NTISthis.com

Evidence Guide: RIICTT306D - Install cure in-place linings for existing pipeline systems

Student: __________________________________________________

Signature: _________________________________________________

Tips for gathering evidence to demonstrate your skills

The important thing to remember when gathering evidence is that the more evidence the better - that is, the more evidence you gather to demonstrate your skills, the more confident an assessor can be that you have learned the skills not just at one point in time, but are continuing to apply and develop those skills (as opposed to just learning for the test!). Furthermore, one piece of evidence that you collect will not usualy demonstrate all the required criteria for a unit of competency, whereas multiple overlapping pieces of evidence will usually do the trick!

From the Wiki University

 

RIICTT306D - Install cure in-place linings for existing pipeline systems

What evidence can you provide to prove your understanding of each of the following citeria?

Plan and prepare to install cure in-place linings for existing pipeline systems

  1. Access, interpret and apply cure in-place linings for existing pipeline system installation documentation and ensure the work activity is compliant
  2. Obtain, read, interpret, clarify and confirm work requirements
  3. Identify and address potential risks, hazards and environmental issues and implement control measures
  4. Select and wear personal protective equipment appropriate for work activities
  5. Identify, obtain and implement signage requirements from the project traffic management plan
  6. Identify and select plant, tools and equipment, check for serviceability and rectify or report any faults
Access, interpret and apply cure in-place linings for existing pipeline system installation documentation and ensure the work activity is compliant

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Obtain, read, interpret, clarify and confirm work requirements

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Identify and address potential risks, hazards and environmental issues and implement control measures

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Select and wear personal protective equipment appropriate for work activities

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Identify, obtain and implement signage requirements from the project traffic management plan

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Identify and select plant, tools and equipment, check for serviceability and rectify or report any faults

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Perform site survey

  1. Notify and obtain approval from property owners and occupiers for entry onto their property
  2. Determine site conditions by visual inspection, plans, discussion with land owners and information from service utilities
  3. Located underground utilities
  4. Maintain system serviceability during rehabilitation works
  5. Survey and record existing site conditions
Notify and obtain approval from property owners and occupiers for entry onto their property

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Determine site conditions by visual inspection, plans, discussion with land owners and information from service utilities

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Located underground utilities

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Maintain system serviceability during rehabilitation works

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Survey and record existing site conditions

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Initiate rehabilitation work

  1. Prepare entry and exit pits where specified
  2. Identify, interpret and apply confined space entry procedures
  3. Monitor installation process and finished product to ensure conformity to the design requirements
Prepare entry and exit pits where specified

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Identify, interpret and apply confined space entry procedures

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Monitor installation process and finished product to ensure conformity to the design requirements

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Complete cure in-place lining

  1. Determine fault with the aid of plans, drawings, CCTV recordings or other mechanisms
  2. Select resin impregnated liners appropriate to the fault
  3. Apply pressure cleaning to the designated location
  4. Install cure in-place lining material
  5. Conduct curing process
  6. Correctly secure and seal termination at ends of process
  7. Open junctions for inspection and operation
  8. Monitor installation process and finished product to ensure conformity to the design requirements
Determine fault with the aid of plans, drawings, CCTV recordings or other mechanisms

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Select resin impregnated liners appropriate to the fault

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Apply pressure cleaning to the designated location

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Install cure in-place lining material

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Conduct curing process

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Correctly secure and seal termination at ends of process

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Open junctions for inspection and operation

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Monitor installation process and finished product to ensure conformity to the design requirements

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Clean up

  1. Clear work area and dispose of, reuse or recycle materials
  2. Clean, check, maintain and store plant, tools and equipment
Clear work area and dispose of, reuse or recycle materials

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Clean, check, maintain and store plant, tools and equipment

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Plan and prepare to install cure in-place linings for existing pipeline systems

  1. Access, interpret and apply cure in-place linings for existing pipeline system installation documentation and ensure the work activity is compliant
  2. Obtain, read, interpret, clarify and confirm work requirements
  3. Identify and address potential risks, hazards and environmental issues and implement control measures
  4. Select and wear personal protective equipment appropriate for work activities
  5. Identify, obtain and implement signage requirements from the project traffic management plan
  6. Identify and select plant, tools and equipment, check for serviceability and rectify or report any faults
Access, interpret and apply cure in-place linings for existing pipeline system installation documentation and ensure the work activity is compliant

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Obtain, read, interpret, clarify and confirm work requirements

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Identify and address potential risks, hazards and environmental issues and implement control measures

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Select and wear personal protective equipment appropriate for work activities

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Identify, obtain and implement signage requirements from the project traffic management plan

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Identify and select plant, tools and equipment, check for serviceability and rectify or report any faults

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Perform site survey

  1. Notify and obtain approval from property owners and occupiers for entry onto their property
  2. Determine site conditions by visual inspection, plans, discussion with land owners and information from service utilities
  3. Located underground utilities
  4. Maintain system serviceability during rehabilitation works
  5. Survey and record existing site conditions
Notify and obtain approval from property owners and occupiers for entry onto their property

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Determine site conditions by visual inspection, plans, discussion with land owners and information from service utilities

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Located underground utilities

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Maintain system serviceability during rehabilitation works

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Survey and record existing site conditions

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Initiate rehabilitation work

  1. Prepare entry and exit pits where specified
  2. Identify, interpret and apply confined space entry procedures
  3. Monitor installation process and finished product to ensure conformity to the design requirements
Prepare entry and exit pits where specified

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Identify, interpret and apply confined space entry procedures

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Monitor installation process and finished product to ensure conformity to the design requirements

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Complete cure in-place lining

  1. Determine fault with the aid of plans, drawings, CCTV recordings or other mechanisms
  2. Select resin impregnated liners appropriate to the fault
  3. Apply pressure cleaning to the designated location
  4. Install cure in-place lining material
  5. Conduct curing process
  6. Correctly secure and seal termination at ends of process
  7. Open junctions for inspection and operation
  8. Monitor installation process and finished product to ensure conformity to the design requirements
  9. Clear work area and dispose of, reuse or recycle materials
  10. Clean, check, maintain and store plant, tools and equipment
Determine fault with the aid of plans, drawings, CCTV recordings or other mechanisms

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Select resin impregnated liners appropriate to the fault

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Apply pressure cleaning to the designated location

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Install cure in-place lining material

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Conduct curing process

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Correctly secure and seal termination at ends of process

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Open junctions for inspection and operation

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Monitor installation process and finished product to ensure conformity to the design requirements

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Clear work area and dispose of, reuse or recycle materials

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Clean, check, maintain and store plant, tools and equipment

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Assessed

Teacher: ___________________________________ Date: _________

Signature: ________________________________________________

Comments:

 

 

 

 

 

 

 

 

Instructions to Assessors

Evidence Guide

1. Plan and prepare to install cure in-place linings for existing pipeline systems

1.1 Access, interpret and apply cure in-place linings for existing pipeline system installation documentation and ensure the work activity is compliant

1.2 Obtain, read, interpret, clarify and confirm work requirements

1.3 Identify and address potential risks, hazards and environmental issues and implement control measures

1.4 Select and wear personal protective equipment appropriate for work activities

1.5 Identify, obtain and implement signage requirements from the project traffic management plan

1.6 Identify and select plant, tools and equipment, check for serviceability and rectify or report any faults

2. Perform site survey

2.1 Notify and obtain approval from property owners and occupiers for entry onto their property

2.2 Determine site conditions by visual inspection, plans, discussion with land owners and information from service utilities

2.3 Located underground utilities

2.4 Maintain system serviceability during rehabilitation works

2.5 Survey and record existing site conditions

3. Initiate rehabilitation work

3.1 Prepare entry and exit pits where specified

3.2 Identify, interpret and apply confined space entry procedures

3.3 Monitor installation process and finished product to ensure conformity to the design requirements

4. Complete cure in-place lining

4.1 Determine fault with the aid of plans, drawings, CCTV recordings or other mechanisms

4.2 Select resin impregnated liners appropriate to the fault

4.3 Apply pressure cleaning to the designated location

4.4 Install cure in-place lining material

4.5 Conduct curing process

4.6 Correctly secure and seal termination at ends of process

4.7 Open junctions for inspection and operation

4.8 Monitor installation process and finished product to ensure conformity to the design requirements

5. Clean up

5.1 Clear work area and dispose of, reuse or recycle materials

5.2 Clean, check, maintain and store plant, tools and equipment

Required Skills and Knowledge

1. Plan and prepare to install cure in-place linings for existing pipeline systems

1.1 Access, interpret and apply cure in-place linings for existing pipeline system installation documentation and ensure the work activity is compliant

1.2 Obtain, read, interpret, clarify and confirm work requirements

1.3 Identify and address potential risks, hazards and environmental issues and implement control measures

1.4 Select and wear personal protective equipment appropriate for work activities

1.5 Identify, obtain and implement signage requirements from the project traffic management plan

1.6 Identify and select plant, tools and equipment, check for serviceability and rectify or report any faults

2. Perform site survey

2.1 Notify and obtain approval from property owners and occupiers for entry onto their property

2.2 Determine site conditions by visual inspection, plans, discussion with land owners and information from service utilities

2.3 Located underground utilities

2.4 Maintain system serviceability during rehabilitation works

2.5 Survey and record existing site conditions

3. Initiate rehabilitation work

3.1 Prepare entry and exit pits where specified

3.2 Identify, interpret and apply confined space entry procedures

3.3 Monitor installation process and finished product to ensure conformity to the design requirements

4. Complete cure in-place lining

4.1 Determine fault with the aid of plans, drawings, CCTV recordings or other mechanisms

4.2 Select resin impregnated liners appropriate to the fault

4.3 Apply pressure cleaning to the designated location

4.4 Install cure in-place lining material

4.5 Conduct curing process

4.6 Correctly secure and seal termination at ends of process

4.7 Open junctions for inspection and operation

4.8 Monitor installation process and finished product to ensure conformity to the design requirements

5. Clean up

5.1 Clear work area and dispose of, reuse or recycle materials

5.2 Clean, check, maintain and store plant, tools and equipment

Evidence is required to be collected that demonstrates a candidate’s competency in this unit. Evidence must be relevant to the roles within this sector’s work operations and satisfy all of the requirements of the performance criteria of this unit and include evidence that the candidate:

locates and applies applicable documentation, policies and procedures

implements the requirements, procedures and techniques for the safe, effective and efficient installing of cure in-place linings for existing pipeline systems including:

selecting and using the required tools and equipment

determining site conditions and locating underground utilities

preparing exit and entry pits

undertaking confined space entry

identifying and selecting resin impregnated liners

monitoring installation process and the finished product

works effectively with others to undertake and complete the installation of cure in-place linings for existing pipeline systems that meets all of the required outcomes including:

using a range of communication techniques and equipment to convey information to others

maintaining written and verbal reporting requirements and procedures

organising work activities to meet all task requirements

demonstrates completion of installing cure in-place linings for existing pipeline systems that safely, effectively and efficiently meets all of the required outcomes on more than one (1) occasion including:

completing a minimum of two (2) cure in-place linings for existing pipeline systems

identifying, obtaining, confirming and applying work, safety and signage instructions and requirements

cleaning, checking, maintaining and storing plant, tools and equipment

The candidate must demonstrate knowledge in installing cure in-place linings for existing pipeline systems through:

organisation and site requirements and procedures for:

work health and safety

operating equipment

confined space entry

operations, maintenance and basic diagnostics

project quality management

installing cure in-place linings

laser control equipment techniques

manual handling techniques

remote units

engineering drawings, plans and specifications

equipment types, characteristics, technical capabilities and limitations

site isolation and traffic control responsibilities

safety data sheets and materials handling methods

pipeline systems

civil construction terminology