Evidence Guide: RIICRC207D - Install noise barriers

Student: __________________________________________________

Signature: _________________________________________________

Tips for gathering evidence to demonstrate your skills

The important thing to remember when gathering evidence is that the more evidence the better - that is, the more evidence you gather to demonstrate your skills, the more confident an assessor can be that you have learned the skills not just at one point in time, but are continuing to apply and develop those skills (as opposed to just learning for the test!). Furthermore, one piece of evidence that you collect will not usualy demonstrate all the required criteria for a unit of competency, whereas multiple overlapping pieces of evidence will usually do the trick!

From the Wiki University

 

RIICRC207D - Install noise barriers

What evidence can you provide to prove your understanding of each of the following citeria?

Plan and prepare for installing noise barriers

  1. Access, interpret and apply noise barrier installation documentation and ensure the work activity is compliant
  2. Obtain, read, interpret, clarify and confirm work requirements
  3. Identify and address potential risks, hazards and environmental issues, and implement control measures
  4. Select and wear correct personal protective equipment appropriate for work activities
  5. Identify, obtain, confirm and implement signage requirements
  6. Select and check for faults all plant, tools and equipment to carry out tasks
  7. Survey work area for loading and unloading and stock-piling materials
  8. Assess plant and crane capabilities as required
Access, interpret and apply noise barrier installation documentation and ensure the work activity is compliant

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Obtain, read, interpret, clarify and confirm work requirements

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Identify and address potential risks, hazards and environmental issues, and implement control measures

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Select and wear correct personal protective equipment appropriate for work activities

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Identify, obtain, confirm and implement signage requirements

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Select and check for faults all plant, tools and equipment to carry out tasks

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Survey work area for loading and unloading and stock-piling materials

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Assess plant and crane capabilities as required

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Erect noise barriers

  1. Set out position of noise barrier line and post holes, and excavate to specifications
  2. Install base section
  3. Install uprights plumb and to alignment
  4. Fit and fix rails, cladding or panels
Set out position of noise barrier line and post holes, and excavate to specifications

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Install base section

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Install uprights plumb and to alignment

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Fit and fix rails, cladding or panels

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Clean up

  1. Clear work area and recycle or dispose of materials
  2. Store and stack unused materials
  3. Clean, check, maintain and store plant, tools and equipment
Clear work area and recycle or dispose of materials

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Store and stack unused materials

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Clean, check, maintain and store plant, tools and equipment

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Plan and prepare for installing noise barriers

  1. Access, interpret and apply noise barrier installation documentation and ensure the work activity is compliant
  2. Obtain, read, interpret, clarify and confirm work requirements
  3. Identify and address potential risks, hazards and environmental issues, and implement control measures
  4. Select and wear correct personal protective equipment appropriate for work activities
  5. Identify, obtain, confirm and implement signage requirements
  6. Select and check for faults all plant, tools and equipment to carry out tasks
  7. Survey work area for loading and unloading and stock-piling materials
  8. Assess plant and crane capabilities as required
Access, interpret and apply noise barrier installation documentation and ensure the work activity is compliant

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Obtain, read, interpret, clarify and confirm work requirements

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Identify and address potential risks, hazards and environmental issues, and implement control measures

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Select and wear correct personal protective equipment appropriate for work activities

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Identify, obtain, confirm and implement signage requirements

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Select and check for faults all plant, tools and equipment to carry out tasks

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Survey work area for loading and unloading and stock-piling materials

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Assess plant and crane capabilities as required

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Erect noise barriers

  1. Set out position of noise barrier line and post holes, and excavate to specifications
  2. Install base section
  3. Install uprights plumb and to alignment
  4. Fit and fix rails, cladding or panels
  5. Clear work area and recycle or dispose of materials
  6. Store and stack unused materials
  7. Clean, check, maintain and store plant, tools and equipment
Set out position of noise barrier line and post holes, and excavate to specifications

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Install base section

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Install uprights plumb and to alignment

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Fit and fix rails, cladding or panels

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Clear work area and recycle or dispose of materials

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Store and stack unused materials

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Clean, check, maintain and store plant, tools and equipment

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Assessed

Teacher: ___________________________________ Date: _________

Signature: ________________________________________________

Comments:

 

 

 

 

 

 

 

 

Instructions to Assessors

Evidence Guide

1. Plan and prepare for installing noise barriers

1.1 Access, interpret and apply noise barrier installation documentation and ensure the work activity is compliant

1.2 Obtain, read, interpret, clarify and confirm work requirements

1.3 Identify and address potential risks, hazards and environmental issues, and implement control measures

1.4 Select and wear correct personal protective equipment appropriate for work activities

1.5 Identify, obtain, confirm and implement signage requirements

1.6 Select and check for faults all plant, tools and equipment to carry out tasks

1.7 Survey work area for loading and unloading and stock-piling materials

1.8 Assess plant and crane capabilities as required

2. Erect noise barriers

2.1 Set out position of noise barrier line and post holes, and excavate to specifications

2.2 Install base section

2.3 Install uprights plumb and to alignment

2.4 Fit and fix rails, cladding or panels

3. Clean up

3.1 Clear work area and recycle or dispose of materials

3.2 Store and stack unused materials

3.3 Clean, check, maintain and store plant, tools and equipment

Required Skills and Knowledge

1. Plan and prepare for installing noise barriers

1.1 Access, interpret and apply noise barrier installation documentation and ensure the work activity is compliant

1.2 Obtain, read, interpret, clarify and confirm work requirements

1.3 Identify and address potential risks, hazards and environmental issues, and implement control measures

1.4 Select and wear correct personal protective equipment appropriate for work activities

1.5 Identify, obtain, confirm and implement signage requirements

1.6 Select and check for faults all plant, tools and equipment to carry out tasks

1.7 Survey work area for loading and unloading and stock-piling materials

1.8 Assess plant and crane capabilities as required

2. Erect noise barriers

2.1 Set out position of noise barrier line and post holes, and excavate to specifications

2.2 Install base section

2.3 Install uprights plumb and to alignment

2.4 Fit and fix rails, cladding or panels

3. Clean up

3.1 Clear work area and recycle or dispose of materials

3.2 Store and stack unused materials

3.3 Clean, check, maintain and store plant, tools and equipment

Evidence is required to be collected that demonstrates a candidate’s competency in this unit. Evidence must be relevant to the roles within this sector’s work operations and satisfy all of the requirements of the performance criteria of this unit and include evidence that the candidate:

locates and applies applicable documentation, policies and procedures

implements the requirements, procedures and techniques for the safe, effective and efficient completion of noise barrier installation including:

accessing, interpreting and applying documentation relevant to the installation of noise barriers

identifying and applying relevant drawings and job specifications to all work activities

identifying, addressing and reporting potential hazards and risks

identifying, obtaining, confirming and implementing signage requirements

selecting and checking for faults all plant, tools and equipment to carry out tasks

identifying, addressing and reporting environmental issues and ground conditions

surveying work area for loading and unloading and stock-piling materials

correct use of plant and crane as required

works effectively with others to undertake and complete the installation of noise barriers in a way that meets all requirements including:

preparing for and organising work activities to meet all task requirements

communicating clearly and concisely with others to receive and clarify work instructions

using a range of communication techniques and aids to advise others of work activity and exclusion zones

monitoring hazards and identifying and communicating changes to the work environment during the work process

demonstrates completion of installing noise barriers that safely, effectively and efficiently meets all of the required outcomes on more than one (1) occasion including:

erecting noise barriers to meet drawings and job specifications requirements

clearing work area and disposing of, recycling or storing materials

as an individual or as a member of a two-three (2-3) person team, undertake and complete the installation of fifty (50) metres of noise barriers

The candidate must demonstrate knowledge in installing noise barriers through:

accessing, interpreting and applying, organisation and site requirements and procedures for:

identifying and managing risks

identifying, addressing and reporting environmental issues and ground conditions

setting up work activity

site isolation and traffic control responsibilities

work health and safety

managing waste

selecting and checking for faults, tools and equipment to carry out tasks

confirming plant and crane capabilities as required

carrying out work to drawings and specifications

applying effective installation techniques