NTISthis.com

Evidence Guide: RIICTC401D - Apply the principles of tunnel construction

Student: __________________________________________________

Signature: _________________________________________________

Tips for gathering evidence to demonstrate your skills

The important thing to remember when gathering evidence is that the more evidence the better - that is, the more evidence you gather to demonstrate your skills, the more confident an assessor can be that you have learned the skills not just at one point in time, but are continuing to apply and develop those skills (as opposed to just learning for the test!). Furthermore, one piece of evidence that you collect will not usualy demonstrate all the required criteria for a unit of competency, whereas multiple overlapping pieces of evidence will usually do the trick!

From the Wiki University

 

RIICTC401D - Apply the principles of tunnel construction

What evidence can you provide to prove your understanding of each of the following citeria?

Plan and prepare to apply the principles of tunnel construction

  1. Access, interpret and apply principles of tunnel construction documentation and ensure the work activity is compliant
  2. Access, interpret and clarify the specific task information and requirements
  3. Ensure a job plan, is available which makes best use of the available resources and meets the tunnel construction task requirements
  4. Identify the training requirements of team members and develop training plans
Access, interpret and apply principles of tunnel construction documentation and ensure the work activity is compliant

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Access, interpret and clarify the specific task information and requirements

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Ensure a job plan, is available which makes best use of the available resources and meets the tunnel construction task requirements

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Identify the training requirements of team members and develop training plans

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Ensure appropriate initiation of tasks is carried out

  1. Confirm that the necessary resources are available
  2. Ensure clear and timely instructions are communicated to team members and others involved
  3. Ensure appropriate set out of tasks
Confirm that the necessary resources are available

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Ensure clear and timely instructions are communicated to team members and others involved

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Ensure appropriate set out of tasks

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Oversee the execution of tasks

  1. Monitor tunnel construction task performance to ensure it achieves the required outcomes
  2. Initiate adjustments to tunnel construction practice or job plan and ensure safe execution of work and achievement of required outcomes
  3. Ensure plant equipment and tools maintenance requirements are carried out and recorded
  4. Implement training plans
Monitor tunnel construction task performance to ensure it achieves the required outcomes

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Initiate adjustments to tunnel construction practice or job plan and ensure safe execution of work and achievement of required outcomes

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Ensure plant equipment and tools maintenance requirements are carried out and recorded

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Implement training plans

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Report on the execution of tasks

  1. Complete and submit reports
  2. Recommend changes to improve the safety, efficiency and effectiveness of the execution of tasks
Complete and submit reports

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Recommend changes to improve the safety, efficiency and effectiveness of the execution of tasks

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Plan and prepare to apply the principles of tunnel construction

  1. Access, interpret and apply principles of tunnel construction documentation and ensure the work activity is compliant
  2. Access, interpret and clarify the specific task information and requirements
  3. Ensure a job plan, is available which makes best use of the available resources and meets the tunnel construction task requirements
  4. Identify the training requirements of team members and develop training plans
Access, interpret and apply principles of tunnel construction documentation and ensure the work activity is compliant

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Access, interpret and clarify the specific task information and requirements

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Ensure a job plan, is available which makes best use of the available resources and meets the tunnel construction task requirements

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Identify the training requirements of team members and develop training plans

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Ensure appropriate initiation of tasks is carried out

  1. Confirm that the necessary resources are available
  2. Ensure clear and timely instructions are communicated to team members and others involved
  3. Ensure appropriate set out of tasks
Confirm that the necessary resources are available

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Ensure clear and timely instructions are communicated to team members and others involved

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Ensure appropriate set out of tasks

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Oversee the execution of tasks

  1. Monitor tunnel construction task performance to ensure it achieves the required outcomes
  2. Initiate adjustments to tunnel construction practice or job plan and ensure safe execution of work and achievement of required outcomes
  3. Ensure plant equipment and tools maintenance requirements are carried out and recorded
  4. Implement training plans
Monitor tunnel construction task performance to ensure it achieves the required outcomes

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Initiate adjustments to tunnel construction practice or job plan and ensure safe execution of work and achievement of required outcomes

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Ensure plant equipment and tools maintenance requirements are carried out and recorded

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Implement training plans

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Report on the execution of tasks

  1. Complete and submit reports
  2. Recommend changes to improve the safety, efficiency and effectiveness of the execution of tasks
Complete and submit reports

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Recommend changes to improve the safety, efficiency and effectiveness of the execution of tasks

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Assessed

Teacher: ___________________________________ Date: _________

Signature: ________________________________________________

Comments:

 

 

 

 

 

 

 

 

Instructions to Assessors

Evidence Guide

1. Plan and prepare to apply the principles of tunnel construction

1.1 Access, interpret and apply principles of tunnel construction documentation and ensure the work activity is compliant

1.2 Access, interpret and clarify the specific task information and requirements

1.3 Ensure a job plan, is available which makes best use of the available resources and meets the tunnel construction task requirements

1.4 Identify the training requirements of team members and develop training plans

2. Ensure appropriate initiation of tasks is carried out

2.1 Confirm that the necessary resources are available

2.2 Ensure clear and timely instructions are communicated to team members and others involved

2.3 Ensure appropriate set out of tasks

3. Oversee the execution of tasks

3.1 Monitor tunnel construction task performance to ensure it achieves the required outcomes

3.2 Initiate adjustments to tunnel construction practice or job plan and ensure safe execution of work and achievement of required outcomes

3.3 Ensure plant equipment and tools maintenance requirements are carried out and recorded

3.4 Implement training plans

4. Report on the execution of tasks

4.1 Complete and submit reports

4.2 Recommend changes to improve the safety, efficiency and effectiveness of the execution of tasks

Required Skills and Knowledge

1. Plan and prepare to apply the principles of tunnel construction

1.1 Access, interpret and apply principles of tunnel construction documentation and ensure the work activity is compliant

1.2 Access, interpret and clarify the specific task information and requirements

1.3 Ensure a job plan, is available which makes best use of the available resources and meets the tunnel construction task requirements

1.4 Identify the training requirements of team members and develop training plans

2. Ensure appropriate initiation of tasks is carried out

2.1 Confirm that the necessary resources are available

2.2 Ensure clear and timely instructions are communicated to team members and others involved

2.3 Ensure appropriate set out of tasks

3. Oversee the execution of tasks

3.1 Monitor tunnel construction task performance to ensure it achieves the required outcomes

3.2 Initiate adjustments to tunnel construction practice or job plan and ensure safe execution of work and achievement of required outcomes

3.3 Ensure plant equipment and tools maintenance requirements are carried out and recorded

3.4 Implement training plans

4. Report on the execution of tasks

4.1 Complete and submit reports

4.2 Recommend changes to improve the safety, efficiency and effectiveness of the execution of tasks

vidence is required to be collected that demonstrates a candidate’s competency in this unit. Evidence must be relevant to the roles within this sector’s work operations and satisfy all of the requirements of the performance criteria of this unit and include evidence that the candidate:

locates and applies relevant legislation, documentation, policies and procedures

works effectively with others to undertake and complete the applying of the principles of tunnel construction that meets all of the required outcomes including:

communicating clear and timely instructions to those involved

preparing for and conducting briefings, toolbox and site meetings

maintaining clear and legible written records and the reports

demonstrates completion of the principles of tunnel construction that safely, effectively and efficiently meets all of the required outcomes on more than one (1) occasion including:

successful supervision of tunnel construction tasks

interpreting tunnel construction materials properties and test results

providing recommendations for the improvement of the safe, effective and efficient execution of tunnel construction tasks

preparation of job plan, which includes at least five (5) of the following:

human resource requirements

plant and machinery requirements

construction materials requirements

sub-contractor support requirements

waste disposal requirements

coordination requirements

activity scheduling

materials delivery scheduling

risk assessment and management requirements

occupational health and safety requirements

quality management requirements, including testing scheduling requirements

traffic management requirements

environmental requirements

task monitoring requirements

task performance monitoring requirements

communication requirements

reporting requirements

assessment of resource requirements including at least two (2) of the following:

labour

plant, equipment and tools

highway haulage vehicles

construction materials

shoring materials

sub-contractor services

The candidate must demonstrate knowledge in applying the principles of tunnel construction through:

engineering survey principles

materials quality and delivery requirements and procedures

shoring requirements and procedures

slope management requirements and procedures

tunnel construction plant and equipment capabilities and application

operational techniques for the execution of tunnel construction tasks

job plan drafting of and administration requirements and procedures

tunnel construction and related activities’ terminology

set out requirements and procedures

scheduling work activities

relationship between various areas of resources and infrastructure industries

monitoring methods

resource requirements

activities scheduling

estimating principles

civil works construction sequencing