The important thing to remember when gathering evidence is that the more evidence the better - that is, the more evidence you gather to demonstrate your skills, the more confident an assessor can be that you have learned the skills not just at one point in time, but are continuing to apply and develop those skills (as opposed to just learning for the test!). Furthermore, one piece of evidence that you collect will not usualy demonstrate all the required criteria for a unit of competency, whereas multiple overlapping pieces of evidence will usually do the trick!

From the Wiki University

 

RIICTT302D - Conduct impact moling, ramming and augering

What evidence can you provide to prove your understanding of each of the following citeria?

Plan and prepare for impact moling, ramming and augering

  1. Access, interpret and apply impact moling, ramming and augering documentation and ensure the work activity is compliant
  2. Obtain, read, interpret, clarify and confirm work requirements
  3. Identify and address potential risks, hazards and environmental issues and implement control measures
  4. Select and wear personal protective equipment appropriate for work activities
  5. Identify, obtain and implement traffic signage requirements
  6. Select tools and equipment for the task, check for and report faults
Access, interpret and apply impact moling, ramming and augering documentation and ensure the work activity is compliant

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Obtain, read, interpret, clarify and confirm work requirements

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Identify and address potential risks, hazards and environmental issues and implement control measures

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Select and wear personal protective equipment appropriate for work activities

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Identify, obtain and implement traffic signage requirements

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Select tools and equipment for the task, check for and report faults

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Determine boring requirements

  1. Determine location, alignment direction, level and grade of bore from drawings and specifications
  2. Use above and below ground survey instruments and determine the bore pathway for underground vertical and horizontal alignment
  3. Conduct visual geological investigation of alignment and determine the differing soil types and groundwater conditions
  4. Select bore head for the strata
  5. Position, anchor/stake down boring equipment
Determine location, alignment direction, level and grade of bore from drawings and specifications

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Use above and below ground survey instruments and determine the bore pathway for underground vertical and horizontal alignment

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Conduct visual geological investigation of alignment and determine the differing soil types and groundwater conditions

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Select bore head for the strata

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Position, anchor/stake down boring equipment

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Conduct equipment checks

  1. Carry out start-up, shutdown and communication procedures
  2. Check equipment controls and functions, including implements or other attachments, anchors and/or stabilising equipment for serviceability and report faults
  3. Conduct inspection and fault finding
  4. Carry out equipment maintenance
Carry out start-up, shutdown and communication procedures

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Check equipment controls and functions, including implements or other attachments, anchors and/or stabilising equipment for serviceability and report faults

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Conduct inspection and fault finding

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Carry out equipment maintenance

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Drive bore hole

  1. Prepare launch and receiving pits in accordance with site requirements to accommodate bore rig and tools
  2. Prepare launch and receiving pits for inserting and receiving bore head in accordance with site requirements
  3. Establish traverse line of bore head to receiving pit prior to launching mole
  4. Monitor machine for continuity of production to site conditions
Prepare launch and receiving pits in accordance with site requirements to accommodate bore rig and tools

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Prepare launch and receiving pits for inserting and receiving bore head in accordance with site requirements

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Establish traverse line of bore head to receiving pit prior to launching mole

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Monitor machine for continuity of production to site conditions

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Clean up

  1. Clear work area and dispose of, reuse or recycle materials
  2. Clean, check, maintain and store plant, tools and equipment
Clear work area and dispose of, reuse or recycle materials

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Clean, check, maintain and store plant, tools and equipment

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Plan and prepare for impact moling, ramming and augering

  1. Access, interpret and apply impact moling, ramming and augering documentation and ensure the work activity is compliant
  2. Obtain, read, interpret, clarify and confirm work requirements
  3. Identify and address potential risks, hazards and environmental issues and implement control measures
  4. Select and wear personal protective equipment appropriate for work activities
  5. Identify, obtain and implement traffic signage requirements
  6. Select tools and equipment for the task, check for and report faults
Access, interpret and apply impact moling, ramming and augering documentation and ensure the work activity is compliant

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Obtain, read, interpret, clarify and confirm work requirements

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Identify and address potential risks, hazards and environmental issues and implement control measures

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Select and wear personal protective equipment appropriate for work activities

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Identify, obtain and implement traffic signage requirements

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Select tools and equipment for the task, check for and report faults

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Determine boring requirements

  1. Determine location, alignment direction, level and grade of bore from drawings and specifications
  2. Use above and below ground survey instruments and determine the bore pathway for underground vertical and horizontal alignment
  3. Conduct visual geological investigation of alignment and determine the differing soil types and groundwater conditions
  4. Select bore head for the strata
  5. Position, anchor/stake down boring equipment
Determine location, alignment direction, level and grade of bore from drawings and specifications

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Use above and below ground survey instruments and determine the bore pathway for underground vertical and horizontal alignment

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Conduct visual geological investigation of alignment and determine the differing soil types and groundwater conditions

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Select bore head for the strata

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Position, anchor/stake down boring equipment

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Conduct equipment checks

  1. Carry out start-up, shutdown and communication procedures
  2. Check equipment controls and functions, including implements or other attachments, anchors and/or stabilising equipment for serviceability and report faults
  3. Conduct inspection and fault finding
  4. Carry out equipment maintenance
Carry out start-up, shutdown and communication procedures

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Check equipment controls and functions, including implements or other attachments, anchors and/or stabilising equipment for serviceability and report faults

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Conduct inspection and fault finding

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Carry out equipment maintenance

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Drive bore hole

  1. Prepare launch and receiving pits in accordance with site requirements to accommodate bore rig and tools
  2. Prepare launch and receiving pits for inserting and receiving bore head in accordance with site requirements
  3. Establish traverse line of bore head to receiving pit prior to launching mole
  4. Monitor machine for continuity of production to site conditions
  5. Clear work area and dispose of, reuse or recycle materials
  6. Clean, check, maintain and store plant, tools and equipment
Prepare launch and receiving pits in accordance with site requirements to accommodate bore rig and tools

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Prepare launch and receiving pits for inserting and receiving bore head in accordance with site requirements

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Establish traverse line of bore head to receiving pit prior to launching mole

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Monitor machine for continuity of production to site conditions

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Clear work area and dispose of, reuse or recycle materials

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Clean, check, maintain and store plant, tools and equipment

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Assessed

Teacher: ___________________________________ Date: _________

Signature: ________________________________________________

Comments:

 

 

 

 

 

 

 

 

Instructions to Assessors

Evidence Guide

1. Plan and prepare for impact moling, ramming and augering

1.1 Access, interpret and apply impact moling, ramming and augering documentation and ensure the work activity is compliant

1.2 Obtain, read, interpret, clarify and confirm work requirements

1.3 Identify and address potential risks, hazards and environmental issues and implement control measures

1.4 Select and wear personal protective equipment appropriate for work activities

1.5 Identify, obtain and implement traffic signage requirements

1.6 Select tools and equipment for the task, check for and report faults

2. Determine boring requirements

2.1 Determine location, alignment direction, level and grade of bore from drawings and specifications

2.2 Use above and below ground survey instruments and determine the bore pathway for underground vertical and horizontal alignment

2.3 Conduct visual geological investigation of alignment and determine the differing soil types and groundwater conditions

2.4 Select bore head for the strata

2.5 Position, anchor/stake down boring equipment

3. Conduct equipment checks

3.1 Carry out start-up, shutdown and communication procedures

3.2 Check equipment controls and functions, including implements or other attachments, anchors and/or stabilising equipment for serviceability and report faults

3.3 Conduct inspection and fault finding

3.4 Carry out equipment maintenance

4. Drive bore hole

4.1 Prepare launch and receiving pits in accordance with site requirements to accommodate bore rig and tools

4.2 Prepare launch and receiving pits for inserting and receiving bore head in accordance with site requirements

4.3 Establish traverse line of bore head to receiving pit prior to launching mole

4.4 Monitor machine for continuity of production to site conditions

5. Clean up

5.1 Clear work area and dispose of, reuse or recycle materials

5.2 Clean, check, maintain and store plant, tools and equipment

Required Skills and Knowledge

1. Plan and prepare for impact moling, ramming and augering

1.1 Access, interpret and apply impact moling, ramming and augering documentation and ensure the work activity is compliant

1.2 Obtain, read, interpret, clarify and confirm work requirements

1.3 Identify and address potential risks, hazards and environmental issues and implement control measures

1.4 Select and wear personal protective equipment appropriate for work activities

1.5 Identify, obtain and implement traffic signage requirements

1.6 Select tools and equipment for the task, check for and report faults

2. Determine boring requirements

2.1 Determine location, alignment direction, level and grade of bore from drawings and specifications

2.2 Use above and below ground survey instruments and determine the bore pathway for underground vertical and horizontal alignment

2.3 Conduct visual geological investigation of alignment and determine the differing soil types and groundwater conditions

2.4 Select bore head for the strata

2.5 Position, anchor/stake down boring equipment

3. Conduct equipment checks

3.1 Carry out start-up, shutdown and communication procedures

3.2 Check equipment controls and functions, including implements or other attachments, anchors and/or stabilising equipment for serviceability and report faults

3.3 Conduct inspection and fault finding

3.4 Carry out equipment maintenance

4. Drive bore hole

4.1 Prepare launch and receiving pits in accordance with site requirements to accommodate bore rig and tools

4.2 Prepare launch and receiving pits for inserting and receiving bore head in accordance with site requirements

4.3 Establish traverse line of bore head to receiving pit prior to launching mole

4.4 Monitor machine for continuity of production to site conditions

5. Clean up

5.1 Clear work area and dispose of, reuse or recycle materials

5.2 Clean, check, maintain and store plant, tools and equipment

Evidence is required to be collected that demonstrates a candidate’s competency in this unit. Evidence must be relevant to the roles within this sector’s work operations and satisfy all of the requirements of the performance criteria of this unit and include evidence that the candidate:

locates and applies applicable documentation, policies and procedures

works effectively with others to undertake and complete impact moling, ramming and augering that meets all of the required outcomes including:

organising work activities to meet all task requirements

communicating clearly and concisely with others to receive and clarify work instructions

using a range of communication techniques and systems such as signage to advise others of work activity and exclusion zones

demonstrates completion of conducting impact moling, ramming and augering that safely, effectively and efficiently meets all of the required outcomes on more than one (1) occasion including:

completing at least 50 metres of impact moling, ramming and augering

using systems to monitor task

confirming the work instructions, plans, specifications and quality requirements

The candidate must demonstrate knowledge in impact moling, ramming and augering through:

equipment operational requirements and procedures

site and equipment safety requirements

the correct drilling fluids

categories of horizontal directional drilling

use of laser control equipment

manual handling requirements and procedures

use of electronic cable locating devices

slinging procedures

engineering drawings, plans and specifications

operational, maintenance and basic diagnostic procedures

site isolation and traffic control responsibilities

materials safety data sheets and materials handling methods

equipment types, characteristics, technical capabilities and limitations using civil construction terminology