The important thing to remember when gathering evidence is that the more evidence the better - that is, the more evidence you gather to demonstrate your skills, the more confident an assessor can be that you have learned the skills not just at one point in time, but are continuing to apply and develop those skills (as opposed to just learning for the test!). Furthermore, one piece of evidence that you collect will not usualy demonstrate all the required criteria for a unit of competency, whereas multiple overlapping pieces of evidence will usually do the trick!
From the Wiki University
What evidence can you provide to prove your understanding of each of the following citeria?
Plan and prepare
|
|
Access, interpret and apply compliance documentation relevant to construction site water table drainage and dewatering systems Completed |
Evidence:
|
Obtain, confirm and apply work instructions to the allotted task Completed |
Evidence:
|
Obtain, confirm and apply safety requirements to the allotted task Completed |
Evidence:
|
Identify, obtain and implement signage requirements from the project traffic management plan Completed |
Evidence:
|
Select plant, tools and equipment to carry out tasks that are consistent with the requirements of the job, and check them for serviceability and rectify or report any faults Completed |
Evidence:
|
Identify, confirm and apply environmental protection requirements from the project environmental management plan to the allotted task Completed |
Evidence:
|
Install site drainage/ dewatering system
|
|
Identify proposed permanent stormwater outlets from site plans and drawings Completed |
Evidence:
|
Erect barricades around the excavation/ installation area Completed |
Evidence:
|
Construct sumps and wells to specified levels and locations Completed |
Evidence:
|
Install well points, spears or wick drains to specified configuration and required depths Completed |
Evidence:
|
Place gravel and filter material in spears, sumps and wells to level above that of existing water table Completed |
Evidence:
|
Install surface or submersible pumps in designed locations to spears, sumps and wells Completed |
Evidence:
|
Connect suction hoses to sumps, wells, spears and pumps in accordance specifications and site designed drainage Completed |
Evidence:
|
Fit pipes and hoses to well points, spears and pumps in accordance with specifications and site designed drainage Completed |
Evidence:
|
Establish stormwater treatment system
|
|
Set out holding pond and support construction operations Completed |
Evidence:
|
Monitor and respond to water quality and treatment standards Completed |
Evidence:
|
Release water which meets the approved quality criteria into the main system Completed |
Evidence:
|
Operate and maintain drainage and dewatering system
|
|
Activate pumps to lower water table level to designed requirement Completed |
Evidence:
|
Maintain pumps Completed |
Evidence:
|
Maintain site drainage and dewatering system to maximise water flow to project requirements Completed |
Evidence:
|
Remove and make good
|
|
Disconnect and remove pumping system Completed |
Evidence:
|
Withdraw and remove well points and spears Completed |
Evidence:
|
Restore area to environmental management plan Completed |
Evidence:
|
Clean up
|
|
Clear work area and dispose of or recycle materials in accordance with project environmental management plan Completed |
Evidence:
|
Clean, check, maintain and store plant, tools and equipment Completed |
Evidence:
|