NTISthis.com

Evidence Guide: RIICTC305D - Construct portals

Student: __________________________________________________

Signature: _________________________________________________

Tips for gathering evidence to demonstrate your skills

The important thing to remember when gathering evidence is that the more evidence the better - that is, the more evidence you gather to demonstrate your skills, the more confident an assessor can be that you have learned the skills not just at one point in time, but are continuing to apply and develop those skills (as opposed to just learning for the test!). Furthermore, one piece of evidence that you collect will not usualy demonstrate all the required criteria for a unit of competency, whereas multiple overlapping pieces of evidence will usually do the trick!

From the Wiki University

 

RIICTC305D - Construct portals

What evidence can you provide to prove your understanding of each of the following citeria?

Plan and prepare to construct portals

  1. Access, interpret and apply construct portals documentation and ensure the work activity is compliant
  2. Obtain, interpret, clarify and confirm work instructions before proceeding
  3. Identify, obtain and implement the traffic signage requirements
  4. Select and check for faults plant, tools and equipment to carry out tasks
  5. Select and wear personal protective equipment appropriate for work activities
  6. Obtain and interpret emergency procedures, and be prepared for fire/accident/emergency
  7. Identify preliminary ground work requirements to support portal surrounds prior to excavation
  8. Identify, address and report environmental issues, potential hazards and risks
Access, interpret and apply construct portals documentation and ensure the work activity is compliant

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Obtain, interpret, clarify and confirm work instructions before proceeding

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Identify, obtain and implement the traffic signage requirements

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Select and check for faults plant, tools and equipment to carry out tasks

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Select and wear personal protective equipment appropriate for work activities

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Obtain and interpret emergency procedures, and be prepared for fire/accident/emergency

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Identify preliminary ground work requirements to support portal surrounds prior to excavation

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Identify, address and report environmental issues, potential hazards and risks

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Excavate portal shape

  1. Determine location, alignment and direction portals from details contained in job drawings and specifications
  2. Identify and apply method of construction for portal
  3. Prepare material for the construction process of the selected portals according to design plans and specifications
  4. Complete excavation to plan
  5. Control dust and noise suppression in accordance with EPA and WHS requirements
Determine location, alignment and direction portals from details contained in job drawings and specifications

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Identify and apply method of construction for portal

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Prepare material for the construction process of the selected portals according to design plans and specifications

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Complete excavation to plan

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Control dust and noise suppression in accordance with EPA and WHS requirements

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Support excavation and form portal surrounds

  1. Install sheeting and/or first set to specifications
  2. Excavate and trim battering to design and drainage specifications
Install sheeting and/or first set to specifications

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Excavate and trim battering to design and drainage specifications

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Install ground support

  1. Identify ground support from project drawings and specifications
  2. Construct base to detail drawings and specifications
  3. Install ground support and shotcrete/concrete
  4. Place drainage and seepage provisions
Identify ground support from project drawings and specifications

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Construct base to detail drawings and specifications

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Install ground support and shotcrete/concrete

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Place drainage and seepage provisions

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

5. Conduct housekeeping activities

  1. Clear work area and dispose of or recycle materials
  2. Clean, check, maintain and store plant, tools and equipment
  3. Carry out housekeeping activities
Clear work area and dispose of or recycle materials

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Clean, check, maintain and store plant, tools and equipment

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Carry out housekeeping activities

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Plan and prepare to construct portals

  1. Access, interpret and apply construct portals documentation and ensure the work activity is compliant
  2. Obtain, interpret, clarify and confirm work instructions before proceeding
  3. Identify, obtain and implement the traffic signage requirements
  4. Select and check for faults plant, tools and equipment to carry out tasks
  5. Select and wear personal protective equipment appropriate for work activities
  6. Obtain and interpret emergency procedures, and be prepared for fire/accident/emergency
  7. Identify preliminary ground work requirements to support portal surrounds prior to excavation
  8. Identify, address and report environmental issues, potential hazards and risks
Access, interpret and apply construct portals documentation and ensure the work activity is compliant

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Obtain, interpret, clarify and confirm work instructions before proceeding

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Identify, obtain and implement the traffic signage requirements

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Select and check for faults plant, tools and equipment to carry out tasks

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Select and wear personal protective equipment appropriate for work activities

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Obtain and interpret emergency procedures, and be prepared for fire/accident/emergency

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Identify preliminary ground work requirements to support portal surrounds prior to excavation

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Identify, address and report environmental issues, potential hazards and risks

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Excavate portal shape

  1. Determine location, alignment and direction portals from details contained in job drawings and specifications
  2. Identify and apply method of construction for portal
  3. Prepare material for the construction process of the selected portals according to design plans and specifications
  4. Complete excavation to plan
  5. Control dust and noise suppression in accordance with EPA and WHS requirements
Determine location, alignment and direction portals from details contained in job drawings and specifications

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Identify and apply method of construction for portal

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Prepare material for the construction process of the selected portals according to design plans and specifications

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Complete excavation to plan

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Control dust and noise suppression in accordance with EPA and WHS requirements

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Support excavation and form portal surrounds

  1. Install sheeting and/or first set to specifications
  2. Excavate and trim battering to design and drainage specifications
Install sheeting and/or first set to specifications

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Excavate and trim battering to design and drainage specifications

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Install ground support

  1. Identify ground support from project drawings and specifications
  2. Construct base to detail drawings and specifications
  3. Install ground support and shotcrete/concrete
  4. Place drainage and seepage provisions
Identify ground support from project drawings and specifications

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Construct base to detail drawings and specifications

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Install ground support and shotcrete/concrete

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Place drainage and seepage provisions

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Conduct housekeeping activities

  1. Clear work area and dispose of or recycle materials
  2. Clean, check, maintain and store plant, tools and equipment
  3. Carry out housekeeping activities
Clear work area and dispose of or recycle materials

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Clean, check, maintain and store plant, tools and equipment

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Carry out housekeeping activities

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Assessed

Teacher: ___________________________________ Date: _________

Signature: ________________________________________________

Comments:

 

 

 

 

 

 

 

 

Instructions to Assessors

Evidence Guide

1. Plan and prepare to construct portals

1.1 Access, interpret and apply construct portals documentation and ensure the work activity is compliant

1.2 Obtain, interpret, clarify and confirm work instructions before proceeding

1.3 Identify, obtain and implement the traffic signage requirements

1.4 Select and check for faults plant, tools and equipment to carry out tasks

1.5 Select and wear personal protective equipment appropriate for work activities

1.6 Obtain and interpret emergency procedures, and be prepared for fire/accident/emergency

1.7 Identify preliminary ground work requirements to support portal surrounds prior to excavation

1.8 Identify, address and report environmental issues, potential hazards and risks

2. Excavate portal shape

2.1 Determine location, alignment and direction portals from details contained in job drawings and specifications

2.2 Identify and apply method of construction for portal

2.3 Prepare material for the construction process of the selected portals according to design plans and specifications

2.4 Complete excavation to plan

2.5 Control dust and noise suppression in accordance with EPA and WHS requirements

3. Support excavation and form portal surrounds

3.1 Install sheeting and/or first set to specifications

3.2 Excavate and trim battering to design and drainage specifications

4. Install ground support

4.1 Identify ground support from project drawings and specifications

4.2 Construct base to detail drawings and specifications

4.3 Install ground support and shotcrete/concrete

4.4 Place drainage and seepage provisions

5. Conduct housekeeping activities

5.1 Clear work area and dispose of or recycle materials

5.2 Clean, check, maintain and store plant, tools and equipment

5.3 Carry out housekeeping activities

Required Skills and Knowledge

1. Plan and prepare to construct portals

1.1 Access, interpret and apply construct portals documentation and ensure the work activity is compliant

1.2 Obtain, interpret, clarify and confirm work instructions before proceeding

1.3 Identify, obtain and implement the traffic signage requirements

1.4 Select and check for faults plant, tools and equipment to carry out tasks

1.5 Select and wear personal protective equipment appropriate for work activities

1.6 Obtain and interpret emergency procedures, and be prepared for fire/accident/emergency

1.7 Identify preliminary ground work requirements to support portal surrounds prior to excavation

1.8 Identify, address and report environmental issues, potential hazards and risks

2. Excavate portal shape

2.1 Determine location, alignment and direction portals from details contained in job drawings and specifications

2.2 Identify and apply method of construction for portal

2.3 Prepare material for the construction process of the selected portals according to design plans and specifications

2.4 Complete excavation to plan

2.5 Control dust and noise suppression in accordance with EPA and WHS requirements

3. Support excavation and form portal surrounds

3.1 Install sheeting and/or first set to specifications

3.2 Excavate and trim battering to design and drainage specifications

4. Install ground support

4.1 Identify ground support from project drawings and specifications

4.2 Construct base to detail drawings and specifications

4.3 Install ground support and shotcrete/concrete

4.4 Place drainage and seepage provisions

5. Conduct housekeeping activities

5.1 Clear work area and dispose of or recycle materials

5.2 Clean, check, maintain and store plant, tools and equipment

5.3 Carry out housekeeping activities

Evidence is required to be collected that demonstrates a candidate’s competency in this unit. Evidence must be relevant to the roles within this sector’s work operations and satisfy all of the requirements of the performance criteria of this unit and include evidence that the candidate:

locates and applies relevant legislation documentation, policies and procedures

implements the requirements, procedures and techniques for the safe, effective and efficient completion of constructing portals including:

applying equipment/manual handling techniques

selecting and using relevant tools and equipment

identifying, reporting and recording hazards and risks

installation of portals

works effectively with others to undertake and complete the constructing of portals that meets all of the required outcomes including:

organising work activities to meet all task requirements

communicating clearly and concisely with others to receive and clarify work instructions

using a range of communication techniques and systems such as signage to advise others of work activity and exclusion zone

demonstrates completion of constructing portals that safely, effectively and efficiently meets all of the required outcomes on more than one (1) occasion including:

the construction of a portal using an excavation ground support system

The candidate must demonstrate knowledge in construct portals through:

basic principles of soil technology for civil works

types and purposes of portals

principles of ground support

types, functions, characteristics and limitations of excavation ground support systems

types, functions, characteristics and limitations of finishing ground support systems

ground support systems installation techniques

construction principles

equipment types, characteristics, technical capabilities and limitations

project quality requirements

civil construction terminology

site isolation and traffic control responsibilities and authorities

safety data sheets and materials handling methods

prepared for fire/accident/emergency