The important thing to remember when gathering evidence is that the more evidence the better - that is, the more evidence you gather to demonstrate your skills, the more confident an assessor can be that you have learned the skills not just at one point in time, but are continuing to apply and develop those skills (as opposed to just learning for the test!). Furthermore, one piece of evidence that you collect will not usualy demonstrate all the required criteria for a unit of competency, whereas multiple overlapping pieces of evidence will usually do the trick!

From the Wiki University

 

RIICTC302D - Line tunnel

What evidence can you provide to prove your understanding of each of the following citeria?

Plan and prepare to line tunnel

  1. Access, interpret and apply tunnel lining documentation and ensure the work activity is compliant
  2. Obtain, interpret, clarify and confirm work instructions before proceeding
  3. Identify, obtain and implement the traffic signage requirements
  4. Select and wear personal protective equipment appropriate for work activities
  5. Select and check for faults plant, tools and equipment to carry out tasks
  6. Identify, address and report environmental issues, potential hazards and risks
  7. Obtain and interpret emergency procedures, and be prepared for fire/accident/emergency
Access, interpret and apply tunnel lining documentation and ensure the work activity is compliant

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Obtain, interpret, clarify and confirm work instructions before proceeding

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Identify, obtain and implement the traffic signage requirements

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Select and wear personal protective equipment appropriate for work activities

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Select and check for faults plant, tools and equipment to carry out tasks

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Identify, address and report environmental issues, potential hazards and risks

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Obtain and interpret emergency procedures, and be prepared for fire/accident/emergency

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Prepare tunnel face for concrete/shotcrete

  1. Install rock anchors and/or bolts to designed locations
  2. Prepare reinforcing mesh in accordance with tunnel shape and designed lining, where specified
  3. Locate and secure reinforcing mesh in place
  4. Fix dowels to wall face to provide depth gauge to thickness of concrete/shotcrete
  5. Install drainage to the tunnel roof and walls where specified
Install rock anchors and/or bolts to designed locations

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Prepare reinforcing mesh in accordance with tunnel shape and designed lining, where specified

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Locate and secure reinforcing mesh in place

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Fix dowels to wall face to provide depth gauge to thickness of concrete/shotcrete

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Install drainage to the tunnel roof and walls where specified

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Line/shotcrete tunnel face

  1. Set up pump, pipelines and spray equipment and check for serviceability and operation
  2. Prepare and control shotcrete mix
  3. Operate pump
  4. Prepare formwork and set to specifications
  5. Provide support to shotcreter in monitoring supply and assist with elevated platform and allied equipment
  6. Apply shotcrete consistently
Set up pump, pipelines and spray equipment and check for serviceability and operation

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Prepare and control shotcrete mix

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Operate pump

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Prepare formwork and set to specifications

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Provide support to shotcreter in monitoring supply and assist with elevated platform and allied equipment

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Apply shotcrete consistently

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Clean up

  1. Clear work area and dispose of or recycle materials
  2. Clean, check, maintain and store plant, tools and equipment
  3. Carry out housekeeping activities
Clear work area and dispose of or recycle materials

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Clean, check, maintain and store plant, tools and equipment

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Carry out housekeeping activities

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Plan and prepare to line tunnel

  1. Access, interpret and apply tunnel lining documentation and ensure the work activity is compliant
  2. Obtain, interpret, clarify and confirm work instructions before proceeding
  3. Identify, obtain and implement the traffic signage requirements
  4. Select and wear personal protective equipment appropriate for work activities
  5. Select and check for faults plant, tools and equipment to carry out tasks
  6. Identify, address and report environmental issues, potential hazards and risks
  7. Obtain and interpret emergency procedures, and be prepared for fire/accident/emergency
Access, interpret and apply tunnel lining documentation and ensure the work activity is compliant

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Obtain, interpret, clarify and confirm work instructions before proceeding

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Identify, obtain and implement the traffic signage requirements

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Select and wear personal protective equipment appropriate for work activities

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Select and check for faults plant, tools and equipment to carry out tasks

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Identify, address and report environmental issues, potential hazards and risks

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Obtain and interpret emergency procedures, and be prepared for fire/accident/emergency

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Prepare tunnel face for concrete/shotcrete

  1. Install rock anchors and/or bolts to designed locations
  2. Prepare reinforcing mesh in accordance with tunnel shape and designed lining, where specified
  3. Locate and secure reinforcing mesh in place
  4. Fix dowels to wall face to provide depth gauge to thickness of concrete/shotcrete
  5. Install drainage to the tunnel roof and walls where specified
Install rock anchors and/or bolts to designed locations

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Prepare reinforcing mesh in accordance with tunnel shape and designed lining, where specified

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Locate and secure reinforcing mesh in place

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Fix dowels to wall face to provide depth gauge to thickness of concrete/shotcrete

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Install drainage to the tunnel roof and walls where specified

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Line/shotcrete tunnel face

  1. Set up pump, pipelines and spray equipment and check for serviceability and operation
  2. Prepare and control shotcrete mix
  3. Operate pump
  4. Prepare formwork and set to specifications
  5. Provide support to shotcreter in monitoring supply and assist with elevated platform and allied equipment
  6. Apply shotcrete consistently
  7. Clear work area and dispose of or recycle materials
  8. Clean, check, maintain and store plant, tools and equipment
  9. Carry out housekeeping activities
Set up pump, pipelines and spray equipment and check for serviceability and operation

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Prepare and control shotcrete mix

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Operate pump

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Prepare formwork and set to specifications

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Provide support to shotcreter in monitoring supply and assist with elevated platform and allied equipment

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Apply shotcrete consistently

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Clear work area and dispose of or recycle materials

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Clean, check, maintain and store plant, tools and equipment

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Carry out housekeeping activities

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Assessed

Teacher: ___________________________________ Date: _________

Signature: ________________________________________________

Comments:

 

 

 

 

 

 

 

 

Instructions to Assessors

Evidence Guide

1. Plan and prepare to line tunnel

1.1 Access, interpret and apply tunnel lining documentation and ensure the work activity is compliant

1.2 Obtain, interpret, clarify and confirm work instructions before proceeding

1.3 Identify, obtain and implement the traffic signage requirements

1.4 Select and wear personal protective equipment appropriate for work activities

1.5 Select and check for faults plant, tools and equipment to carry out tasks

1.6 Identify, address and report environmental issues, potential hazards and risks

1.7 Obtain and interpret emergency procedures, and be prepared for fire/accident/emergency

2. Prepare tunnel face for concrete/shotcrete

2.1 Install rock anchors and/or bolts to designed locations

2.2 Prepare reinforcing mesh in accordance with tunnel shape and designed lining, where specified

2.3 Locate and secure reinforcing mesh in place

2.4 Fix dowels to wall face to provide depth gauge to thickness of concrete/shotcrete

2.5 Install drainage to the tunnel roof and walls where specified

3. Line/shotcrete tunnel face

3.1 Set up pump, pipelines and spray equipment and check for serviceability and operation

3.2 Prepare and control shotcrete mix

3.3 Operate pump

3.4 Prepare formwork and set to specifications

3.5 Provide support to shotcreter in monitoring supply and assist with elevated platform and allied equipment

3.6 Apply shotcrete consistently

4. Clean up

4.1 Clear work area and dispose of or recycle materials

4.2 Clean, check, maintain and store plant, tools and equipment

4.3 Carry out housekeeping activities

Required Skills and Knowledge

1. Plan and prepare to line tunnel

1.1 Access, interpret and apply tunnel lining documentation and ensure the work activity is compliant

1.2 Obtain, interpret, clarify and confirm work instructions before proceeding

1.3 Identify, obtain and implement the traffic signage requirements

1.4 Select and wear personal protective equipment appropriate for work activities

1.5 Select and check for faults plant, tools and equipment to carry out tasks

1.6 Identify, address and report environmental issues, potential hazards and risks

1.7 Obtain and interpret emergency procedures, and be prepared for fire/accident/emergency

2. Prepare tunnel face for concrete/shotcrete

2.1 Install rock anchors and/or bolts to designed locations

2.2 Prepare reinforcing mesh in accordance with tunnel shape and designed lining, where specified

2.3 Locate and secure reinforcing mesh in place

2.4 Fix dowels to wall face to provide depth gauge to thickness of concrete/shotcrete

2.5 Install drainage to the tunnel roof and walls where specified

3. Line/shotcrete tunnel face

3.1 Set up pump, pipelines and spray equipment and check for serviceability and operation

3.2 Prepare and control shotcrete mix

3.3 Operate pump

3.4 Prepare formwork and set to specifications

3.5 Provide support to shotcreter in monitoring supply and assist with elevated platform and allied equipment

3.6 Apply shotcrete consistently

4. Clean up

4.1 Clear work area and dispose of or recycle materials

4.2 Clean, check, maintain and store plant, tools and equipment

4.3 Carry out housekeeping activities

Evidence is required to be collected that demonstrates a candidate’s competency in this unit. Evidence must be relevant to the roles within this sector’s work operations and satisfy all of the requirements of the performance criteria of this unit and include evidence that the candidate:

locates and applies relevant documentation, policies and procedures

implements the requirements, procedures and techniques for the safe, effective and efficient completion of lining tunnels including:

applying equipment/manual handling techniques

selecting and using relevant tools and equipment

identifying, reporting and recording hazards and risks

interpreting engineering drawings

identifying and reporting defects

works effectively with others to undertake and complete the lining of tunnels that meets all of the required outcomes including:

organising work activities to meet all task requirements

communicating clearly and concisely with others to receive and clarify work instructions

using a range of communication techniques and systems such as signage to advise others of work activity and exclusion zone

demonstrates completion of line tunnelling that safely, effectively and efficiently meets all of the required outcomes on more than one (1) occasion including:

completion of drilling and installation of rock bolts, application of reinforcing mesh and shotcreting/concreting of a minimum of a five (5) lineal metre section of tunnel

The candidate must demonstrate knowledge in lining of tunnels through:

identifying materials used in tunnel lining

applying construction principles

identifying equipment types, characteristics, technical capabilities and limitations

complying with project quality requirements

identifying and using civil construction terminology

complying with site isolation and traffic control responsibilities and authorities

complying with safety data sheets and materials handling methods

being prepared for fire/accident/emergency