Tips for gathering evidence to demonstrate your skills

The important thing to remember when gathering evidence is that the more evidence the better - that is, the more evidence you gather to demonstrate your skills, the more confident an assessor can be that you have learned the skills not just at one point in time, but are continuing to apply and develop those skills (as opposed to just learning for the test!). Furthermore, one piece of evidence that you collect will not usualy demonstrate all the required criteria for a unit of competency, whereas multiple overlapping pieces of evidence will usually do the trick!

From the Wiki University

 

UEENEEG025B - Plan electrical installations with a LV demand up to 400 A per phase

What evidence can you provide to prove your understanding of each of the following citeria?

Prepare to plan electrical installations.

  1. OHS risk control measures and procedures for carrying out the work are followed.
  2. The extent and nature of the electrical installation is determined from job specifications.
  3. Safety and other regulatory requirements to which the electrical installation shall comply are identified, obtained and understood.
  4. Electricity tariffs required are discussed with appropriate person(s) to ascertain control and metering needs of the installation.
OHS risk control measures and procedures for carrying out the work are followed.

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

The extent and nature of the electrical installation is determined from job specifications.

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Safety and other regulatory requirements to which the electrical installation shall comply are identified, obtained and understood.

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Electricity tariffs required are discussed with appropriate person(s) to ascertain control and metering needs of the installation.

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Arrange installation circuits, control and metering.

  1. Circuits are arranged to ensure safe and functional operation of the installation.
  2. Circuits are arranged to comply with technical standards and job specifications and requirements.
  3. Control and metering of the installation is arranged in accordance with regulatory and local requirements and consumer needs.
  4. Earthing is arranged to comply with the standards and local energy supplier's requirements.
Circuits are arranged to ensure safe and functional operation of the installation.

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Circuits are arranged to comply with technical standards and job specifications and requirements.

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Control and metering of the installation is arranged in accordance with regulatory and local requirements and consumer needs.

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Earthing is arranged to comply with the standards and local energy supplier's requirements.

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Specify cables, protection and switchgear.

  1. Fault levels at each relevant point of the installation are determined from calculations and/or information from the local energy supplier's.
  2. Suitability of the wiring systems selected is determined to meet requirements for protection against environmental factors and job specifications.
  3. Cable conductor sizes are determined to meet current-carrying capacity requirements and voltage-drop and fault-loop impedance limitations and short circuit performance.
  4. Protection methods and devices are specified to meet co-ordination requirements for overload and short-circuit protection.
  5. Switchgear and control gear are specified to meet fault levels, current, voltage and IP ratings and functional requirements.
  6. Earthing system components are specified to meet requirements of the earthing system used.
  7. Evidence is obtained that electrical equipment selected complies with safety requirements.
Fault levels at each relevant point of the installation are determined from calculations and/or information from the local energy supplier's.

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Suitability of the wiring systems selected is determined to meet requirements for protection against environmental factors and job specifications.

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Cable conductor sizes are determined to meet current-carrying capacity requirements and voltage-drop and fault-loop impedance limitations and short circuit performance.

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Protection methods and devices are specified to meet co-ordination requirements for overload and short-circuit protection.

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Switchgear and control gear are specified to meet fault levels, current, voltage and IP ratings and functional requirements.

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Earthing system components are specified to meet requirements of the earthing system used.

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Evidence is obtained that electrical equipment selected complies with safety requirements.

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Document electrical installation plan.

  1. Equipment specified for the installation is documented together with supporting calculations in accordance with established procedures.
  2. Electrical installation arrangement, equipment locations, cable routes and schedules and requirements are documented in accordance with established procedures and forwarded to appropriate person(s).
Equipment specified for the installation is documented together with supporting calculations in accordance with established procedures.

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Electrical installation arrangement, equipment locations, cable routes and schedules and requirements are documented in accordance with established procedures and forwarded to appropriate person(s).

Completed
Date:

Teacher:
Evidence:

 

 

 

 

 

 

 

Assessed

Teacher: ___________________________________ Date: _________

Signature: ________________________________________________

Comments:

 

 

 

 

 

 

 

 

Instructions to Assessors

Evidence Guide

9) The evidence guide provides advice on assessment and must be read in conjunction with the Performance Criteria, Required Skills and Knowledge, the Range Statement and the Assessment Guidelines for this Training Package.

The Evidence Guide forms an integral part of this unit. It must be used in conjunction with all parts of this unit and performed in accordance with the Assessment Guidelines of this Training Package.

Overview of Assessment

9.1)

Longitudinal competency development approaches to assessment, such as Profiling, require data to be reliably gathered in a form that can be consistently interpreted over time. This approach is best utilised in Apprenticeship programs and reduces assessment intervention. It is the Industry's preferred model for apprenticeships. However, where summative (or final) assessment is used it is to include the application of the competency in the normal work environment or, at a minimum, the application of the competency in a realistically simulated work environment. It is recognised that, in some circumstances, assessment in part or full can occur outside the workplace. However, it must be in accordance with industry and regulatory policy.

Methods chosen for a particular assessment will be influenced by various factors. These include the extent of the assessment, the most effective locations for the assessment activities to take place, access to physical resources, additional safety measures that may be required and the critical nature of the competencies being assessed.

The critical safety nature of working with electricity, electrical equipment, gas or any other hazardous substance/material carries risk in deeming a person competent. Sources of evidence need to be 'rich' in nature to minimise error in judgment.

Activities associated with normal every day work have a bearing on the decision as to how much and how detailed the data gathered will contribute to its 'richness'. Some skills are more critical to safety and operational requirements while the same skills may be more or less frequently practised. These points are raised for the assessors to consider when choosing an assessment method and developing assessment instruments. Sample assessment instruments are included for Assessors in the Assessment Guidelines of this Training Package.

Critical aspects of evidence required to demonstrate competency in this unit

9.2)

Before the critical aspects of evidence are considered all prerequisites shall be met.

Evidence for competence in this unit shall be considered holistically. Each element and associated performance criteria shall be demonstrated on at least two occasions in accordance with the 'Assessment Guidelines - UEE07'. Evidence shall also comprise:

A representative body of work performance demonstrated within the timeframes typically expected of the discipline, work function and industrial environment. In particular this shall incorporate evidence that shows a candidate is able to:

Implement Occupational Health and Safety workplace procedures and practices including the use of risk control measures as specified in the performance criteria and range statement

Apply sustainable energy principles and practices as specified in the performance criteria and range statement

Demonstrate an understanding of the essential knowledge and associated skills as described in this unit . It may be required by some jurisdictions that RTOs provide a percentile graded result for the purpose of regulatory or licensing requirements.

Demonstrate an appropriate level of skills enabling employment

Conduct work observing the relevant Anti Discrimination legislation, regulations, polices and workplace procedures

Demonstrated consistent performance across a representative range of contexts from the prescribed items below:

Plan electrical installations with a LV demand up to 400A per phase as described in 8) and including:

A

Arranging electrical installations to comply with control, metering, safety and other regulatory and functional requirements.

B

Specifying appropriate type and size of cables.

C

Specifying protection methods and devices that meet co-ordination requirements for overload and short-circuit protection.

D

Specifying switchgear and control gear that meet fault level, current, voltage and IP ratings and functional requirements.

E

Selecting appropriate earthing system components.

F

Documenting installation plan, specifications of equipment, equipment locations, cable routes and schedules and supporting calculations.

G

Arranging electrical installations to comply with control, metering, safety and other regulatory and functional requirements.

Context of and specific resources for assessment

9.3)

This unit should be assessed as it relates to normal work practice using procedures, information and resources typical of a workplace. This should include:

OHS policy and work procedures and instructions.

Suitable work environment, facilities, equipment and materials to undertake actual work as prescribed by this unit.

These should be part of the formal learning/assessment environment.

Note:

Where simulation is considered a suitable strategy for assessment, conditions must be authentic and as far as possible reproduce and replicate the workplace and be consistent with the approved industry simulation policy.

The resources used for assessment should reflect current industry practices in relation to planning electrical installations with a LV demand up to 400A per phase.

Method of assessment

9.4)

This unit shall be assessed by methods given in Volume 1, Part 3 'Assessment Guidelines'.

Note:
Competent performance with inherent safe working practices is expected in the industry to which this unit applies. This requires assessment in a structured environment which is primarily intended for learning/assessment and incorporates all necessary equipment and facilities for learners to develop and demonstrate the essential knowledge and skills described in this unit.

Concurrent assessment and relationship with other units

9.5)

For optimisation of training and assessment effort, competency development in this unit may be arranged concurrently with unit:

UEENEED001B

Use basic computer applications relevant to a workplace

Required Skills and Knowledge

7) This describes the essential skills and knowledge and their level, required for this unit.

Evidence shall show that knowledge has been acquired of safe working practices and planning electrical installations with a LV demand up to 400A per phase.

All knowledge and skills detailed in this unit should be contextualised to current industry practices and technologies.

The extent of the essential knowledge and associated skills (EKAS) required is given in Volume 2 - Part 2.2 EKAS. It forms an integral part of this unit.

2.6.2.2

Electrical metering arrangements

Range Statement

8) This relates to the unit as a whole providing the range of contexts and conditions to which the performance criteria apply. It allows for different work environments and situations that will affect performance.

This unit shall be demonstrated in relation to planning electrical installations with a LV demand up to 400A per phase. The installation shall comprise a main switchboard CT metering, multiple tariffs or tenants, distribution boards single and three phase final sub circuits.

The electrical installations shall comprise consumers' mains, main earthing system and main switchboard and sub-mains, earthing system and distribution boards, final sub circuits and requirement particular to the installation type.

Generic terms used throughout this Vocational Standard shall be regarded as part of the Range Statement in which competency is demonstrated. The definition of these and other terms that apply are given in Volume 2, Part 2.1.