Unit Description
Reconstruct the unit from the xml and display it as an HTML page.
Assessment Tool
an assessor resource that builds a framework for writing an assessment tool
Assessment Template
generate a spreadsheet for marking this unit in a classroom environment. Put student names in the top row and check them off as they demonstrate competenece for each of the unit's elements and performance criteria.
Assessment Matrix
a slightly different format than the assessment template. A spreadsheet with unit names, elements and performance criteria in separate columns. Put assessment names in column headings to track which performance criteria each one covers. Good for ensuring that you've covered every one of the performance criteria with your assessment instrument (all assessement tools together).
Wiki Markup
mark up the unit in a wiki markup codes, ready to copy and paste into a wiki page. The output will work in most wikis but is designed to work particularly well as a Wikiversity learning project.
Evidence Guide
create an evidence guide for workplace assessment and RPL applicants
Competency Mapping Template
Unit of Competency Mapping – Information for Teachers/Assessors – Information for Learners. A template for developing assessments for a unit, which will help you to create valid, fair and reliable assessments for the unit, ready to give to trainers and students
Observation Checklist
create an observation checklist for workplace assessment and RPL applicants. This is similar to the evidence guide above, but a little shorter and friendlier on your printer. You will also need to create a seperate Assessor Marking Guide for guidelines on gathering evidence and a list of key points for each activity observed using the unit's range statement, required skills and evidence required (see the unit's html page for details)

Self Assessment Survey
A form for students to assess thier current skill levels against each of the unit's performance criteria. Cut and paste into a web document or print and distribute in hard copy.
Moodle Outcomes
Create a csv file of the unit's performance criteria to import into a moodle course as outcomes, ready to associate with each of your assignments. Here's a quick 'how to' for importing these into moodle 2.x
Registered Training Organisations
Trying to find someone to train or assess you? This link lists all the RTOs that are currently registered to deliver MSMBIO301, 'Process biomass using pyrolyser'.
Google Links
links to google searches, with filtering in place to maximise the usefulness of the returned results
Books
Reference books for 'Process biomass using pyrolyser' on fishpond.com.au. This online store has a huge range of books, pretty reasonable prices, free delivery in Australia *and* they give a small commission to ntisthis.com for every purchase, so go nuts :)


Elements and Performance Criteria

Elements

Performance Criteria

Elements describe the essential outcomes.

Performance criteria describe the performance needed to demonstrate achievement of the element.

1. Prepare for work

1.1 Identify and follow work and safety requirements

1.2 Identify and control hazards

1.3 Check operational status of pyrolyser

1.4 Complete required pre-start checks

1.5 Start up pyrolyser and ancillary equipment in accordance with standard operating procedures

2. Maintain production

2.1 Complete routine checks, logs and paperwork taking appropriate action on unexpected readings

2.2 Check biomass is pre-treated and dried for pyrolyser requirements for production

2.3 Check particle size of biomass is correct for pyrolyser requirements for production

2.4 Feed biomass feedstock into pyrolyser in accordance with standard operating procedures

2.5 Monitor and adjust feed to maintain consistent and stable feed conditions for production

2.6 Monitor additives in accordance with production requirements

2.7 Operate pyrolyser to maintain continuity and production through-put

3. Monitor pyrolyser

3.1 Monitor pyrolyser throughout process

3.2 Identify and act on changes upstream and downstream impacting on process

3.3 Resolve routine problems and maintain safe operating environment

3.4 Shut down pyrolyser in an emergency

3.5 Identify and rectify impact of shut down on process and production

4. Isolate and de-isolate pyrolyser

4.1 Shut down pyrolyser and ancillary equipment in accordance with standard operating procedures

4.2 Isolate pyrolyser and components

4.3 Make safe for required work

4.4 Check pyrolyser is ready to be returned to service

4.5 De-isolate and prepare pyrolyser and components for return to service