Undertake basic rigging

Formats and tools

Unit Description
Reconstruct the unit from the xml and display it as an HTML page.
Assessment Tool
an assessor resource that builds a framework for writing an assessment tool
Assessment Template
generate a spreadsheet for marking this unit in a classroom environment. Put student names in the top row and check them off as they demonstrate competenece for each of the unit's elements and performance criteria.
Assessment Matrix
a slightly different format than the assessment template. A spreadsheet with unit names, elements and performance criteria in separate columns. Put assessment names in column headings to track which performance criteria each one covers. Good for ensuring that you've covered every one of the performance criteria with your assessment instrument (all assessement tools together).
Wiki Markup
mark up the unit in a wiki markup codes, ready to copy and paste into a wiki page. The output will work in most wikis but is designed to work particularly well as a Wikiversity learning project.
Evidence Guide
create an evidence guide for workplace assessment and RPL applicants
Competency Mapping Template
Unit of Competency Mapping – Information for Teachers/Assessors – Information for Learners. A template for developing assessments for a unit, which will help you to create valid, fair and reliable assessments for the unit, ready to give to trainers and students
Observation Checklist
create an observation checklist for workplace assessment and RPL applicants. This is similar to the evidence guide above, but a little shorter and friendlier on your printer. You will also need to create a seperate Assessor Marking Guide for guidelines on gathering evidence and a list of key points for each activity observed using the unit's range statement, required skills and evidence required (see the unit's html page for details)

Self Assessment Survey
A form for students to assess thier current skill levels against each of the unit's performance criteria. Cut and paste into a web document or print and distribute in hard copy.
Moodle Outcomes
Create a csv file of the unit's performance criteria to import into a moodle course as outcomes, ready to associate with each of your assignments. Here's a quick 'how to' for importing these into moodle 2.x
Registered Training Organisations
Trying to find someone to train or assess you? This link lists all the RTOs that are currently registered to deliver MEM11024A, 'Undertake basic rigging'.
Google Links
links to google searches, with filtering in place to maximise the usefulness of the returned results
Books
Reference books for 'Undertake basic rigging' on fishpond.com.au. This online store has a huge range of books, pretty reasonable prices, free delivery in Australia *and* they give a small commission to ntisthis.com for every purchase, so go nuts :)


Elements and Performance Criteria

1

Assess rigging site

1.1

Rigging to be undertaken is identified and assessed from supervisor’s instructions, drawings and other appropriate sources

1.2

Equipment and processes in close proximity to rigging site are identified and need for protection, shielding or closure during rigging identified with appropriate personnel

1.3

Other potential workplace hazards and appropriate hazard control measures are identified

1.4

Site information is obtained

1.5

Rigging equipment and associated equipment, including safety equipment available on site, is identified

2

Plan rigging work

2.1

All forces and loads associated with erecting and dismantling structures and associated equipment are considered in consultation with appropriate personnel

2.2

Required safety equipment for rigging task is identified

2.3

Procedures for minimising disruption to other site processes are considered

2.4

Appropriate communication methods are identified with appropriate personnel

3

Select and inspect equipment

3.1

Rigging equipment and associated equipment is selected and inspected according to procedures and the appropriate standard

3.2

Required safety equipment is selected and inspected according to procedures

3.3

All defective rigging equipment, associated equipment and safety equipment is isolated, reported and recorded according to procedures

3.4

Where applicable, communication equipment is selected and inspected for serviceability

4

Set up rigging task

4.1

Appropriate hazard prevention or control measures are applied to the work area according to procedures

4.2

Ground suitability is inspected and checked where appropriate

4.3

Site information is reviewed and interpreted with appropriate personnel

4.4

All forces and loads associated with erecting and dismantling structures and associated plant are determined and compared with planned forces and loads in consultation with appropriate personnel

4.5

Required adjustments for actual forces and loads are made to rigging plan, rigging equipment, associated equipment and safety equipment

4.6

Personal safety equipment is fitted and worn correctly

4.7

Rigging equipment and associated plant are positioned for work application and stability according to procedures

4.8

Methods of applying temporary connections using fibre rope are applied according to procedures and the appropriate standard

5

Erect, move or dismantle structures, plant or equipment

5.1

Structures, plant or equipment are erected, moved or dismantled according to procedures and site information

5.2

Stability of structures, plant or equipment is maintained during erection, movement or dismantling

5.3

Where height work is required, safety procedures are followed, including safe and effective use of safety equipment

5.4

Appropriate communication methods and communication equipment are used to coordinate the rigging tasks

5.5

Associated plant and equipment are used according to procedures and the appropriate standard

5.6

Temporary guys, ties, propping and shoring, including flexible steel wire rope and tubing, are connected where required

5.7

Procedures are followed to minimise disruption to other site operations

5.8

The completed task is inspected according to the appropriate standard

6

Finalise rigging task

6.1

Approval for completion of rigging task is obtained according to site or enterprise procedures

6.2

Excess materials are removed from the work area, where applicable

6.3

Rigging equipment, associated equipment, safety equipment and associated plant used during rigging task are inspected for damage and defects

6.4

All defective rigging equipment, associated equipment, associated plant and safety equipment are isolated reported and recorded according to procedures

6.5

Rigging equipment and associated equipment are stored according to procedures and the appropriate standard

6.6

Hazard prevention/control measures are removed, where appropriate


Qualifications and Skillsets

MEM11024A appears in the following qualifications:

  • MEM20205 - Certificate II in Engineering - Production Technology
  • MEM20205 - Certificate II in Engineering - Production Technology
  • MEM20205 - Certificate II in Engineering - Production Technology