The important thing to remember when gathering evidence is that the more evidence the better - that is, the more evidence you gather to demonstrate your skills, the more confident an assessor can be that you have learned the skills not just at one point in time, but are continuing to apply and develop those skills (as opposed to just learning for the test!). Furthermore, one piece of evidence that you collect will not usualy demonstrate all the required criteria for a unit of competency, whereas multiple overlapping pieces of evidence will usually do the trick!

From the Wiki University

 

RIIWMG203D - Drain and dewater civil construction site

What evidence can you provide to prove your understanding of each of the following citeria?

Plan and prepare for draining and dewatering

  1. Access, interpret and apply drain and dewatering documentation and ensure the work activity is compliant
  2. Obtain, read, interpret, clarify and confirm work requirements
  3. Identify, obtain and implement traffic signage requirements
  4. Select and inspect required plant, tools and equipment and rectify/report any faults
  5. Identify, clarify and apply environmental protection requirements
  6. Identify and address potential risks, hazards and environmental issues, and implement control measures
  7. Select and wear personal protective equipment appropriate for work activities
Access, interpret and apply drain and dewatering documentation and ensure the work activity is compliant

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Obtain, read, interpret, clarify and confirm work requirements

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Identify, obtain and implement traffic signage requirements

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Select and inspect required plant, tools and equipment and rectify/report any faults

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Identify, clarify and apply environmental protection requirements

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Identify and address potential risks, hazards and environmental issues, and implement control measures

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Select and wear personal protective equipment appropriate for work activities

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Position sedimentation control

  1. Position sedimentation controls
  2. Construct sedimentation control barriers
  3. Position geo-fabrics and/or woven wire
Position sedimentation controls

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Construct sedimentation control barriers

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Position geo-fabrics and/or woven wire

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Remove surface water

  1. Establish temporary drainage systems and drain or divert surface and sub-surface water to the storm water drainage system
  2. Remove slab and site surface water and/or direct to the temporary drainage system
  3. Fill surface holes and depressions
  4. Drain surface water to drainage system using adequate fall
Establish temporary drainage systems and drain or divert surface and sub-surface water to the storm water drainage system

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Remove slab and site surface water and/or direct to the temporary drainage system

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Fill surface holes and depressions

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Drain surface water to drainage system using adequate fall

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Construct sump/wells

  1. Locate sump and/or well at the lowest point to be drained
  2. Construct sumps and/or wells
Locate sump and/or well at the lowest point to be drained

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Construct sumps and/or wells

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Remove water from sumps/wells, trenches and pits

  1. Install surface or submersible pumps
  2. Locate surface pump as close as practicable to the sump or well
  3. Pump water to temporary drainage system
  4. Disperse discharged water
Install surface or submersible pumps

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Locate surface pump as close as practicable to the sump or well

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Pump water to temporary drainage system

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Disperse discharged water

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Clean up

  1. Clear work area and dispose of or recycle materials
  2. Clean, check, maintain and store plant, tools and equipment
Clear work area and dispose of or recycle materials

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Clean, check, maintain and store plant, tools and equipment

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Plan and prepare for draining and dewatering

  1. Access, interpret and apply drain and dewatering documentation and ensure the work activity is compliant
  2. Obtain, read, interpret, clarify and confirm work requirements
  3. Identify, obtain and implement traffic signage requirements
  4. Select and inspect required plant, tools and equipment and rectify/report any faults
  5. Identify, clarify and apply environmental protection requirements
  6. Identify and address potential risks, hazards and environmental issues, and implement control measures
  7. Select and wear personal protective equipment appropriate for work activities
Access, interpret and apply drain and dewatering documentation and ensure the work activity is compliant

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Obtain, read, interpret, clarify and confirm work requirements

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Identify, obtain and implement traffic signage requirements

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Select and inspect required plant, tools and equipment and rectify/report any faults

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Identify, clarify and apply environmental protection requirements

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Identify and address potential risks, hazards and environmental issues, and implement control measures

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Select and wear personal protective equipment appropriate for work activities

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Position sedimentation control

  1. Position sedimentation controls
  2. Construct sedimentation control barriers
  3. Position geo-fabrics and/or woven wire
Position sedimentation controls

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Construct sedimentation control barriers

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Position geo-fabrics and/or woven wire

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Remove surface water

  1. Establish temporary drainage systems and drain or divert surface and sub-surface water to the storm water drainage system
  2. Remove slab and site surface water and/or direct to the temporary drainage system
  3. Fill surface holes and depressions
  4. Drain surface water to drainage system using adequate fall
Establish temporary drainage systems and drain or divert surface and sub-surface water to the storm water drainage system

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Remove slab and site surface water and/or direct to the temporary drainage system

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Fill surface holes and depressions

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Drain surface water to drainage system using adequate fall

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Construct sump/wells

  1. Locate sump and/or well at the lowest point to be drained
  2. Construct sumps and/or wells
Locate sump and/or well at the lowest point to be drained

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Construct sumps and/or wells

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Remove water from sumps/wells, trenches and pits

  1. Install surface or submersible pumps
  2. Locate surface pump as close as practicable to the sump or well
  3. Pump water to temporary drainage system
  4. Disperse discharged water
  5. Clear work area and dispose of or recycle materials
  6. Clean, check, maintain and store plant, tools and equipment
Install surface or submersible pumps

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Locate surface pump as close as practicable to the sump or well

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Pump water to temporary drainage system

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Disperse discharged water

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Clear work area and dispose of or recycle materials

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Clean, check, maintain and store plant, tools and equipment

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Assessed

Teacher: ___________________________________ Date: _________

Signature: ________________________________________________

Comments:

 

 

 

 

 

 

 

 

Instructions to Assessors

Evidence Guide

1. Plan and prepare for draining and dewatering

1.1 Access, interpret and apply drain and dewatering documentation and ensure the work activity is compliant

1.2 Obtain, read, interpret, clarify and confirm work requirements

1.3 Identify, obtain and implement traffic signage requirements

1.4 Select and inspect required plant, tools and equipment and rectify/report any faults

1.5 Identify, clarify and apply environmental protection requirements

1.6 Identify and address potential risks, hazards and environmental issues, and implement control measures

1.7 Select and wear personal protective equipment appropriate for work activities

2. Position sedimentation control

2.1 Position sedimentation controls

2.2 Construct sedimentation control barriers

2.3 Position geo-fabrics and/or woven wire

3. Remove surface water

3.1 Establish temporary drainage systems and drain or divert surface and sub-surface water to the storm water drainage system

3.2 Remove slab and site surface water and/or direct to the temporary drainage system

3.3 Fill surface holes and depressions

3.4 Drain surface water to drainage system using adequate fall

4. Construct sump/wells

4.1 Locate sump and/or well at the lowest point to be drained

4.2 Construct sumps and/or wells

5. Remove water from sumps/wells, trenches and pits

5.1 Install surface or submersible pumps

5.2 Locate surface pump as close as practicable to the sump or well

5.3 Pump water to temporary drainage system

5.4 Disperse discharged water

6. Clean up

6.1 Clear work area and dispose of or recycle materials

6.2 Clean, check, maintain and store plant, tools and equipment

Required Skills and Knowledge

1. Plan and prepare for draining and dewatering

1.1 Access, interpret and apply drain and dewatering documentation and ensure the work activity is compliant

1.2 Obtain, read, interpret, clarify and confirm work requirements

1.3 Identify, obtain and implement traffic signage requirements

1.4 Select and inspect required plant, tools and equipment and rectify/report any faults

1.5 Identify, clarify and apply environmental protection requirements

1.6 Identify and address potential risks, hazards and environmental issues, and implement control measures

1.7 Select and wear personal protective equipment appropriate for work activities

2. Position sedimentation control

2.1 Position sedimentation controls

2.2 Construct sedimentation control barriers

2.3 Position geo-fabrics and/or woven wire

3. Remove surface water

3.1 Establish temporary drainage systems and drain or divert surface and sub-surface water to the storm water drainage system

3.2 Remove slab and site surface water and/or direct to the temporary drainage system

3.3 Fill surface holes and depressions

3.4 Drain surface water to drainage system using adequate fall

4. Construct sump/wells

4.1 Locate sump and/or well at the lowest point to be drained

4.2 Construct sumps and/or wells

5. Remove water from sumps/wells, trenches and pits

5.1 Install surface or submersible pumps

5.2 Locate surface pump as close as practicable to the sump or well

5.3 Pump water to temporary drainage system

5.4 Disperse discharged water

6. Clean up

6.1 Clear work area and dispose of or recycle materials

6.2 Clean, check, maintain and store plant, tools and equipment