s competency in this unit. Evidence must be relevant to the roles within this sector’s work operations and satisfy all of the requirements of the performance criteria of this unit and include evidence that the candidate:

locates and applies applicable legislation, documentation, policies and procedures

implements the requirements, procedures and techniques for the safe, effective and efficient completion of installation of stormwater systems including:

applying problem solving and troubleshooting techniques

applying diagnostic techniques

works effectively with others to undertake and complete the installation of stormwater systems that meets all of the required outcomes including:

communicating to confirm work/plans/specifications

using a range of communications techniques and equipment to convey information to others

demonstrates completion of installing stormwater systems that safely, effectively and efficiently meets all of the required outcomes on more than one (1) occasion including:

determining location, alignment direction level and grade of stormwater system

installing stormwater system bedding

installing a minimum of 100 metres of stormwater pipe

completing pipe joins

performing test procedures, establishing functionality and serviceability

maintaining written and verbal reporting requirements and procedures

The candidate must demonstrate knowledge in installing stormwater systems through:

accessing, interpreting and applying the legislative, organisation and site requirements and procedures for;

hazard identification, risk assessment and response

using JSA/JSEA/safe work method statements

project quality measures

using tools/equipment

maintaining excavation/trench safety

confined space entry

site dewatering

using safety data sheets and materials handling methods

using civil construction terminology

using pipe systems and installation procedures

identifying mains pipe and utility services

using concrete and concrete fabrication

using sedimentation and erosion controls

reading and interpreting engineering drawings

identifying equipment types, characteristics, technical capabilities and limitations

identifying valves and flow control devices

construction of water reticulation

calculating pipeline grades and percentages

identifying site isolation and traffic control responsibilities and authorities