The important thing to remember when gathering evidence is that the more evidence the better - that is, the more evidence you gather to demonstrate your skills, the more confident an assessor can be that you have learned the skills not just at one point in time, but are continuing to apply and develop those skills (as opposed to just learning for the test!). Furthermore, one piece of evidence that you collect will not usualy demonstrate all the required criteria for a unit of competency, whereas multiple overlapping pieces of evidence will usually do the trick!

From the Wiki University

 

RIICRC209D - Lay reinforced concrete box culverts

What evidence can you provide to prove your understanding of each of the following citeria?

Plan and prepare to lay reinforced concrete box culverts

  1. Access, interpret and apply reinforced concrete box culverts laying documentation and ensure the work activity is compliant
  2. Obtain, read, interpret, clarify and confirm work requirements
  3. Identify and address potential risks, hazards and environmental issues, and implement control measures
  4. Select and wear correct personal protective equipment appropriate for work activities
  5. Identify, obtain, confirm and implement signage requirements
  6. Select and check for faults all plant, tools and equipment to carry out tasks
  7. Check box culverts (RCBC) units to ensure conformity to relevant drawing and job specifications
  8. Confirm plant and/or crane requirements to assist in preparing ground and placing box culverts
Access, interpret and apply reinforced concrete box culverts laying documentation and ensure the work activity is compliant

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Obtain, read, interpret, clarify and confirm work requirements

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Identify and address potential risks, hazards and environmental issues, and implement control measures

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Select and wear correct personal protective equipment appropriate for work activities

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Identify, obtain, confirm and implement signage requirements

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Select and check for faults all plant, tools and equipment to carry out tasks

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Check box culverts (RCBC) units to ensure conformity to relevant drawing and job specifications

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Confirm plant and/or crane requirements to assist in preparing ground and placing box culverts

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Set out and excavation

  1. Determine location and depths of excavation from job drawings
  2. Set out and clearly mark excavation location
  3. Advise plant operator of excavation requirements
  4. Check excavation depths and grades to conform with plans and specifications
  5. Compact and prepare foundations base for testing
Determine location and depths of excavation from job drawings

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Set out and clearly mark excavation location

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Advise plant operator of excavation requirements

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Check excavation depths and grades to conform with plans and specifications

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Compact and prepare foundations base for testing

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Construct concrete base

  1. Set out and construct formwork to required dimensions
  2. Place steel reinforcement to specifications
  3. Form recesses in slab as specified
  4. Connect and tighten hold down anchors to specified requirements
  5. Place, compact, finish and cure concrete to specified requirements
Set out and construct formwork to required dimensions

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Place steel reinforcement to specifications

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Form recesses in slab as specified

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Connect and tighten hold down anchors to specified requirements

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Place, compact, finish and cure concrete to specified requirements

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Lay culvert units

  1. Place continuous mortar bed to support legs
  2. Lower and position RCBC units to line and level on supporting slab
  3. Connect hold down anchors to RCBC units
  4. Finish joints between RCBC units to specification
  5. Infill space between legs of multiple culverts to specification
  6. Install spanning slabs where specified for multiple culverts
  7. Cut off and treat lifting lugs
  8. Finish inlet and outlet of culvert
  9. Advise plant operator of compaction and backfill requirements and backfill culvert to required finish level
Place continuous mortar bed to support legs

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Lower and position RCBC units to line and level on supporting slab

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Connect hold down anchors to RCBC units

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Finish joints between RCBC units to specification

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Infill space between legs of multiple culverts to specification

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Install spanning slabs where specified for multiple culverts

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Cut off and treat lifting lugs

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Finish inlet and outlet of culvert

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Advise plant operator of compaction and backfill requirements and backfill culvert to required finish level

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Clean up

  1. Clear work area and dispose of or recycle materials
  2. Clean, check, maintain and store tools and equipment
Clear work area and dispose of or recycle materials

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Clean, check, maintain and store tools and equipment

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Plan and prepare to lay reinforced concrete box culverts

  1. Access, interpret and apply reinforced concrete box culverts laying documentation and ensure the work activity is compliant
  2. Obtain, read, interpret, clarify and confirm work requirements
  3. Identify and address potential risks, hazards and environmental issues, and implement control measures
  4. Select and wear correct personal protective equipment appropriate for work activities
  5. Identify, obtain, confirm and implement signage requirements
  6. Select and check for faults all plant, tools and equipment to carry out tasks
  7. Check box culverts (RCBC) units to ensure conformity to relevant drawing and job specifications
  8. Confirm plant and/or crane requirements to assist in preparing ground and placing box culverts
Access, interpret and apply reinforced concrete box culverts laying documentation and ensure the work activity is compliant

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Obtain, read, interpret, clarify and confirm work requirements

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Identify and address potential risks, hazards and environmental issues, and implement control measures

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Select and wear correct personal protective equipment appropriate for work activities

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Identify, obtain, confirm and implement signage requirements

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Select and check for faults all plant, tools and equipment to carry out tasks

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Check box culverts (RCBC) units to ensure conformity to relevant drawing and job specifications

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Confirm plant and/or crane requirements to assist in preparing ground and placing box culverts

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Set out and excavation

  1. Determine location and depths of excavation from job drawings
  2. Set out and clearly mark excavation location
  3. Advise plant operator of excavation requirements
  4. Check excavation depths and grades to conform with plans and specifications
  5. Compact and prepare foundations base for testing
Determine location and depths of excavation from job drawings

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Set out and clearly mark excavation location

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Advise plant operator of excavation requirements

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Check excavation depths and grades to conform with plans and specifications

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Compact and prepare foundations base for testing

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Construct concrete base

  1. Set out and construct formwork to required dimensions
  2. Place steel reinforcement to specifications
  3. Form recesses in slab as specified
  4. Connect and tighten hold down anchors to specified requirements
  5. Place, compact, finish and cure concrete to specified requirements
Set out and construct formwork to required dimensions

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Place steel reinforcement to specifications

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Form recesses in slab as specified

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Connect and tighten hold down anchors to specified requirements

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Place, compact, finish and cure concrete to specified requirements

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Lay culvert units

  1. Place continuous mortar bed to support legs
  2. Lower and position RCBC units to line and level on supporting slab
  3. Connect hold down anchors to RCBC units
  4. Finish joints between RCBC units to specification
  5. Infill space between legs of multiple culverts to specification
  6. Install spanning slabs where specified for multiple culverts
  7. Cut off and treat lifting lugs
  8. Finish inlet and outlet of culvert
  9. Advise plant operator of compaction and backfill requirements and backfill culvert to required finish level
  10. Clear work area and dispose of or recycle materials
  11. Clean, check, maintain and store tools and equipment
Place continuous mortar bed to support legs

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Lower and position RCBC units to line and level on supporting slab

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Connect hold down anchors to RCBC units

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Finish joints between RCBC units to specification

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Infill space between legs of multiple culverts to specification

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Install spanning slabs where specified for multiple culverts

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Cut off and treat lifting lugs

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Finish inlet and outlet of culvert

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Advise plant operator of compaction and backfill requirements and backfill culvert to required finish level

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Clear work area and dispose of or recycle materials

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Clean, check, maintain and store tools and equipment

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Assessed

Teacher: ___________________________________ Date: _________

Signature: ________________________________________________

Comments:

 

 

 

 

 

 

 

 

Instructions to Assessors

Evidence Guide

1. Plan and prepare to lay reinforced concrete box culverts

1.1 Access, interpret and apply reinforced concrete box culverts laying documentation and ensure the work activity is compliant

1.2 Obtain, read, interpret, clarify and confirm work requirements

1.3 Identify and address potential risks, hazards and environmental issues, and implement control measures

1.4 Select and wear correct personal protective equipment appropriate for work activities

1.5 Identify, obtain, confirm and implement signage requirements

1.6 Select and check for faults all plant, tools and equipment to carry out tasks

1.7 Check box culverts (RCBC) units to ensure conformity to relevant drawing and job specifications

1.8 Confirm plant and/or crane requirements to assist in preparing ground and placing box culverts

2. Set out and excavation

2.1 Determine location and depths of excavation from job drawings

2.2 Set out and clearly mark excavation location

2.3 Advise plant operator of excavation requirements

2.4 Check excavation depths and grades to conform with plans and specifications

2.5 Compact and prepare foundations base for testing

3. Construct concrete base

3.1 Set out and construct formwork to required dimensions

3.2 Place steel reinforcement to specifications

3.3 Form recesses in slab as specified

3.4 Connect and tighten hold down anchors to specified requirements

3.5 Place, compact, finish and cure concrete to specified requirements

4. Lay culvert units

4.1 Place continuous mortar bed to support legs

4.2 Lower and position RCBC units to line and level on supporting slab

4.3 Connect hold down anchors to RCBC units

4.4 Finish joints between RCBC units to specification

4.5 Infill space between legs of multiple culverts to specification

4.6 Install spanning slabs where specified for multiple culverts

4.7 Cut off and treat lifting lugs

4.8 Finish inlet and outlet of culvert

4.9 Advise plant operator of compaction and backfill requirements and backfill culvert to required finish level

5. Clean up

5.1 Clear work area and dispose of or recycle materials

5.2 Clean, check, maintain and store tools and equipment

Required Skills and Knowledge

1. Plan and prepare to lay reinforced concrete box culverts

1.1 Access, interpret and apply reinforced concrete box culverts laying documentation and ensure the work activity is compliant

1.2 Obtain, read, interpret, clarify and confirm work requirements

1.3 Identify and address potential risks, hazards and environmental issues, and implement control measures

1.4 Select and wear correct personal protective equipment appropriate for work activities

1.5 Identify, obtain, confirm and implement signage requirements

1.6 Select and check for faults all plant, tools and equipment to carry out tasks

1.7 Check box culverts (RCBC) units to ensure conformity to relevant drawing and job specifications

1.8 Confirm plant and/or crane requirements to assist in preparing ground and placing box culverts

2. Set out and excavation

2.1 Determine location and depths of excavation from job drawings

2.2 Set out and clearly mark excavation location

2.3 Advise plant operator of excavation requirements

2.4 Check excavation depths and grades to conform with plans and specifications

2.5 Compact and prepare foundations base for testing

3. Construct concrete base

3.1 Set out and construct formwork to required dimensions

3.2 Place steel reinforcement to specifications

3.3 Form recesses in slab as specified

3.4 Connect and tighten hold down anchors to specified requirements

3.5 Place, compact, finish and cure concrete to specified requirements

4. Lay culvert units

4.1 Place continuous mortar bed to support legs

4.2 Lower and position RCBC units to line and level on supporting slab

4.3 Connect hold down anchors to RCBC units

4.4 Finish joints between RCBC units to specification

4.5 Infill space between legs of multiple culverts to specification

4.6 Install spanning slabs where specified for multiple culverts

4.7 Cut off and treat lifting lugs

4.8 Finish inlet and outlet of culvert

4.9 Advise plant operator of compaction and backfill requirements and backfill culvert to required finish level

5. Clean up

5.1 Clear work area and dispose of or recycle materials

5.2 Clean, check, maintain and store tools and equipment

Evidence of the ability to:

interpret scripts when planning and undertaking continuity tasks for productions maintain continuity of performers’ costumes and accessories during productions

produce accurate documentation of costume continuity information

monitor and maintain condition of costumes for continuity during productions

take account of continuity issues when arranging costume repairs or alterations

provide updates about continuity issues to relevant personnel.

Note: If a specific volume or frequency is not stated, then evidence must be provided at least once.

To complete the unit requirements safely and effectively, the individual must:

describe protocols in relation to undertaking costume continuity tasks on film shoots or during live productions

outline roles and responsibilities of production personnel who need to be aware of continuity issues

describe elements of costumes that require particular attention for continuity purposes

explain continuity conventions in relation to how aspects of costumes are viewed by audiences or captured on camera

describe administrative procedures and documentation associated with costume continuity.