The important thing to remember when gathering evidence is that the more evidence the better - that is, the more evidence you gather to demonstrate your skills, the more confident an assessor can be that you have learned the skills not just at one point in time, but are continuing to apply and develop those skills (as opposed to just learning for the test!). Furthermore, one piece of evidence that you collect will not usualy demonstrate all the required criteria for a unit of competency, whereas multiple overlapping pieces of evidence will usually do the trick!
From the Wiki University
What evidence can you provide to prove your understanding of each of the following citeria?
Plan electrical installation
|
|
Work health and safety (WHS)/occupational health and safety (OHS) risk control measures and workplace procedures for carrying out work are followed Completed |
Evidence:
|
Nature of the electrical installation is determined from job specifications |
|
Completed |
Evidence:
|
Safety and regulatory requirements for electrical installation are identified, obtained and applied in accordance with relevant industry standards and safe work practices |
|
Completed |
Evidence:
|
Electricity tariffs required are discussed with appropriate person/s to determine control and metering needs of the installation |
|
Completed |
Evidence:
|
Arrange installation circuits, control and metering
|
|
Circuits are arranged to ensure safe and functional operation of the installation in accordance with relevant industry standards Completed |
Evidence:
|
Circuits are arranged in accordance with relevant industry standards and job specifications |
|
Completed |
Evidence:
|
Control and metering of the installation are arranged in accordance with relevant industry standards and job specifications |
|
Completed |
Evidence:
|
Earthing is arranged in accordance with relevant industry standards and energy supplier requirements |
|
Completed |
Evidence:
|
Identify cables protection and switchgear
|
|
Fault levels at relevant point/s of the installation are determined from calculations and/or information from the energy supplier Completed |
Evidence:
|
Wiring systems selected are confirmed as meeting sustainable energy practices and job specifications |
|
Completed |
Evidence:
|
Cable conductor sizes are confirmed to meet current-carrying capacity requirements and voltage-drop and fault-loop impedance limitations and short circuit performance |
|
Completed |
Evidence:
|
Protection methods and devices are identified to meet coordination requirements for overload and short circuit protection |
|
Completed |
Evidence:
|
Switchgear and control gear are identified to meet fault levels, current voltage and ingress protection (IP) ratings and functional requirements |
|
Completed |
Evidence:
|
Earthing system components are identified to meet requirements of the earthing system used |
|
Completed |
Evidence:
|
Evidence is obtained that electrical equipment selected is in accordance with WHS/OHS and safe work practices |
|
Completed |
Evidence:
|
Document electrical installation plan
|
|
Equipment identified for the installation is documented with supporting calculations in accordance with workplace procedures Completed |
Evidence:
|
Electrical installation is documented in accordance with workplace procedures and forwarded to relevant person/s |
|
Completed |
Evidence:
|