The important thing to remember when gathering evidence is that the more evidence the better - that is, the more evidence you gather to demonstrate your skills, the more confident an assessor can be that you have learned the skills not just at one point in time, but are continuing to apply and develop those skills (as opposed to just learning for the test!). Furthermore, one piece of evidence that you collect will not usualy demonstrate all the required criteria for a unit of competency, whereas multiple overlapping pieces of evidence will usually do the trick!
From the Wiki University
What evidence can you provide to prove your understanding of each of the following citeria?
Plan and prepare to coordinate pipeline installation
|
|
Alignment of gas main and associated equipment is confirmed and location of other services verified against work schedule(s) and established procedures and confirmed if necessary by site inspection Completed |
Evidence:
|
Relevant requirements and established procedures for the work are communicated to all persons and identified for all work sites Completed |
Evidence:
|
OHS, environmental and sustainable energy policies and procedures related to the coordination of construction, laying and testing of gas distribution pipelines are obtained and confirmed for the purposes of the work performed and communicated Completed |
Evidence:
|
Appropriate persons are consulted to ensure the work plan is coordinated and that work is prioritised and sequenced following consultation with others for completion within acceptable timeframes and in accordance with established procedures Completed |
Evidence:
|
Risk control measures for identified hazards are implemented, prioritised and monitored against the work schedule Completed |
Evidence:
|
Relevant work permits are obtained to access, isolate/de-energise systems and perform work according to requirements and established procedures Completed |
Evidence:
|
Resources including persons, equipment, tools and personal protective equipment required for the job are identified, scheduled and obtained and confirmed in working order Completed |
Evidence:
|
Relevant persons at worksite are confirmed to be current in in First Aid and other related work procedures according to requirements Completed |
Evidence:
|
Liaison and communication with authorised persons, authorities, clients and land-owners is completed so work can be carried out where necessary Completed |
Evidence:
|
Site is prepared according to the work schedule and to minimise risk and damage to property, commerce and individuals in accordance with established procedures Completed |
Evidence:
|
Persons participating in the work, including plant operators and contractors are fully briefed and respective responsibilities confirmed where applicable in accordance with established procedures Completed |
Evidence:
|
Road signs, barriers and warning devices are positioned in accordance with requirements including traffic management plans Completed |
Evidence:
|
Coordinate construction, laying and insertion of pipelines and associated equipment and test pipeline for conformance to specifications
|
|
OHS policies and procedures and safe work practices are followed to eliminate or minimise incidents and hazards Completed |
Evidence:
|
Lifting, climbing, working in confined spaces, excavations, trenches, or aloft, and use of power tools, techniques and practices are safely followed and currency according to requirements confirmed Completed |
Evidence:
|
Essential Knowledge and Associated Skills for the coordination of construction, laying and testing of gas distribution pipelines are applied to ensure completion in an agreed timeframe and to quality standards with a minimum of waste according to requirements Completed |
Evidence:
|
Performing the coordination of construction, laying and testing of gas distribution pipelines is carried out in accordance with the work schedule and to established procedures Completed |
Evidence:
|
Hazard warnings and safety signs are recognised and hazards are assessed and OHS risks are reported to the authorised persons for directions according to established procedures Completed |
Evidence:
|
Unplanned events in the coordination of construction, laying and testing of gas distribution pipelines is undertaken within the scope of established procedures Completed |
Evidence:
|
Known solutions to a variety of problems are applied using acquired Essential Knowledge and Associated Skills Completed |
Evidence:
|
Ongoing checks of work quality are undertaken in accordance with given instructions and established procedures Completed |
Evidence:
|
Complete the coordination of construction, laying and testing of gas distribution pipelines
|
|
Final inspection are undertaken to ensure the construction, laying and testing conforms to requirements and anomalies reported in accordance with established procedures Completed |
Evidence:
|
Accidents and injuries are reported in accordance with established procedures where applicable Completed |
Evidence:
|
Work site is rehabilitated, cleaned up and made safe in accordance with given instructions and established procedures Completed |
Evidence:
|
Tools, equipment and any surplus resources and materials are, where appropriate, cleaned, checked and returned to storage in accordance with established procedures Completed |
Evidence:
|
Relevant work permit(s) are signed off and equipment is returned to service in accordance with requirements Completed |
Evidence:
|
Work completion records, reports and information are finalised and processed and appropriate persons notified Completed |
Evidence:
|