Evidence Guide: RIICTB310D - Construct specialised timber deck systems

Student: __________________________________________________

Signature: _________________________________________________

Tips for gathering evidence to demonstrate your skills

The important thing to remember when gathering evidence is that the more evidence the better - that is, the more evidence you gather to demonstrate your skills, the more confident an assessor can be that you have learned the skills not just at one point in time, but are continuing to apply and develop those skills (as opposed to just learning for the test!). Furthermore, one piece of evidence that you collect will not usualy demonstrate all the required criteria for a unit of competency, whereas multiple overlapping pieces of evidence will usually do the trick!

From the Wiki University

 

RIICTB310D - Construct specialised timber deck systems

What evidence can you provide to prove your understanding of each of the following citeria?

Plan and prepare to construct specialised timber deck systems

  1. Access, interpret and apply timber deck systems documentation and ensure the work activity is compliant
  2. Obtain, read, interpret, clarify and confirm work requirements
  3. Identify, address and report hazards, risks and environmental issues and implement control measures
  4. Select and wear personal protective equipment appropriate for work activities
  5. Confirm and apply environmental protection and safety requirements
  6. Obtain, interpret and implement traffic management signage requirements
  7. Select and check for faults plant, tools and equipment to carry out tasks
  8. Identify, confirm, safely handle and locate, ready for use, materials required for the work application
  9. Obtain and interpret emergency procedures, and be prepared for fire/accident/emergency
Access, interpret and apply timber deck systems documentation and ensure the work activity is compliant

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Obtain, read, interpret, clarify and confirm work requirements

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Identify, address and report hazards, risks and environmental issues and implement control measures

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Select and wear personal protective equipment appropriate for work activities

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Confirm and apply environmental protection and safety requirements

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Obtain, interpret and implement traffic management signage requirements

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Select and check for faults plant, tools and equipment to carry out tasks

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Identify, confirm, safely handle and locate, ready for use, materials required for the work application

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Obtain and interpret emergency procedures, and be prepared for fire/accident/emergency

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Construct bridge deck

  1. Select deck materials
  2. Pre-drill connection points
  3. Fix deck temporarily with nails
  4. Connect stressing cables to the bridge deck
  5. Stress and rest bridge deck for the specified timeframe
Select deck materials

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Pre-drill connection points

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Fix deck temporarily with nails

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Connect stressing cables to the bridge deck

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Stress and rest bridge deck for the specified timeframe

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Install bridge deck

  1. Re-stress bridge deck prior to removal to location
  2. Trim bridge deck prior to securing in location
  3. Install bridge deck at location
  4. Bolt bridge deck to the cross girders
  5. Re-stress bridge deck
  6. Pack stressing cable location holes with grease
  7. Fit protection angles, kerbs and handrails
  8. Apply waterproofing to the deck and fittings
Re-stress bridge deck prior to removal to location

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Trim bridge deck prior to securing in location

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Install bridge deck at location

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Bolt bridge deck to the cross girders

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Re-stress bridge deck

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Pack stressing cable location holes with grease

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Fit protection angles, kerbs and handrails

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Apply waterproofing to the deck and fittings

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Clean up

  1. Clear work area and dispose of or recycle materials
  2. Clean, check, maintain and store machinery, tools and equipment
Clear work area and dispose of or recycle materials

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Clean, check, maintain and store machinery, tools and equipment

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Plan and prepare to construct specialised timber deck systems

  1. Access, interpret and apply timber deck systems documentation and ensure the work activity is compliant
  2. Obtain, read, interpret, clarify and confirm work requirements
  3. Identify, address and report hazards, risks and environmental issues and implement control measures
  4. Select and wear personal protective equipment appropriate for work activities
  5. Confirm and apply environmental protection and safety requirements
  6. Obtain, interpret and implement traffic management signage requirements
  7. Select and check for faults plant, tools and equipment to carry out tasks
  8. Identify, confirm, safely handle and locate, ready for use, materials required for the work application
  9. Obtain and interpret emergency procedures, and be prepared for fire/accident/emergency
Access, interpret and apply timber deck systems documentation and ensure the work activity is compliant

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Obtain, read, interpret, clarify and confirm work requirements

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Identify, address and report hazards, risks and environmental issues and implement control measures

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Select and wear personal protective equipment appropriate for work activities

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Confirm and apply environmental protection and safety requirements

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Obtain, interpret and implement traffic management signage requirements

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Select and check for faults plant, tools and equipment to carry out tasks

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Identify, confirm, safely handle and locate, ready for use, materials required for the work application

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Obtain and interpret emergency procedures, and be prepared for fire/accident/emergency

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Construct bridge deck

  1. Select deck materials
  2. Pre-drill connection points
  3. Fix deck temporarily with nails
  4. Connect stressing cables to the bridge deck
  5. Stress and rest bridge deck for the specified timeframe
Select deck materials

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Pre-drill connection points

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Fix deck temporarily with nails

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Connect stressing cables to the bridge deck

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Stress and rest bridge deck for the specified timeframe

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Install bridge deck

  1. Re-stress bridge deck prior to removal to location
  2. Trim bridge deck prior to securing in location
  3. Install bridge deck at location
  4. Bolt bridge deck to the cross girders
  5. Re-stress bridge deck
  6. Pack stressing cable location holes with grease
  7. Fit protection angles, kerbs and handrails
  8. Apply waterproofing to the deck and fittings
  9. Clear work area and dispose of or recycle materials
  10. Clean, check, maintain and store machinery, tools and equipment
Re-stress bridge deck prior to removal to location

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Trim bridge deck prior to securing in location

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Install bridge deck at location

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Bolt bridge deck to the cross girders

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Re-stress bridge deck

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Pack stressing cable location holes with grease

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Fit protection angles, kerbs and handrails

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Apply waterproofing to the deck and fittings

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Clear work area and dispose of or recycle materials

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Clean, check, maintain and store machinery, tools and equipment

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Assessed

Teacher: ___________________________________ Date: _________

Signature: ________________________________________________

Comments:

 

 

 

 

 

 

 

 

Instructions to Assessors

Evidence Guide

1. Plan and prepare to construct specialised timber deck systems

1.1. Access, interpret and apply timber deck systems documentation and ensure the work activity is compliant

1.2. Obtain, read, interpret, clarify and confirm work requirements

1.3. Identify, address and report hazards, risks and environmental issues and implement control measures

1.4. Select and wear personal protective equipment appropriate for work activities

1.5. Confirm and apply environmental protection and safety requirements

1.6. Obtain, interpret and implement traffic management signage requirements

1.7. Select and check for faults plant, tools and equipment to carry out tasks

1.8. Identify, confirm, safely handle and locate, ready for use, materials required for the work application

1.9. Obtain and interpret emergency procedures, and be prepared for fire/accident/emergency

2. Construct bridge deck

2.1. Select deck materials

2.2. Pre-drill connection points

2.3. Fix deck temporarily with nails

2.4. Connect stressing cables to the bridge deck

2.5. Stress and rest bridge deck for the specified timeframe

3. Install bridge deck

3.1. Re-stress bridge deck prior to removal to location

3.2. Trim bridge deck prior to securing in location

3.3. Install bridge deck at location

3.4. Bolt bridge deck to the cross girders

3.5. Re-stress bridge deck

3.6. Pack stressing cable location holes with grease

3.7. Fit protection angles, kerbs and handrails

3.8. Apply waterproofing to the deck and fittings

4. Clean up

4.1. Clear work area and dispose of or recycle materials

4.2. Clean, check, maintain and store machinery, tools and equipment

Required Skills and Knowledge

1. Plan and prepare to construct specialised timber deck systems

1.1. Access, interpret and apply timber deck systems documentation and ensure the work activity is compliant

1.2. Obtain, read, interpret, clarify and confirm work requirements

1.3. Identify, address and report hazards, risks and environmental issues and implement control measures

1.4. Select and wear personal protective equipment appropriate for work activities

1.5. Confirm and apply environmental protection and safety requirements

1.6. Obtain, interpret and implement traffic management signage requirements

1.7. Select and check for faults plant, tools and equipment to carry out tasks

1.8. Identify, confirm, safely handle and locate, ready for use, materials required for the work application

1.9. Obtain and interpret emergency procedures, and be prepared for fire/accident/emergency

2. Construct bridge deck

2.1. Select deck materials

2.2. Pre-drill connection points

2.3. Fix deck temporarily with nails

2.4. Connect stressing cables to the bridge deck

2.5. Stress and rest bridge deck for the specified timeframe

3. Install bridge deck

3.1. Re-stress bridge deck prior to removal to location

3.2. Trim bridge deck prior to securing in location

3.3. Install bridge deck at location

3.4. Bolt bridge deck to the cross girders

3.5. Re-stress bridge deck

3.6. Pack stressing cable location holes with grease

3.7. Fit protection angles, kerbs and handrails

3.8. Apply waterproofing to the deck and fittings

4. Clean up

4.1. Clear work area and dispose of or recycle materials

4.2. Clean, check, maintain and store machinery, tools and equipment

Evidence is required to be collected that demonstrates a candidate’s competency in this unit. Evidence must be relevant to the roles within this sector’s work operations and satisfy all of the requirements of the performance criteria of this unit and include evidence that the candidate:

locates and applies applicable legislation, documentation, policies and procedures

implements the requirements, procedures and techniques for the safe, effective and efficient completion of construction of specialised timber deck systems including:

selecting and using required tools and equipment

constructing timber bridge deck in accordance with production plans

selecting and preparing decking materials

stressing, resting and re-stressing bridge deck prior to moving to location

installing bridge deck at locations

fitting protection angles, kerbs and handrails

waterproofing deck and fittings

works effectively with others to undertake and complete the construction of specialised timber deck systems that meets all of the required outcomes including:

organising work activities to meet all task requirements

communicating clearly and concisely with others to receive and clarify work instructions

using a range of communication techniques and systems such as signage to advise others of work activity and exclusion zone

demonstrates completion of constructing specialised timber deck systems that safely, effectively and efficiently meets all of the required outcomes on more than one (1) occasion including:

identifying, reporting and recording hazards and risks

construction and installation of at least one (1) span of a specialised timber deck system, constructed of stressed laminated timber

The candidate must demonstrate knowledge of the construction of specialised timber deck systems through:

applying legislative, organisational and site requirements and procedures for:

site and equipment safety requirements

boat and water safety

sheet piling

Environmental Protection Act

dewatering

caulking

dial before you dig

bridge foundations

bridge heritage

calculation of material requirements

equipment types, characteristics, technical capabilities and limitations

applying and monitoring operational, maintenance and basic diagnostic procedures

applying site isolation and traffic control responsibilities and authorities

interpreting and complying with materials safety data sheets and materials handling methods

monitoring quality assurance systems and standards

preparing and/or implementing JSAs/safe work method statements